Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Taylorsville Network Projects Completed Since 2017

July, 2023 by Granite Schools

Arcadia Elementary:

A freezer/cooler was added. The front office security project was completed. Carbon monoxide detectors were installed. The domestic water pipping was replaced. A partial re-roof project occurred. A special education relocation project was completed.

Bennion Elementary:

The fire alarm system was upgraded. The front office security remodel was completed. The HAVC air flow was upgraded. Some student drop-off modifications were completed.

Calvin Smith Elementary:

The front office security remodel was completed. The fire alarm was upgraded. The irrigation for the play fields was automated. An interior facelift happened. The HVAC controls were upgraded.

Fox Hills Elementary:

An interior facelift occurred. The front office security was completed. Carbon Monoxide detectors were installed. Playground turf was installed under the play structures. The air conditioning system was upgraded. A pedestrian bridge was added with associated site improvements. The HVAC controls were upgraded.

Fremont Elementary:

The front office security project was completed with an addition. Carbon Monoxide detectors were installed. The concrete columns under the school were shored up.

Taylorsville Elementary:

Kitchen and associated cooler box addition was completed. New in-wall cafeteria tables were added. Computer room change occurred.

Truman Elementary:

The front office security project was completed. The furnace and condenser were replaced. The HVAC system was upgraded.

Vista Elementary:

New in-wall cafeteria tables were added. The front office security project was completed with an addition. Carbon Monoxide detectors were installed. The irrigation for the play fields was automated.

Eisenhower Jr.:

The domestic water piping was redone. The auditorium audio system needed to be upgraded with a new system. New single-occupancy changing rooms were added. The south exterior wall was cleaned up so waterproofing could be applied the concrete wall. 

Bennion Jr.: 

The auditorium audio system was upgraded. The boiler was replaced. Significant earthquake repairs were performed. The fire panel was replaced for the fire alarm system and the HVAC controls were to be upgraded.

Taylorsville High:

The tennis courts were resurfaced and are being worked on again summer 2023. An auto shop lift was installed. Gymnasium bleachers were replaced. The softball home run fence was installed. The EPIC audio enhancement was installed. A main office remodel occurred. A new 16 room portable classroom unit was purchased and had all the necessary power, security, fire alarm and water/sewer connections. The baseball and softball dugouts were redone. A new chiller was purchased and installed. A new artificial turf replaced the old one. Four new relocatable classrooms have been installed. HVAC controls are being upgraded. Air conditioning addition to the main and auxiliary gymnasiums is underway.

Filed Under: Feature, Uncategorized

Status of Projects November 2022 – West Lake

November, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.

Gymnasium
Gymnasium
Academic wing
Academic wing
Interior framing in academic wing
Interior framing in academic wing
Exterior sheathing
Exterior sheathing
Stairs at south commons
Stairs at south commons
Stairs at south commons
Stairs at south commons
Preparation for paving of north parking lot –October 27
Preparation for paving of north parking lot –October 27
Library and teacher collaboration steel structure
Library and teacher collaboration steel structure
Roof decking and structural steel for sheer wall –southwest wing
Roof decking and structural steel for sheer wall –southwest wing
West elevation -gymnasium
West elevation -gymnasium
East elevation –gymnasium reaching top out height
East elevation –gymnasium reaching top out height

Filed Under: Project Updates, West Lake

Status of Projects November 2022 – Skyline High School

November, 2022 by Granite Schools

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – Cyprus

November, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls

Filed Under: Cyprus, Project Updates

Status of Projects October 2022 – West Lake

October, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.

Site overview
Site overview
Site overview
Site overview
Gymnasium masonry walls
Gymnasium masonry walls
Gymnasium and locker room masonry walls
Gymnasium and locker room masonry walls
Classroom floor decking
Classroom floor decking
Classroom floor decking
Classroom floor decking
FACS concrete slab
FACS concrete slab
Mechanical equipment
Mechanical equipment

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October, 2022 by Granite Schools

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.

Floor boxes for testing center
Floor boxes for testing center
Underground utilities
Underground utilities
Grading at softball field
Grading at softball field
Grading at tennis courts
Grading at tennis courts
Sod on practice field
Sod on practice field
Concrete pour and tilt panels being formed
Concrete pour and tilt panels being formed
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
West pool stairs graphic
West pool stairs graphic

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – West Lake

October, 2022 by Granite Schools

West Lake Junior High School STEM (Westbrook Campus): FACS Modular Building

Building is 100% complete.

Backordered furniture is shipping as available.

West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building

West Lake STEM Junior High School: Abatement / Demolition

Building abatement is 100% complete.
Demolition is at 40%, with completion scheduled for mid November.
Classroom wings have been demolished and debris hauled away.
Demolition of the auditorium and gymnasium is on going.

West Lake Demolition
West Lake Demolition
West Lake Demolition
West Lake Demolition

West Lake STEM Junior High School: Replacement

Estimated project completion is 2024.
Design is in process with bidding in December 2021.
New West Lake is based on existing Utah middle school buildings using 21 st century design with flexibility to support current and future learning activities.

Preliminary West Lake Floor Plan

Sample Floor Plan (First Floor)
Sample Floor Plan (First Floor)
Sample Floor Plan (Second Floor)
Sample Floor Plan (Second Floor)

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October, 2022 by Granite Schools

Skyline High School: Athletics Complex

Athletics phase is 60% complete.
Baseball diamond and football stadium are complete.
Interior painting is in progress.
Excavation for the pool is scheduled to begin in October.
Grading is underway for the athletic fields.

Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – Cyprus

October, 2022 by Granite Schools

Cyprus High School: Site Preparation

Site preparation is 100% complete.
Mass grading has been completed.
Kennecott site storm water drainage redirection project is completed.

Cyprus Site Work
Cyprus Site Work
Cyprus Site Work
Cyprus Site Work

Cyprus High School: Building Construction

Purchase order was issued to Westland Construction for construction of the new Cyprus High School.
Notice to proceed issued 09/13/2021.
Excavation of footings has begun.

Cyprus Footings
Cyprus Footings
Cyprus Footings
Cyprus Footings

Filed Under: Cyprus, Project Updates

Status of Projects August 2022 – West Lake

August, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.

Footings
Footings
Floor slab for teacher’s common area
Floor slab for teacher’s common area
North parking lot curb & gutter
North parking lot curb & gutter
North parking lot curb & gutter
North parking lot curb & gutter
Structural steel framing being erected
Structural steel framing being erected
Structural steel framing being erected
Structural steel framing being erected

Filed Under: Project Updates, West Lake

  • 1
  • 2
  • 3