Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.