Area H (Classroom Wing):
- Classroom A/V and electrical punch work completed.Systems are functional with only a small list of correctiveitems remaining.
- Countertops have been installed in the main restroomson Levels 2 and 3.
- Corridor LVT installation is 95% complete, withremaining punch list items in progress.
- Wood paneling installation is complete.
- Construction cleaning in all areas is ongoing.
Area I (Black Box):
- Black Box Theater bleachers are being installed.
- The Scenery Shop floor has been ground and cleaned.
- Cabinetry and shelving installations are complete.
- Construction cleaning in all areas is ongoing.
Auditorium:
- The Fly Loft orchestra shell has been installed, andlighting is being wired.
- Control booth cabinetry has been installed.
- Interior finish carpentry in the Auditorium is complete.
- Seating installation began on May 18th.
Area J (Performing Arts Entry):
- Entry wall graphics and display cases have beeninstalled.
Sitework / Demolition:
- Building demolition and abatement have been completed.During demolition of the Auditorium, a significant amountof underground transite piping was discovered. Throughcoordination between Hughes, A1 Abatement, and GSD,the affected areas were cleared daily, allowing thedemolition contractor to remain productive on site,completing the impacted areas ahead of schedule, andkeeping the project moving forward.
- Storm drainage chambers are being installed, along withconnections to all storm branch lines.
- South-side landscaping has been installed. Over theweekend the day after the grass was installed, a vehiclewas driven through the newly landscaped area, damagingsprinkler lines, sprinkler heads, and portions of the grass.Hughes responded quickly and completed all necessaryrepairs the following week.
- Courtyard sprinkler installation is complete, and the area isbeing prepared for grass installation.
- Handrails have been installed on the stairway leading tothe Seminary Building.
- Courtyard fence posts have been installed.
- Final grading activities are ongoing in preparation forasphalt and concrete work.
- Site utilities are being coordinated and tied into existing infrastructure.










