GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
  • Skyline High School
    • Project Updates
  • West Lake Jr. High
    • Project Updates
  • All Updates

Copyright 2023
Granite School District

Status of Projects
November 2022
Architecture, Engineering & Construction

November, 2022 by Granite School District Communications Office

Objective

Updatethe GSD Board and Superintendencyon the progress of major construction projects overseen by the Architecture, Engineering & Construction Department on behalf of Granite School District.

Security Upgrades

William Penn Security Remodel

Main office cabinetry
Main office cabinetry
Curtain wall and glass
Curtain wall and glass

Construction Remodels

Fremont Elementary School
Pillar Repair

First phase is complete.
Placing concrete in the next two phases.
Tracking for completion by end of December.

Concrete patch and repairs
Concrete patch and repairs
Concrete patch and repairs
Concrete patch and repairs

GEC Chiller
GEC Chiller Replacement

Chiller #1 is online but waiting for controls.
Chiller #2 is waiting for controls.
Old chillers have been removed.
At this stage, primary cooling and back up cooling for the data center has been accomplished.

Old chiller demolished
Old chiller demolished

Hunter Elementary School
Boiler Replacement

Old boilers have been removed.
Concreteequipment pad has been placed.
New boilers in place.
Hot water piping and connections are being fabricated.
Control contractor working on control system.
Test fire of boiler occurred the week of October 24.
Completion expected in November.

New boiler unit
New boiler unit
Boiler piping in process
Boiler piping in process

Hunter High School
HVAC Control Upgrades

20% of HVAC controls have been upgraded.

New Construction

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab
  • Skyline High School Cost Summary
    • Construction Management Fees: PO #070055
      • Construction Payments to Date: $6,641,432.82
      • Change Orders Requiring Board Authorization Owner Request: $5,827,842.00
      • Change Order Sub Total: $5,827,842.00
    • Phase 1 – Baseball Field – Phase Complete: PO #070441
      • Construction Payments to Date: $3,215,045.66
    • Phase 2 – Athletics: PO #170038
      • Construction Payments to Date: $40,927,897.47
      • Change Orders Requiring Board Authorization Owner Request: $2,513,634.43
      • Advancing Work Into Earlier Phase: $654,253.71
      • Unknown Conditions: $107,327.02
      • Erors & Omission: $305,449.44
      • Staff Level Change Orders: -$2,606,263.01
      • Change Order Sub Total: $974,311.59
      • Phase Advancement Sub Total: $654,253.71
    • Phase 3 – Site Package: PO #2070113
      • Construction Payments to Date: $9,014,551.00
      • Change orders Requiring Board Authorization Owner Request: $0.00
      • Advancing Work Into Earlier Phase: $193,225.74
      • Unknown Conditions: $71,537.66
      • Errors & Omission: $48,139.45
      • Staff Level Change Orders: -$1,509,104.04
      • CO7 Property Line Revisions: $45,793.21
      • Change Order Sub Total: -$1,277,201.19
      • Phase Advancement Sub Total: $193,225.74
    • Phase 4 – Academic Building: PO #270306
      • Construction Payments to Date: $13,885,544.76
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing Work Into Earlier Phase
      • Unknown Conditions: $1,010.00
      • Errors & Omission: $59,089.87
      • Staff Level Change Orders: -$2,171,410.87
      • Change Order Sub Total: -$2,111,311.00
      • Phase Advancement Sub Total
    • Summary
      • Payments to Date – Grand Total: $73,684,471.71
      • Change Order – Grand Total: $3,416,493.06
      • Phase Advancement – Grand Total: $1,056,371.44
      • Bid Price approved by board 11/2021: $173,736,642.48
      • Revised Cost: $174,262,478.61

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls
  • Cyprus High School Cost Summary
    • Phase 1 Mass Grading: PO #170253
      • Construction Payments: $4,170,965.69
      • Change Orders Requiring Board Authorization Owner Request: $167,624.60
      • Staff Level Change Orders: $116,091.09
      • Change Order Sub Total: $283,715.69
    • Phase 2 Construction: PO #270185
      • Construction Payments to Date: $45,173,454.46
      • Change Orders Requiring Board Authorization Owner Request: $117,489.00
      • Advancing Work Into Earlier Phase: $0.00
      • Unknown Conditions: $259,712.42
        • CO14: $161,969.66
      • Errors & Omission: $287,643.70
      • Staff Level Change Orders: $59,285.32
      • Change Order Sub Total: $724,130.44
      • Phase Advancement Sub Total
    • Summary
      • Payments to Date – Grand Total: $49,344,420.15
      • Change Order – Grand Total: $1,007,846.13

West Lake STEM Junior High School
Building Construction

Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.

Gymnasium
Gymnasium
Academic wing
Academic wing
Interior framing in academic wing
Interior framing in academic wing
Exterior sheathing
Exterior sheathing
Stairs at south commons
Stairs at south commons
Stairs at south commons
Stairs at south commons
Preparation for paving of north parking lot –October 27
Preparation for paving of north parking lot –October 27
Library and teacher collaboration steel structure
Library and teacher collaboration steel structure
Roof decking and structural steel for sheer wall –southwest wing
Roof decking and structural steel for sheer wall –southwest wing
West elevation -gymnasium
West elevation -gymnasium
East elevation –gymnasium reaching top out height
East elevation –gymnasium reaching top out height

Filed Under: Project Updates

  • 1
  • 2
  • 3
  • …
  • 80
  • Next Page »
 

Loading Comments...