• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List

Skyline High Update – June 2026

June 2026

Area H (Classroom Wing):​

  • Classroom A/V and electrical punch work completed.Systems are functional with only a small list of correctiveitems remaining.​
  • Countertops have been installed in the main restroomson Levels 2 and 3.​
  • Corridor LVT installation is 95% complete, withremaining punch list items in progress.​
  • Wood paneling installation is complete.​
  • Construction cleaning in all areas is ongoing.​

Area I (Black Box):​

  • Black Box Theater bleachers are being installed.​
  • The Scenery Shop floor has been ground and cleaned.​
  • Cabinetry and shelving installations are complete.​
  • Construction cleaning in all areas is ongoing.​

Auditorium:​

  • The Fly Loft orchestra shell has been installed, andlighting is being wired.​
  • Control booth cabinetry has been installed.​
  • Interior finish carpentry in the Auditorium is complete.​
  • Seating installation began on May 18th.​

Area J (Performing Arts Entry):​

  • Entry wall graphics and display cases have beeninstalled. ​

Sitework / Demolition:​

  • Building demolition and abatement have been completed.During demolition of the Auditorium, a significant amountof underground transite piping was discovered. Throughcoordination between Hughes, A1 Abatement, and GSD,the affected areas were cleared daily, allowing thedemolition contractor to remain productive on site,completing the impacted areas ahead of schedule, andkeeping the project moving forward.​
  • Storm drainage chambers are being installed, along withconnections to all storm branch lines.​
  • South-side landscaping has been installed. Over theweekend the day after the grass was installed, a vehiclewas driven through the newly landscaped area, damagingsprinkler lines, sprinkler heads, and portions of the grass.Hughes responded quickly and completed all necessaryrepairs the following week.​
  • Courtyard sprinkler installation is complete, and the area isbeing prepared for grass installation.​
  • Handrails have been installed on the stairway leading tothe Seminary Building.​
  • Courtyard fence posts have been installed.​
  • Final grading activities are ongoing in preparation forasphalt and concrete work.​
  • Site utilities are being coordinated and tied into existing infrastructure.​
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)

Filed Under: Project Updates, Skyline

Construction Updates June 2026

June 2026

At the June 2, 2026 Board of Education meeting, a capitol and construction update was presented to the board. Click here to view the slides from the presentation, and a recording is available below.

Filed Under: Project Updates, West Kearns Elementary

West Kearns Elementary Rebuild Meeting

May 2026

On May 6, 2025, District and School leadership held an rebuild information meeting with the West Kearns Community. Please see a recording of the video below, and click here for a copy of the presentation slides.

Filed Under: Uncategorized, West Kearns Elementary

Granite School District Fencing Projects

April 2026

Granite School District has begun a series of fencing improvement projects at several school campuses, focused on strengthening safety and security for students, staff, and visitors.

As part of this effort, some fencing may be replaced, select areas will receive new or upgraded gates, and layouts may be adjusted to better manage access points. These updates are designed to create more secure campus boundaries while still maintaining a welcoming environment for our school communities.

During the coming weeks, students, families, and patrons may notice construction activity at various schools. Work will be scheduled to minimize disruption to the school day whenever possible, and all projects will follow established safety guidelines.

These enhancements are part of our ongoing commitment to providing safe, supportive learning environments. We appreciate the community’s patience and understanding as this important work is completed.

Specifically, fencing projects will happen at these schools in April/May 2026:

  • Cottonwood Elementary
  • Woodstock Elementary
  • Fox Hills Elementary
  • Hillsdale Elementary
  • Hillside Elementary
  • Hunter Elementary
  • Fremont Elementary

It’s estimated that the above projects will be completed by the end of May 2026.

All other schools in Granite will be evaluated for fencing projects. Fencing projects at other elementary schools will happen over the next year, with projects at jr. and sr. high schools happening later on. Updates will be posted here on GSDFuture.org.

Filed Under: Project Updates

Skyline High Update – March 2026

April 2026

Academics:​

  • Punch list and warranty ongoing​

Performing Arts Demo:​

  • Interior asbestos abatement​
  • Exterior cement panel removal and disposal​

Performing Arts:​

  • Interior wall covering and lights installationongoing​
  • Classroom divisible accordion door installation​
  • Auditorium wall and stair light installation​
  • Black Box Theater flooring installation​
  • Air handler relocation and demo work​
  • School marquee concrete patching and touch up​
  • EV charging station installed​

Filed Under: Skyline

Construction Updates March 2026

April 2026

A presentation on Capital and Construction updates was given at the March 31, 2026 Board Study Session. A recording can be watched at the beginning of the video below. (Starting shortly after the 20-minute mark)

Filed Under: Project Updates

Construction Updates – February 2026

February 2026

A presentation on Capital and Construction updates was given at the February 2026 Board Study Session. A recording can be watched at the beginning of the video below.

Filed Under: Project Updates

Skyline High Update – February 2026

February 2026

Academics:​

  • Punch list and warranty ongoing​

Performing Arts Demo:​

  • Asbestos abatement and utility management​

Performing Arts:​

  • Southeast parking concrete steps completed​
  • Exterior material installation ongoing​
  • Relocation of air handler to Mechanical Room​
  • Concrete floor preparation​
  • Blackbox Theater progress​
  • Corridor wall panel installation progress​
  • Band and Choral Room acoustical fabric wallpanels​
  • Auditorium wall paneling​
  • Auditorium soffit and light fixture installation​

Click here to see construction progress photos.

Filed Under: Skyline

Cyprus High Update – November 2025

November 2025

Work on some finishing touches continues at Cyprus High School. Click here for a presentation and photos.

Site Work/Exterior Building:

  • Parking lot island landscaping
  • Baseball/Softball AV 
  • Visitor side bleacher gates 

Athletics/Pool:

  • Weight Room/Cardio AV
  • Pool Locker Room/Observation Deck doors
  • Gym shade control

Administration/Commons:

  • Testing Center projector
  • Motors installed on the Serving Area doors
  • Digital vinyl wall covering
  • Operational Kitchen
  • Column extension in Crow’s Nest

Academics/CTE/Social Studies:

  • Metal Shop copper piping
  • Welding booths
  • Electric kilns

Performing Arts:

  • Elevator completed

Filed Under: Cyprus, Project Updates

Skyline Progress Photos

November 2025

Click on the links below to view recent photos of construction progress at Skyline High School. The photos are organized by month in reverse order.

  • February 2026
  • November 2025
  • September 2025
  • August 2025
  • July 2025
  • June 2025
  • May 2025
  • April 2025
  • March 2025
Skyline Auditorium

Filed Under: Project Updates, Skyline

  • Page 1
  • Page 2
  • Page 3
  • Interim pages omitted …
  • Page 19
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

 

Loading Comments...