Objective
Updatethe GSD Board and Superintendencyon the progress of major construction projects overseen by the Architecture, Engineering & Construction Department on behalf of Granite School District.
Security Upgrades
William Penn Security Remodel


Construction Remodels
Fremont Elementary School
Pillar Repair
First phase is complete.
Placing concrete in the next two phases.
Tracking for completion by end of December.


GEC Chiller
GEC Chiller Replacement
Chiller #1 is online but waiting for controls.
Chiller #2 is waiting for controls.
Old chillers have been removed.
At this stage, primary cooling and back up cooling for the data center has been accomplished.

Hunter Elementary School
Boiler Replacement
Old boilers have been removed.
Concreteequipment pad has been placed.
New boilers in place.
Hot water piping and connections are being fabricated.
Control contractor working on control system.
Test fire of boiler occurred the week of October 24.
Completion expected in November.


Hunter High School
HVAC Control Upgrades
20% of HVAC controls have been upgraded.
New Construction
Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.





- Skyline High School Cost Summary
- Construction Management Fees: PO #070055
- Construction Payments to Date: $6,641,432.82
- Change Orders Requiring Board Authorization Owner Request: $5,827,842.00
- Change Order Sub Total: $5,827,842.00
- Phase 1 – Baseball Field – Phase Complete: PO #070441
- Construction Payments to Date: $3,215,045.66
- Phase 2 – Athletics: PO #170038
- Construction Payments to Date: $40,927,897.47
- Change Orders Requiring Board Authorization Owner Request: $2,513,634.43
- Advancing Work Into Earlier Phase: $654,253.71
- Unknown Conditions: $107,327.02
- Erors & Omission: $305,449.44
- Staff Level Change Orders: -$2,606,263.01
- Change Order Sub Total: $974,311.59
- Phase Advancement Sub Total: $654,253.71
- Phase 3 – Site Package: PO #2070113
- Construction Payments to Date: $9,014,551.00
- Change orders Requiring Board Authorization Owner Request: $0.00
- Advancing Work Into Earlier Phase: $193,225.74
- Unknown Conditions: $71,537.66
- Errors & Omission: $48,139.45
- Staff Level Change Orders: -$1,509,104.04
- CO7 Property Line Revisions: $45,793.21
- Change Order Sub Total: -$1,277,201.19
- Phase Advancement Sub Total: $193,225.74
- Phase 4 – Academic Building: PO #270306
- Construction Payments to Date: $13,885,544.76
- Change Orders Requiring Board Authorization Owner Request
- Advancing Work Into Earlier Phase
- Unknown Conditions: $1,010.00
- Errors & Omission: $59,089.87
- Staff Level Change Orders: -$2,171,410.87
- Change Order Sub Total: -$2,111,311.00
- Phase Advancement Sub Total
- Summary
- Payments to Date – Grand Total: $73,684,471.71
- Change Order – Grand Total: $3,416,493.06
- Phase Advancement – Grand Total: $1,056,371.44
- Bid Price approved by board 11/2021: $173,736,642.48
- Revised Cost: $174,262,478.61
- Construction Management Fees: PO #070055
Cyprus High School
Building Construction
Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.






- Cyprus High School Cost Summary
- Phase 1 Mass Grading: PO #170253
- Construction Payments: $4,170,965.69
- Change Orders Requiring Board Authorization Owner Request: $167,624.60
- Staff Level Change Orders: $116,091.09
- Change Order Sub Total: $283,715.69
- Phase 2 Construction: PO #270185
- Construction Payments to Date: $45,173,454.46
- Change Orders Requiring Board Authorization Owner Request: $117,489.00
- Advancing Work Into Earlier Phase: $0.00
- Unknown Conditions: $259,712.42
- CO14: $161,969.66
- Errors & Omission: $287,643.70
- Staff Level Change Orders: $59,285.32
- Change Order Sub Total: $724,130.44
- Phase Advancement Sub Total
- Summary
- Payments to Date – Grand Total: $49,344,420.15
- Change Order – Grand Total: $1,007,846.13
- Phase 1 Mass Grading: PO #170253
West Lake STEM Junior High School
Building Construction
Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.










