GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

West Lake Jr. High Rebuild

After sustaining significant damage in the 2020 earthquake, and settling with the district’s insurance provider, the Granite Board of Education has opted to rebuild West Lake Junior High School on its original site.

The new West Lake building will take advantage of architectural plans from an existing Utah middle school building. That school (Hidden Valley Middle School) was completed in 2020, and uses a next-generation layout that supports current and future learning activities. Enhanced security is a priority, and learning communities are simplified to increase the usable collaborative and breakout spaces while reducing the overall building area and building cost.

Rendering of West Lake Junior High

Anticipated West Lake Site Plan:

Sample Floor Plan:

Floor plan of Hidden Valley Middle School
Floor plan of Hidden Valley Middle School

Anticipated Timeline

  • August/September 2021 – Building abatement
  • October/November 2021 – Building demolition
  • Mid-November 2021 – New building plans finalized
  • January 2022 – Construction bids received; construction commences in line with winning bid
 