West Lake STEM Junior High School
Building Construction
Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.
![Gymnasium](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-167-300x169.png)
![Academic wing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-168-300x169.png)
![Interior framing in academic wing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-169-300x225.png)
![Exterior sheathing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-170-300x225.png)
![Stairs at south commons](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-171-300x225.png)
![Stairs at south commons](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-172-300x225.png)
![Preparation for paving of north parking lot –October 27](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-173-300x225.png)
![Library and teacher collaboration steel structure](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-174-300x225.png)
![Roof decking and structural steel for sheer wall –southwest wing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-175-300x225.png)
![West elevation -gymnasium](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-176-300x225.png)
![East elevation –gymnasium reaching top out height](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-177-300x206.png)