GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects October 2022 – West Lake

October, 2022 by Granite Schools

West Lake Junior High School STEM (Westbrook Campus): FACS Modular Building

Building is 100% complete.

Backordered furniture is shipping as available.

West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building

West Lake STEM Junior High School: Abatement / Demolition

Building abatement is 100% complete.
Demolition is at 40%, with completion scheduled for mid November.
Classroom wings have been demolished and debris hauled away.
Demolition of the auditorium and gymnasium is on going.

West Lake Demolition
West Lake Demolition
West Lake Demolition
West Lake Demolition

West Lake STEM Junior High School: Replacement

Estimated project completion is 2024.
Design is in process with bidding in December 2021.
New West Lake is based on existing Utah middle school buildings using 21 st century design with flexibility to support current and future learning activities.

Preliminary West Lake Floor Plan

Sample Floor Plan (First Floor)
Sample Floor Plan (First Floor)
Sample Floor Plan (Second Floor)
Sample Floor Plan (Second Floor)

Filed Under: Project Updates, West Lake

 

Loading Comments...