• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Status of Projects November 2024 – West Lake STEM

November 2024

Updates:

  • Work in the Auditorium should be completed by Thanksgiving, with seating and flooring installation in progress.
  • Stage curtains and rigging are completed.
  • Wall graphics in the Commons area and the Media Center are in place.
  • Punch list items are being worked on throughout the building.
  • Landscaping is 99% complete.

Recent Pictures:

Elevated running track surface
Elevated running track surface
Flooring between fitness and dance rooms
Flooring between fitness and dance rooms
Media Center
Media Center
Bookcases in Media Center
Bookcases in Media Center
Wall finishes at entry to classroom pods
Wall finishes at entry to classroom pods
Paneling and graphics at Administration
Paneling and graphics at Administration
Graphics in the Central Commons Area
Graphics in the Central Commons Area
Graphics in the Central Commons Area
Graphics in the Central Commons Area

Filed Under: West Lake

Status of Projects November 2024 – Skyline High School

November 2024

Updates:

Academics
● Punch list is ongoing

Performing Arts
● Tilt panels on the north of Performing Arts installed.
● Orchestra pit exterior foundation walls poured, damp proofed, and backfilling taking place.
● Stepped footings and foundation walls pouring on both sides of the orchestra pit.
● Conduits, underground plumbing, and underground HVAC continue to be installed.
● Footings formed and poured on the east side of the orchestra pit.
● Footings on the west side of the orchestra pit are being excavated and prepped for pouring.
● Perimeter gravel and pipe drain system being installed.

Recent Pictures:

Performing Arts tilt wall being lifted into place
Performing Arts tilt wall being lifted into place
Forming orchestra pit foundation
Forming orchestra pit foundation
Preparing orchestra pit foundation for concrete
Preparing orchestra pit foundation for concrete
Orchestra pit foundation poured and preparing for backfill
Orchestra pit foundation poured and preparing for backfill
Electrical conduits east of the orchestra pit
Electrical conduits east of the orchestra pit
Electrical conduits north of the orchestra pit
HVAC installation north of the orchestra pit
HVAC installation north of the orchestra pit
Plumbing installation south of the orchestra pit
Plumbing installation south of the orchestra pit
Footings preparation East of the orchestra pit
Footings preparation East of the orchestra pit
Pouring concrete footings East of the orchestra pit
Pouring concrete footings East of the orchestra pit
Testing Center in use
Testing Center in use

Filed Under: Skyline

Status of Projects November 2024 – Cyprus High School

November 2024

Updates:

Site Work:
● Landscaping at the North end of the site
● Grass above Play Fields
● Curbing at the East and South Entrances
● Doors on the Outbuildings

Athletics/Pool:
● Cement floor in the Field House
● Batting cages
● Basketball sub-floor

Administration/Commons:
● Metal paneling on the exterior
● Walk-in freezer in Kitchen

Academics/CTE:
● HVAC in the CTE buildings
● Retaining wall at the CTE entrance
● Glass installed at the labs and classroom pods

Performing Arts:
● Wood paneling at the Auditorium
● Orchestra pit in the Auditorium

Recent Photos:

Landscaping at the North Entrance
Landscaping at the North Entrance
Grass above the Play Fields
Grass above the Play Fields
Curb and gutter at the East Entrance
Curb and gutter at the East Entrance
Curb and gutter to the South
Curb and gutter to the South
Doors at the Outbuildings
Doors at the Outbuildings
Cement floor in the Athletics Fieldhouse
Cement floor in the Athletics Fieldhouse
Batting Cages in Athletics
Batting Cages in Athletics
Basketball subfloor
Basketball subfloor
Metal panels on the exterior of Commons
Metal panels on the exterior of Commons
Walk in freezer in the Kitchen
Walk in freezer in the Kitchen
HVAC in Manufacturing Lab
HVAC in Manufacturing Lab
Retaining wall at CTE Entrance
Retaining wall at CTE Entrance
Glass in classroom pods
Glass in classroom pods
Glass in lab classrooms
Glass in lab classrooms
Wood paneling in the Auditorium
Wood paneling in the Auditorium
Orchestra pit at the Stage
Orchestra pit at the Stage

Filed Under: CyprusTagged With: cyprus high school

Status of Projects Update: November 2024

November 2024

Watch the presentation in the video below for updates about Granite School District construction projects. This presentation was given in the November 2024 Board of Education Meeting – Administrative Session. November 2024 Board of Education Capitol and Construction Update Slide Presentation.

Filed Under: Project Updates

Cyprus High Construction Tour – Fall 2024

October 2024

Filed Under: Cyprus

Skyline High Safety Tour – August 2024

August 2024

Filed Under: Project Updates, Skyline

West Lake STEM Jr. High Safety Tour – August 2024

August 2024

Filed Under: Project Updates, West Lake

Cyprus High Construction Tour – August 2024

August 2024

Filed Under: Cyprus, Project Updates

Status of Projects June 2024 – West Lake STEM

August 2024

Updates:

  • Administrative staff has moved in.
  • Furniture and appliance delivery continues.
  • We are moving in and setting up classrooms.

Recent Pictures:

Hardwood floor in Dance Room installed
Hardwood floor in Dance Room installed
Hardwood floor in Gymnasium progressing
Hardwood floor in Gymnasium progressing
Floor slab preparation for tile in Tech Lab
Floor slab preparation for tile in Tech Lab
Hexagon ceiling cloud tiles in Main Corridor
Hexagon ceiling cloud tiles in Main Corridor
Kitchen equipment installation
Kitchen equipment installation
Kitchen equipment installation
Kitchen equipment installation
Preparation of planting areas on east and north of the building
Preparation of planting areas on east and north of the building
Preparation of planting areas on east and north of the building
Preparation of planting areas on east and north of the building
Landscaping on south side of campus
Landscaping on south side of campus
Landscaping on south side of campus
Landscaping on south side of campus

Filed Under: West Lake

Status of Projects August 2024 – Skyline High School

August 2024

Updates:

Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete

Recent Pictures:

Graphic in Hallway leading to Athletics Building
Graphic in Hallway leading to Athletics Building
Main Entrance with metal panels complete
Main Entrance with metal panels complete
World map graphic in Counseling reception area
World map graphic in Counseling reception area
Special Education classroom progress
Special Education classroom progress
Sewing lab classroom nearing completion
Sewing lab classroom nearing completion
Teacher equipment installation in Ceramics
Teacher equipment installation in Ceramics
Teacher’s Lounge near Administration Suite
Teacher’s Lounge near Administration Suite
Finishes in Level 2 corridor
Finishes in Level 2 corridor
Relocatables set in west parking lot
Relocatables set in west parking lot
Serving line equipment being set
Serving line equipment being set
Demolition of old Academics building
Demolition of old Academics building
Teacher collaboration near Level 2 Media Center
Teacher collaboration near Level 2 Media Center

Filed Under: Skyline

  • Page 1
  • Page 2
  • Page 3
  • Interim pages omitted …
  • Page 17
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2024 Granite School District

 

Loading Comments...