Status of Projects Update: June 2024
Watch the presentation in the video below for updates about Granite School District construction projects. This presentation was given in the June 2024 Board of Education Meeting – Administrative Session. Click here for a copy of the slides.
Status of Projects April 2024 – Cyprus High School
Updates:
Site Work:
● Stadium field base
● Stadium field fencing
● Stadium field drainage
● Flatwork behind home bleachers
Athletics/Pool:
● Track glass handrail
● Precast concrete benches in team locker rooms
● Pool plumbing
Administration/Commons:
● Framing in Administration
● Curtain wall/glazing around the Commons
● Testing Center siding
Academics/CTE:
● Finish paint, casework, and ceiling in Level 3 Academics
● Ceiling grid Levels 2 and 3 Academics
● Underground plumbing/electrical Manufacturing Shop
Performing Arts:
● Auditorium clouds finished
Recent Photos:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Cyprus-10.jpg)
Status of Projects June 2024 – Skyline High School
Updates:
Academics
● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed
Recent Pictures:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-6.jpg)
Commons Area
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-8.jpg)
Learning Staircase
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-9.jpg)
flooring installed
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-11.jpg)
Auditorium placed
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-12.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-13.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/Skyline-14.jpg)
Commons Space
Status of Projects June 2024 – West Lake STEM
Updates:
- Grading, landscaping, irrigation piping, and site concrete installation continues.
- Exterior finishes are approximately 90% complete.
- Interior finishes in the Science and Academic Wings are 75% complete.
- Interior finishes in the Auditorium and CTE Wings are 50% complete.
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-6.jpg)
installed
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-11.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/06/West-Lake-12.jpg)
Cyprus High Construction Tour – April 2024
West Lake STEM Jr. High Construction Tour – April 2024
Status of Projects April 2024 – West Lake STEM
Updates:
- Permanent power to the site is connected. Exterior glazing is 95% complete. The two rooftop air handling units serving the Gymnasium have arrived
- In the Athletic Wing and the Kitchen, the electrical rough-in is 75% complete. The floor and wall tile are also 75% complete.
- The stage rigging in Performing Arts is being installed.
- In the CTE Wing, the mechanical, electrical, plumbing installation and the interior paint work is moving forward.
- The Academic and Administration Wings are progressing with cabinetry installation. The diffusers and grills are 85% complete.
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/WL8.jpg)
Status of Projects April 2024 – Skyline High School
Updates:
Academics
● Ceiling cloud being installed in Cafeteria Area
● Stone cladding complete at Main Entrance
● Lighting installed in Cafeteria
● Glass installed in majority of classroom groups
● Carpet complete on Level 2
● LVT starting in corridors
● Tile started in group restrooms on north end of building on all floors
● Ceiling grid started on all floors
● Cabinetry started on Level 1
● Doors being installed throughout entire building
● Countertops installed in science labs on Level 3
● Restroom accessories being installed
Recent Pictures:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S3.jpg)
Level 1 restroom
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S6.jpg)
Performing Arts
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S10.jpg)
the Cafeteria
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S11.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S12.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S13.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S14.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/S15.jpg)
Status of Projects April 2024 – Cyprus High School
Updates:
Building Exterior:
● Glass installation at the Auditorium
● Glass installation at Academics
Athletics/Pool:
● Pool excavation/footings
● Tile in Pool locker rooms
● Ceiling tile in Athletics Vestibule
● Tectum panels in Weight Room
Administration/Commons:
● Slab on grade in Cafeteria Area of Commons
● Level 1 framing and HVAC in Administration
● Level 2 and 3 framing
Academics/Social Studies:
● Framing Level 2
● Framing and electrical Level 3
Performing Arts:
● Drywall on the Proscenium
● Paint and framing in Scenery Shop
Recent Photos:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C11.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C12.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C13.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C14.jpg)
- 1
- 2
- 3
- …
- 15
- Next Page »