Project Updates
West Lake STEM Jr. High Safety Tour – August 2024
Cyprus High Construction Tour – August 2024
Status of Projects June 2024 – West Lake STEM
Updates:
- Administrative staff has moved in.
- Furniture and appliance delivery continues.
- We are moving in and setting up classrooms.
Recent Pictures:
Status of Projects August 2024 – Skyline High School
Updates:
Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete
Recent Pictures:
Status of Projects August 2024 – Cyprus High School
Updates:
Site Work:
●Football field turf and running track
●Concrete walkways on the east side of the Baseball/Softball field
●Baseball field grading, infill, and fencing
●Roll up doors on the home side bleacher storage
Athletics/Pool:
●Slab on grade pour in the Pool
●Jumbotron and scoreboard installation
Administration/Commons:
●Learning Stairs framed for concrete pour
●Curtain wall/glazing around the Commons
●Metal panels on levels 2 and 3 of Administration
Academics/CTE:
●Masonry walls in the Manufacturing Shop
●Lab cabinetry
●Tile in the group restrooms
Performing Arts:
●Lighting in the Auditorium
●Lights in the Black Box Theater
Recent Photos:
West Lake Construction Update – June 2024
Status of Projects Update: June 2024
Watch the presentation in the video below for updates about Granite School District construction projects. This presentation was given in the June 2024 Board of Education Meeting – Administrative Session. June 2024 Board of Education Capitol and Construction Update Slide Presentation.
Status of Projects June 2024 – Cyprus High School
Updates:
Site Work:
● Stadium field base
● Stadium field fencing
● Stadium field drainage
● Flatwork behind home bleachers
Athletics/Pool:
● Track glass handrail
● Precast concrete benches in team locker rooms
● Pool plumbing
Administration/Commons:
● Framing in Administration
● Curtain wall/glazing around the Commons
● Testing Center siding
Academics/CTE:
● Finish paint, casework, and ceiling in Level 3 Academics
● Ceiling grid Levels 2 and 3 Academics
● Underground plumbing/electrical Manufacturing Shop
Performing Arts:
● Auditorium clouds finished
Recent Photos:
Status of Projects June 2024 – Skyline High School
Updates:
Academics
● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed
Recent Pictures:
Commons Area
Learning Staircase
flooring installed
Auditorium placed
Commons Space