GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects March 2023 – West Lake STEM

March, 2023 by Matthew Sampson

West Lake STEM Junior High School
Building Construction

Steel beams being installed over kitchen and mechanical area.
Interior framing, plumbing, electrical, and mechanical system installation continues in academic classrooms.
Roof decking and steel erecting in progress in entry and commons area.
Boilers and chiller are set in place.
Auditorium and athletics walls are 90% complete.

Boilers and chiller are set in place
Boilers and chiller are set in place
Boilers and chiller are set in place
Boilers and chiller are set in place
Auditorium walls in progress
Auditorium walls in progress
Site overview
Site overview
Mechanical, plumbing, electrical, and framing in classroom wing
Mechanical, plumbing, electrical, and framing in classroom wing
Steel beams being installed
Steel beams being installed
Mechanical, plumbing, electrical, and framing in classroom wing
Mechanical, plumbing, electrical, and framing in classroom wing

Filed Under: Project Updates, West Lake

Status of Projects March 2023 – Cyprus High School

March, 2023 by Matthew Sampson

Auditorium roofing, steel in ceilings and back of house 2nd and 3rd floor continues.
Gymnasium and locker rooms have drywall being installed on one side of metal studs.
Electrical, fire sprinkler/alarm and plumbing continues in the locker rooms and gymnasium.
Gymnasium masonry on stairway walls and under the dance room as well as moving up to pool loft and locker rooms.
Pool roof decking installed, and roofing started. Observation upper deck installed.
Tilt walls for choral and band area have been stood. Steel moving to choral area soon.

Band and choral walls in place
Band and choral walls in place
Auditorium steel
Auditorium steel
HVAC ducting over gymnasium
HVAC ducting over gymnasium
Framing and spray foam insulation
Framing and spray foam insulation
Last section of track being placed
Last section of track being placed
Drywall on one side of metal studs in locker room/changing rooms
Drywall on one side of metal studs in locker room/changing rooms
Masonry below dance room
Masonry below dance room
Ducting to air handlers
Ducting to air handlers
Pool upper observation area decking installed
Pool upper observation area decking installed
Pool trusses installed
Pool trusses installed
Site overview
Site overview

Filed Under: Cyprus, Project Updates

Status of Projects March 2023 – Skyline High School

March, 2023 by Matthew Sampson

Skyline High School
Athletics Complex

Softball batting cages installed.
Concessions and press box are painted with finishes being installed now.
Manufacturing lab and kitchen steel erection continues.
Academics tilt walls continue to be stood.

Softball batting cages
Softball batting cages
Softball dugouts
Softball dugouts
Concessions interior finishes
Concessions interior finishes
Sidewalk prep around the pool connecting the softball complex to the athletics building
Sidewalk prep around the pool connecting the softball complex to the athletics building
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Steel for manufacturing lab / kitchen
Steel for manufacturing lab / kitchen
Tilt walls in academics
Tilt walls in academics
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects February 2023 – West Lake STEM

February, 2023 by Matthew Sampson

West Lake STEM Junior High School
Building Construction

Band and choral room masonry walls are 90% complete and were scheduled to top out the week of January 30th upon which masons will move to auditorium area.
Contractor is placing decking for second floor in northwest academic wing and preparing to place roof decking on southeast academic wing.
Metal stud, framing, interior, plumbing, electrical, lighting, power, and mechanical system installation continues in south wings.

Southwest academic wing exterior sheathing
Southwest academic wing exterior sheathing
Gymnasium roof decking
Gymnasium roof decking
Southeast academic steel trusses
Southeast academic steel trusses
Southeast academic framing 1st floor
Southeast academic framing 1st floor
Site overview auditorium and administration walls started
Site overview auditorium and administration walls started

Filed Under: Project Updates, West Lake

Status of Projects February 2023 – Cyprus High School

February, 2023 by Matthew Sampson

Cyprus High School
Building Construction

Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.

Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Framing mechanical room
Framing mechanical room
Framing bathrooms
Framing bathrooms
Roof steel decking
Roof steel decking
Auditorium cloud steel
Auditorium cloud steel
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Site Overview
Site Overview

Filed Under: Cyprus, Project Updates

Status of Projects February 2023 – Skyline High School

February, 2023 by Matthew Sampson

Skyline High School
Athletics Complex

Softball building is currently being painted and tile is being installed.
Kitchen and testing center walls continue to be stood.
Steel continues with roof joists and decking.
Looking into options to strengthen existing auditorium wall exposed by gymnasium demolition as this will be the exterior wall for next 3 years.

Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium
Softball exterior walls heated prepping for paint
Softball exterior walls heated prepping for paint
Softball interior walls prepping for paint
Softball interior walls prepping for paint
Bathroom tile being installed
Bathroom tile being installed
Testing center roof joists with decking installed
Testing center roof joists with decking installed
Manufacturing lab / kitchen stairs being installed
Manufacturing lab / kitchen stairs being installed
Graphics and sewing rooms
Graphics and sewing rooms
Tilt wall ready to be stood
Tilt wall ready to be stood
Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium

Filed Under: Project Updates, Skyline

Status of Projects January 2023 – West Lake STEM

January, 2023 by Matthew Sampson

West Lake STEM Junior High School
Building Construction

Gymnasium roof trusses and 90% of roof decking is in place.
Locker room masonry walls 90% complete.
Kitchen and mechanical rooms masonry walls 50% complete.
Southwest academic wing framing is complete, exterior sheathing is 75% first floor utilities are 50% complete.
Southeast academic wing second floor decking and teacher hub/commons area concrete slab ready to be placed.

Masonry for kitchen and mechanical rooms
Masonry for kitchen and mechanical rooms
Gymnasium steel roofing
Gymnasium steel roofing
Commons area near teacher’s hub
Commons area near teacher’s hub
Academic building and gymnasium
Academic building and gymnasium
Southwest academic wing utilities and framing
Southwest academic wing utilities and framing

Filed Under: Project Updates, West Lake

Status of Projects January 2023 – Cyprus High School

January, 2023 by Matthew Sampson

Cyprus High School
Building Construction

Auditorium steel trusses, cross bracing and the catwalk are all being installed.
More auditorium tilt panels being prepped to be placed.
Gymnasium steel decking is done around the running track and ½ the concrete has been placed for the track.
Gymnasium floor is being prepped for concrete.
The cardio & wrestling room is being framed, along with HVAC and rough electrical being installed.

Auditorium roof decking and catwalk
Auditorium roof decking and catwalk
Cardio room rough in
Cardio room rough in
Gymnasium stairs
Gymnasium stairs
Gym floor being prepped for concrete
Gym floor being prepped for concrete
Windows have been sealed waiting for frames
Windows have been sealed waiting for frames

Filed Under: Cyprus, Project Updates

Status of Projects January 2023 – Skyline High School

January, 2023 by Matthew Sampson

Skyline High School
Athletics Complex

Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.

Classroom steel trusses
Classroom steel trusses
Demolition of gymnasium from auditorium.
Demolition of gymnasium from auditorium
Pathway emergency phones
Pathway emergency phones
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – West Lake

November, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.

Gymnasium
Gymnasium
Academic wing
Academic wing
Interior framing in academic wing
Interior framing in academic wing
Exterior sheathing
Exterior sheathing
Stairs at south commons
Stairs at south commons
Stairs at south commons
Stairs at south commons
Preparation for paving of north parking lot –October 27
Preparation for paving of north parking lot –October 27
Library and teacher collaboration steel structure
Library and teacher collaboration steel structure
Roof decking and structural steel for sheer wall –southwest wing
Roof decking and structural steel for sheer wall –southwest wing
West elevation -gymnasium
West elevation -gymnasium
East elevation –gymnasium reaching top out height
East elevation –gymnasium reaching top out height

Filed Under: Project Updates, West Lake

  • 1
  • 2
  • 3
  • …
  • 11
  • Next Page »
 

Loading Comments...