A presentation on Capital and Construction updates was given at the February 2026 Board Study Session. A recording can be watched at the beginning of the video below.
Project Updates
Skyline High Update – February 2026
Academics:
- Punch list and warranty ongoing
Performing Arts Demo:
- Asbestos abatement and utility management
Performing Arts:
- Southeast parking concrete steps completed
- Exterior material installation ongoing
- Relocation of air handler to Mechanical Room
- Concrete floor preparation
- Blackbox Theater progress
- Corridor wall panel installation progress
- Band and Choral Room acoustical fabric wallpanels
- Auditorium wall paneling
- Auditorium soffit and light fixture installation
Cyprus High Update – November 2025
Work on some finishing touches continues at Cyprus High School. Click here for a presentation and photos.
Site Work/Exterior Building:
- Parking lot island landscaping
- Baseball/Softball AV
- Visitor side bleacher gates
Athletics/Pool:
- Weight Room/Cardio AV
- Pool Locker Room/Observation Deck doors
- Gym shade control
Administration/Commons:
- Testing Center projector
- Motors installed on the Serving Area doors
- Digital vinyl wall covering
- Operational Kitchen
- Column extension in Crow’s Nest
Academics/CTE/Social Studies:
- Metal Shop copper piping
- Welding booths
- Electric kilns
Performing Arts:
- Elevator completed
Skyline Progress Photos
Click on the links below to view recent photos of construction progress at Skyline High School. The photos are organized by month in reverse order.
- February 2026
- November 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- March 2025

The New Cyprus High is Open!
Select Cyprus High Construction Tour – June 2025
Cyprus High Construction Tour – March 2025
Skyline High School Update
What is the Project Status?
Students have been enjoying the fully-completed academics building and athletic facilities this school year (2024/2025).
The auditorium and remaining classrooms will be completed in time for the 2026/2027 school year. Some minor site, parking lot, and landscaping work will continue into the 2026/2027 school year.

Cyprus High Construction Tour – January 2025
Status of Projects Update: January 2025
Watch the presentation in the video below for updates about Granite School District construction projects. This presentation was given in the January 2025 Board of Education Meeting – Administrative Session. January 2025 Board of Education Capitol and Construction Update Slide Presentation.