Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.
![Athletic building in background, new academic phase under construction](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-156-300x169.png)
![Tennis courts in progress](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-157-300x169.png)
![Sod on softball field](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-158-300x225.png)
![Sod on softball field](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-159-300x225.png)
![Tennis court post-tension slab](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-160-300x225.png)
Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.