• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Skyline

Skyline High School Update

March 2025

What is the Project Status?

Students have been enjoying the fully-completed academics building and athletic facilities this school year (2024/2025).

The auditorium and remaining classrooms will be completed in time for the 2026/2027 school year. Some minor site, parking lot, and landscaping work will continue into the 2026/2027 school year.

Ribbon Cutting image.
Academics Building Ribbon Cutting

Filed Under: Skyline

Status of Projects November 2024 – Skyline High School

November 2024

Updates:

Academics
● Punch list is ongoing

Performing Arts
● Tilt panels on the north of Performing Arts installed.
● Orchestra pit exterior foundation walls poured, damp proofed, and backfilling taking place.
● Stepped footings and foundation walls pouring on both sides of the orchestra pit.
● Conduits, underground plumbing, and underground HVAC continue to be installed.
● Footings formed and poured on the east side of the orchestra pit.
● Footings on the west side of the orchestra pit are being excavated and prepped for pouring.
● Perimeter gravel and pipe drain system being installed.

Recent Pictures:

Performing Arts tilt wall being lifted into place
Performing Arts tilt wall being lifted into place
Forming orchestra pit foundation
Forming orchestra pit foundation
Preparing orchestra pit foundation for concrete
Preparing orchestra pit foundation for concrete
Orchestra pit foundation poured and preparing for backfill
Orchestra pit foundation poured and preparing for backfill
Electrical conduits east of the orchestra pit
Electrical conduits east of the orchestra pit
Electrical conduits north of the orchestra pit
HVAC installation north of the orchestra pit
HVAC installation north of the orchestra pit
Plumbing installation south of the orchestra pit
Plumbing installation south of the orchestra pit
Footings preparation East of the orchestra pit
Footings preparation East of the orchestra pit
Pouring concrete footings East of the orchestra pit
Pouring concrete footings East of the orchestra pit
Testing Center in use
Testing Center in use

Filed Under: Skyline

Skyline High Safety Tour – August 2024

August 2024

Filed Under: Project Updates, Skyline

Status of Projects August 2024 – Skyline High School

August 2024

Updates:

Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete

Recent Pictures:

Graphic in Hallway leading to Athletics Building
Graphic in Hallway leading to Athletics Building
Main Entrance with metal panels complete
Main Entrance with metal panels complete
World map graphic in Counseling reception area
World map graphic in Counseling reception area
Special Education classroom progress
Special Education classroom progress
Sewing lab classroom nearing completion
Sewing lab classroom nearing completion
Teacher equipment installation in Ceramics
Teacher equipment installation in Ceramics
Teacher’s Lounge near Administration Suite
Teacher’s Lounge near Administration Suite
Finishes in Level 2 corridor
Finishes in Level 2 corridor
Relocatables set in west parking lot
Relocatables set in west parking lot
Serving line equipment being set
Serving line equipment being set
Demolition of old Academics building
Demolition of old Academics building
Teacher collaboration near Level 2 Media Center
Teacher collaboration near Level 2 Media Center

Filed Under: Skyline

Status of Projects June 2024 – Skyline High School

June 2024

Updates:

Academics

● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved   into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed

Recent Pictures:

View of Academics from Central Courtyard
View of Academics from Central Courtyard
Furniture installation in Administration
Furniture installation in Administration
Furniture installed in Career Center
Furniture installed in Career Center
Classroom with student desks installed
Classroom with student desks installed
Large format tile installation in Serving Area
Large format tile installation in Serving Area
LVT flooring installation in the
Commons Area
LVT flooring installation in the
Commons Area
Men’s restroom on Level 2
Men’s restroom on Level 2
Pre-cast stairs installed on the
Learning Staircase
Pre-cast stairs installed on the
Learning Staircase
Science classroom with rubber
flooring installed
Science classroom with rubber
flooring installed
LVT flooring installed in Main L2 Corridor
LVT flooring installed in Main L2 Corridor
Temporary pathway around the old
Auditorium placed
Temporary pathway around the old
Auditorium placed
Circular seating placed in Central Courtyard
Circular seating placed in Central Courtyard
Manufacturing Lab with equipment being set
Manufacturing Lab with equipment being set
Wood accent wall installation in Level 2
Commons Space
Wood accent wall installation in Level 2
Commons Space

Filed Under: Skyline

Status of Projects April 2024 – Skyline High School

April 2024

Updates:

Academics

● Ceiling cloud being installed in Cafeteria Area
● Stone cladding complete at Main Entrance
● Lighting installed in Cafeteria
● Glass installed in majority of classroom groups
● Carpet complete on Level 2
● LVT starting in corridors
● Tile started in group restrooms on north end of building   on all floors
● Ceiling grid started on all floors
● Cabinetry started on Level 1
● Doors being installed throughout entire building
● Countertops installed in science labs on Level 3
● Restroom accessories being installed

Recent Pictures:

Cabinets in Special Education Classroom
Cabinets in Special Education Classroom
Cabinets installed in the Administration Suite Workroom
Cabinets installed in the Administration Suite Workroom
Tile and storefront being installed in
Level 1 restroom
Tile and storefront being installed in
Level 1 restroom
LVT flooring and glass installed in Fix-It Room by the Media Center on Level 2
LVT flooring and glass installed in Fix-It Room by the Media Center on Level 2
Stone cladding at the Main Entrance
Stone cladding at the Main Entrance
Stair tower connecting Academics to
Performing Arts
Stair tower connecting Academics to
Performing Arts
Teacher’s Lounge cabinets and accent paint
Teacher’s Lounge cabinets and accent paint
Countertops installed in Level 3 science labs
Countertops installed in Level 3 science labs
Plumbing fixtures and accessories installed in Administration Suite restroom
Plumbing fixtures and accessories installed in Administration Suite restroom
High ceiling clouds being installed in
the Cafeteria
High ceiling clouds being installed in
the Cafeteria
Glass installed at the Level 2 classrooms
Glass installed at the Level 2 classrooms
Wood-look acoustical ceiling grid outside of Level 2 Media Center
Wood-look acoustical ceiling grid outside of Level 2 Media Center
Northwest property line by Softball Fields
Northwest property line by Softball Fields
Stairway into the gully
Stairway into the gully
Gully
Gully

Filed Under: Skyline

Skyline Construction Update Video – March 2024

March 2024

Filed Under: Project Updates, Skyline

Status of Projects March 2024 – Skyline High School

March 2024

Updates:

Academics

●High ceiling in Cafeteria painted
●Exterior glass complete at Main Entrance
●Metal wood look soffits near completion in Cafeteria
●Storefront glass frames installed at Media Center
●Interior glass in classroom groups started
●Carpet and electrical trim started in Level 2 general classrooms
●Cabinet installation ongoing in Level 3 Science classrooms
●Painting on Level 2 near completion
●Main Corridor tile complete on Levels 2 and 3
●Tile at the Smoothie Bar complete
●Plumbing fixtures set in Administration Suite bathrooms

Recent Pictures:

Level 3 general classrooms with finishes being installed
Level 3 general classrooms with finishes being installed
Soffit in the Eagle’s Nest
Soffit in the Eagle’s Nest
Rolling shelves in the Administration file room
Rolling shelves in the Administration file room
Plumbing fixtures in Administration bathrooms
Plumbing fixtures in Administration bathrooms
Exterior glass and painted ceiling in
Cafeteria/Commons
Exterior glass and painted ceiling in
Cafeteria/Commons
Administration Suite entrance
Administration Suite entrance
Cabinets installed in Level 3 Science classrooms
Cabinets installed in Level 3 Science classrooms
Storefront window frames at the Media Center
Storefront window frames at the Media Center
Stone cladding at the Pool/Athletics entrance
Stone cladding at the Pool/Athletics entrance
Ceiling grid in the Testing Center
Ceiling grid in the Testing Center
Smoothie Bar tile
Smoothie Bar tile

Filed Under: Skyline

Status of Projects February 2024 – Skyline High School

February 2024

Updates:

Academics

●Activity Stairs in the cafeteria are fully erected.
●Drywall and framing are nearing completion in the cafeteria area.
●All in-wall utilities are near completion throughout the entire building.
●Ceiling grid is being worked on in all general classrooms and is complete in the Administration Suite. ●Casework/cabinets are being installed in the lab classrooms on level 4.
●Fixed glass walls have started in the general classroom groups on level 3.
●Curtain wall glass is nearing completion on the Cafeteria.
●Testing Center is now drywalled and taped.
●Trophy shelving is being installed in the new Athletics Vestibule.
●Tile is nearing completion in the Administration bathrooms.
●Fire sprinkler systems are nearing completion on 3 floors.
●Framing in the south stair tower has started.

Recent Pictures:

Main academics building and Cafeteria as viewed from the Courtyard
Main academics building and Cafeteria as viewed from the Courtyard
Main academics building and Cafeteria as viewed from the Courtyard
Main academics building and Cafeteria as viewed from the Courtyard
Main Activity staircase and Cafeteria progress
Main Activity staircase and Cafeteria progress
Trophy case glass being installed in Athletics Vestibule
Trophy case glass being installed in Athletics Vestibule
Millwork being installed in the Chemistry Labs on level 3
Millwork being installed in the Chemistry Labs on level 3
Millwork being installed in the Chemistry Labs on level 3
Millwork being installed in the Chemistry Labs on level 3
Grid installed and fixed glass walls in progress in Level 3 classroom group
Grid installed and fixed glass walls in progress in Level 3 classroom group
Testing Center with drywall
Testing Center with drywall
Main Entrance Vestibule being framed in
Main Entrance Vestibule being framed in
Tile installed in the Administration Suite bathrooms
Tile installed in the Administration Suite bathrooms
Wall tile in Main Corridor on Level 2
Wall tile in Main Corridor on Level 2
Large soffits outside of classroom groups
framed and drywalled
Large soffits outside of classroom groups
framed and drywalled

Filed Under: Skyline

Status of Projects January 2024 – Skyline High School

January 2024

Updates:

Academics

  • Activity Stair steel has started in the Cafeteria Space
  • Curtain wall framing (Glass wall) has started around the exterior of the Cafeteria
  • Accent wall paint has started throughout the building
  • Tile is nearing completion in the Kitchen
  • Tile has started in main corridors on Level 2
  • Grid ceiling complete in Administration Suite
  • Athletics Lobby is now open to public for use, with some finishes that still need completing
  • Paint started on Level 3 of the main Academics Building
  • Structure completed on the stair tower on south end of the main Academics building

Recent Pictures:

View of the west side of the main Academics Building
Glass being installed at the northwest stair tower of the main Academics Building
Steel being installed for main staircase in
the Cafeteria
Curtain wall framing being installed on the south side of the Cafeteria
Tile installed in Culinary Arts classroom on Level 1
Tile being installed in the serving area of the Cafeteria
Metal panels being installed on the north side of the main Academics Building
Large soffits being framed in outside
of the classroom groups on level 2
LVT Flooring as it was being
installed in the Athletics Entrance
Media Center walls insulated, ready for sheetrock
Kitchen being painted above the tile, getting ready for finish equipment

Filed Under: Skyline

  • Page 1
  • Page 2
  • Page 3
  • Interim pages omitted …
  • Page 6
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2025 Granite School District

 

Loading Comments...