Skyline
Status of Projects August 2024 – Skyline High School
Updates:
Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete
Recent Pictures:
Status of Projects June 2024 – Skyline High School
Updates:
Academics
● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed
Recent Pictures:
Commons Area
Learning Staircase
flooring installed
Auditorium placed
Commons Space
Status of Projects April 2024 – Skyline High School
Updates:
Academics
● Ceiling cloud being installed in Cafeteria Area
● Stone cladding complete at Main Entrance
● Lighting installed in Cafeteria
● Glass installed in majority of classroom groups
● Carpet complete on Level 2
● LVT starting in corridors
● Tile started in group restrooms on north end of building on all floors
● Ceiling grid started on all floors
● Cabinetry started on Level 1
● Doors being installed throughout entire building
● Countertops installed in science labs on Level 3
● Restroom accessories being installed
Recent Pictures:
Level 1 restroom
Performing Arts
the Cafeteria
Skyline Construction Update Video – March 2024
Status of Projects March 2024 – Skyline High School
Updates:
Academics
●High ceiling in Cafeteria painted
●Exterior glass complete at Main Entrance
●Metal wood look soffits near completion in Cafeteria
●Storefront glass frames installed at Media Center
●Interior glass in classroom groups started
●Carpet and electrical trim started in Level 2 general classrooms
●Cabinet installation ongoing in Level 3 Science classrooms
●Painting on Level 2 near completion
●Main Corridor tile complete on Levels 2 and 3
●Tile at the Smoothie Bar complete
●Plumbing fixtures set in Administration Suite bathrooms
Recent Pictures:
Cafeteria/Commons
Status of Projects February 2024 – Skyline High School
Updates:
Academics
●Activity Stairs in the cafeteria are fully erected.
●Drywall and framing are nearing completion in the cafeteria area.
●All in-wall utilities are near completion throughout the entire building.
●Ceiling grid is being worked on in all general classrooms and is complete in the Administration Suite. ●Casework/cabinets are being installed in the lab classrooms on level 4.
●Fixed glass walls have started in the general classroom groups on level 3.
●Curtain wall glass is nearing completion on the Cafeteria.
●Testing Center is now drywalled and taped.
●Trophy shelving is being installed in the new Athletics Vestibule.
●Tile is nearing completion in the Administration bathrooms.
●Fire sprinkler systems are nearing completion on 3 floors.
●Framing in the south stair tower has started.
Recent Pictures:
framed and drywalled
Status of Projects January 2024 – Skyline High School
Updates:
Academics
- Activity Stair steel has started in the Cafeteria Space
- Curtain wall framing (Glass wall) has started around the exterior of the Cafeteria
- Accent wall paint has started throughout the building
- Tile is nearing completion in the Kitchen
- Tile has started in main corridors on Level 2
- Grid ceiling complete in Administration Suite
- Athletics Lobby is now open to public for use, with some finishes that still need completing
- Paint started on Level 3 of the main Academics Building
- Structure completed on the stair tower on south end of the main Academics building
Recent Pictures:
the Cafeteria
of the classroom groups on level 2
installed in the Athletics Entrance
Status of Projects December 2023 – Skyline High School
Recent Pictures:
on, ceiling tile being dropped.
painted, exterior door installed.
Status of Projects November 2023 – Skyline High School
Updates:
Site Work:
- Underground utility work nearing completion in the central courtyard
Academics:
- Cafeteria steel complete minus the activity stairs
- Glass on main Academics Building 90 percent complete
- Roof completed on the entire building
- Final paint started in the Administration Suite
- Athletics Vestibule life safety is complete, finishes (tile, paint, flooring) starting soon
- Drywall ongoing on all floors, 90 percent complete on the second floor
- In wall electrical, plumbing nearing completion on all floors
- Steel at the south stair tower nearing completion