Click on the links below to view recent photos of construction progress at Skyline High School. The photos are organized by month in reverse order.

Click on the links below to view recent photos of construction progress at Skyline High School. The photos are organized by month in reverse order.

What is the Project Status?
Students have been enjoying the fully-completed academics building and athletic facilities this school year (2024/2025).
The auditorium and remaining classrooms will be completed in time for the 2026/2027 school year. Some minor site, parking lot, and landscaping work will continue into the 2026/2027 school year.

Academics
● Punch list is ongoing
Performing Arts
● Tilt panels on the north of Performing Arts installed.
● Orchestra pit exterior foundation walls poured, damp proofed, and backfilling taking place.
● Stepped footings and foundation walls pouring on both sides of the orchestra pit.
● Conduits, underground plumbing, and underground HVAC continue to be installed.
● Footings formed and poured on the east side of the orchestra pit.
● Footings on the west side of the orchestra pit are being excavated and prepped for pouring.
● Perimeter gravel and pipe drain system being installed.











Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete












Academics
● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed














Academics
● Ceiling cloud being installed in Cafeteria Area
● Stone cladding complete at Main Entrance
● Lighting installed in Cafeteria
● Glass installed in majority of classroom groups
● Carpet complete on Level 2
● LVT starting in corridors
● Tile started in group restrooms on north end of building on all floors
● Ceiling grid started on all floors
● Cabinetry started on Level 1
● Doors being installed throughout entire building
● Countertops installed in science labs on Level 3
● Restroom accessories being installed















Academics
●High ceiling in Cafeteria painted
●Exterior glass complete at Main Entrance
●Metal wood look soffits near completion in Cafeteria
●Storefront glass frames installed at Media Center
●Interior glass in classroom groups started
●Carpet and electrical trim started in Level 2 general classrooms
●Cabinet installation ongoing in Level 3 Science classrooms
●Painting on Level 2 near completion
●Main Corridor tile complete on Levels 2 and 3
●Tile at the Smoothie Bar complete
●Plumbing fixtures set in Administration Suite bathrooms











Academics
●Activity Stairs in the cafeteria are fully erected.
●Drywall and framing are nearing completion in the cafeteria area.
●All in-wall utilities are near completion throughout the entire building.
●Ceiling grid is being worked on in all general classrooms and is complete in the Administration Suite. ●Casework/cabinets are being installed in the lab classrooms on level 4.
●Fixed glass walls have started in the general classroom groups on level 3.
●Curtain wall glass is nearing completion on the Cafeteria.
●Testing Center is now drywalled and taped.
●Trophy shelving is being installed in the new Athletics Vestibule.
●Tile is nearing completion in the Administration bathrooms.
●Fire sprinkler systems are nearing completion on 3 floors.
●Framing in the south stair tower has started.