• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List

Skyline

Skyline High Update – June 2026

June 2026

Area H (Classroom Wing):​

  • Classroom A/V and electrical punch work completed.Systems are functional with only a small list of correctiveitems remaining.​
  • Countertops have been installed in the main restroomson Levels 2 and 3.​
  • Corridor LVT installation is 95% complete, withremaining punch list items in progress.​
  • Wood paneling installation is complete.​
  • Construction cleaning in all areas is ongoing.​

Area I (Black Box):​

  • Black Box Theater bleachers are being installed.​
  • The Scenery Shop floor has been ground and cleaned.​
  • Cabinetry and shelving installations are complete.​
  • Construction cleaning in all areas is ongoing.​

Auditorium:​

  • The Fly Loft orchestra shell has been installed, andlighting is being wired.​
  • Control booth cabinetry has been installed.​
  • Interior finish carpentry in the Auditorium is complete.​
  • Seating installation began on May 18th.​

Area J (Performing Arts Entry):​

  • Entry wall graphics and display cases have beeninstalled. ​

Sitework / Demolition:​

  • Building demolition and abatement have been completed.During demolition of the Auditorium, a significant amountof underground transite piping was discovered. Throughcoordination between Hughes, A1 Abatement, and GSD,the affected areas were cleared daily, allowing thedemolition contractor to remain productive on site,completing the impacted areas ahead of schedule, andkeeping the project moving forward.​
  • Storm drainage chambers are being installed, along withconnections to all storm branch lines.​
  • South-side landscaping has been installed. Over theweekend the day after the grass was installed, a vehiclewas driven through the newly landscaped area, damagingsprinkler lines, sprinkler heads, and portions of the grass.Hughes responded quickly and completed all necessaryrepairs the following week.​
  • Courtyard sprinkler installation is complete, and the area isbeing prepared for grass installation.​
  • Handrails have been installed on the stairway leading tothe Seminary Building.​
  • Courtyard fence posts have been installed.​
  • Final grading activities are ongoing in preparation forasphalt and concrete work.​
  • Site utilities are being coordinated and tied into existing infrastructure.​
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)
Skyline progress (jpg)

Filed Under: Project Updates, Skyline

Skyline High Update – March 2026

April 2026

Academics:​

  • Punch list and warranty ongoing​

Performing Arts Demo:​

  • Interior asbestos abatement​
  • Exterior cement panel removal and disposal​

Performing Arts:​

  • Interior wall covering and lights installationongoing​
  • Classroom divisible accordion door installation​
  • Auditorium wall and stair light installation​
  • Black Box Theater flooring installation​
  • Air handler relocation and demo work​
  • School marquee concrete patching and touch up​
  • EV charging station installed​

Filed Under: Skyline

Skyline High Update – February 2026

February 2026

Academics:​

  • Punch list and warranty ongoing​

Performing Arts Demo:​

  • Asbestos abatement and utility management​

Performing Arts:​

  • Southeast parking concrete steps completed​
  • Exterior material installation ongoing​
  • Relocation of air handler to Mechanical Room​
  • Concrete floor preparation​
  • Blackbox Theater progress​
  • Corridor wall panel installation progress​
  • Band and Choral Room acoustical fabric wallpanels​
  • Auditorium wall paneling​
  • Auditorium soffit and light fixture installation​

Click here to see construction progress photos.

Filed Under: Skyline

Skyline Progress Photos

November 2025

Click on the links below to view recent photos of construction progress at Skyline High School. The photos are organized by month in reverse order.

  • February 2026
  • November 2025
  • September 2025
  • August 2025
  • July 2025
  • June 2025
  • May 2025
  • April 2025
  • March 2025
Skyline Auditorium

Filed Under: Project Updates, Skyline

Skyline High School Update

March 2025

What is the Project Status?

Students have been enjoying the fully-completed academics building and athletic facilities this school year (2024/2025).

The auditorium and remaining classrooms will be completed in time for the 2026/2027 school year. Some minor site, parking lot, and landscaping work will continue into the 2026/2027 school year.

Ribbon Cutting image.
Academics Building Ribbon Cutting

Filed Under: Skyline

Status of Projects November 2024 – Skyline High School

November 2024

Updates:

Academics
● Punch list is ongoing

Performing Arts
● Tilt panels on the north of Performing Arts installed.
● Orchestra pit exterior foundation walls poured, damp proofed, and backfilling taking place.
● Stepped footings and foundation walls pouring on both sides of the orchestra pit.
● Conduits, underground plumbing, and underground HVAC continue to be installed.
● Footings formed and poured on the east side of the orchestra pit.
● Footings on the west side of the orchestra pit are being excavated and prepped for pouring.
● Perimeter gravel and pipe drain system being installed.

Recent Pictures:

Performing Arts tilt wall being lifted into place
Performing Arts tilt wall being lifted into place
Forming orchestra pit foundation
Forming orchestra pit foundation
Preparing orchestra pit foundation for concrete
Preparing orchestra pit foundation for concrete
Orchestra pit foundation poured and preparing for backfill
Orchestra pit foundation poured and preparing for backfill
Electrical conduits east of the orchestra pit
Electrical conduits east of the orchestra pit
Electrical conduits north of the orchestra pit
HVAC installation north of the orchestra pit
HVAC installation north of the orchestra pit
Plumbing installation south of the orchestra pit
Plumbing installation south of the orchestra pit
Footings preparation East of the orchestra pit
Footings preparation East of the orchestra pit
Pouring concrete footings East of the orchestra pit
Pouring concrete footings East of the orchestra pit
Testing Center in use
Testing Center in use

Filed Under: Skyline

Skyline High Safety Tour – August 2024

August 2024

Filed Under: Project Updates, Skyline

Status of Projects August 2024 – Skyline High School

August 2024

Updates:

Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete

Recent Pictures:

Graphic in Hallway leading to Athletics Building
Graphic in Hallway leading to Athletics Building
Main Entrance with metal panels complete
Main Entrance with metal panels complete
World map graphic in Counseling reception area
World map graphic in Counseling reception area
Special Education classroom progress
Special Education classroom progress
Sewing lab classroom nearing completion
Sewing lab classroom nearing completion
Teacher equipment installation in Ceramics
Teacher equipment installation in Ceramics
Teacher’s Lounge near Administration Suite
Teacher’s Lounge near Administration Suite
Finishes in Level 2 corridor
Finishes in Level 2 corridor
Relocatables set in west parking lot
Relocatables set in west parking lot
Serving line equipment being set
Serving line equipment being set
Demolition of old Academics building
Demolition of old Academics building
Teacher collaboration near Level 2 Media Center
Teacher collaboration near Level 2 Media Center

Filed Under: Skyline

Status of Projects June 2024 – Skyline High School

June 2024

Updates:

Academics

● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved   into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed

Recent Pictures:

View of Academics from Central Courtyard
View of Academics from Central Courtyard
Furniture installation in Administration
Furniture installation in Administration
Furniture installed in Career Center
Furniture installed in Career Center
Classroom with student desks installed
Classroom with student desks installed
Large format tile installation in Serving Area
Large format tile installation in Serving Area
LVT flooring installation in the
Commons Area
LVT flooring installation in the
Commons Area
Men’s restroom on Level 2
Men’s restroom on Level 2
Pre-cast stairs installed on the
Learning Staircase
Pre-cast stairs installed on the
Learning Staircase
Science classroom with rubber
flooring installed
Science classroom with rubber
flooring installed
LVT flooring installed in Main L2 Corridor
LVT flooring installed in Main L2 Corridor
Temporary pathway around the old
Auditorium placed
Temporary pathway around the old
Auditorium placed
Circular seating placed in Central Courtyard
Circular seating placed in Central Courtyard
Manufacturing Lab with equipment being set
Manufacturing Lab with equipment being set
Wood accent wall installation in Level 2
Commons Space
Wood accent wall installation in Level 2
Commons Space

Filed Under: Skyline

Status of Projects April 2024 – Skyline High School

April 2024

Updates:

Academics

● Ceiling cloud being installed in Cafeteria Area
● Stone cladding complete at Main Entrance
● Lighting installed in Cafeteria
● Glass installed in majority of classroom groups
● Carpet complete on Level 2
● LVT starting in corridors
● Tile started in group restrooms on north end of building   on all floors
● Ceiling grid started on all floors
● Cabinetry started on Level 1
● Doors being installed throughout entire building
● Countertops installed in science labs on Level 3
● Restroom accessories being installed

Recent Pictures:

Cabinets in Special Education Classroom
Cabinets in Special Education Classroom
Cabinets installed in the Administration Suite Workroom
Cabinets installed in the Administration Suite Workroom
Tile and storefront being installed in
Level 1 restroom
Tile and storefront being installed in
Level 1 restroom
LVT flooring and glass installed in Fix-It Room by the Media Center on Level 2
LVT flooring and glass installed in Fix-It Room by the Media Center on Level 2
Stone cladding at the Main Entrance
Stone cladding at the Main Entrance
Stair tower connecting Academics to
Performing Arts
Stair tower connecting Academics to
Performing Arts
Teacher’s Lounge cabinets and accent paint
Teacher’s Lounge cabinets and accent paint
Countertops installed in Level 3 science labs
Countertops installed in Level 3 science labs
Plumbing fixtures and accessories installed in Administration Suite restroom
Plumbing fixtures and accessories installed in Administration Suite restroom
High ceiling clouds being installed in
the Cafeteria
High ceiling clouds being installed in
the Cafeteria
Glass installed at the Level 2 classrooms
Glass installed at the Level 2 classrooms
Wood-look acoustical ceiling grid outside of Level 2 Media Center
Wood-look acoustical ceiling grid outside of Level 2 Media Center
Northwest property line by Softball Fields
Northwest property line by Softball Fields
Stairway into the gully
Stairway into the gully
Gully
Gully

Filed Under: Skyline

  • Page 1
  • Page 2
  • Page 3
  • Interim pages omitted …
  • Page 7
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

 

Loading Comments...