Status of Projects April 2024 – Cyprus High School
Updates:
Building Exterior:
● Glass installation at the Auditorium
● Glass installation at Academics
Athletics/Pool:
● Pool excavation/footings
● Tile in Pool locker rooms
● Ceiling tile in Athletics Vestibule
● Tectum panels in Weight Room
Administration/Commons:
● Slab on grade in Cafeteria Area of Commons
● Level 1 framing and HVAC in Administration
● Level 2 and 3 framing
Academics/Social Studies:
● Framing Level 2
● Framing and electrical Level 3
Performing Arts:
● Drywall on the Proscenium
● Paint and framing in Scenery Shop
Recent Photos:
Status of Projects March 2024 – Cyprus High School
Updates:
Site Work/Mechanical Yard:
●Footings/foundation at the Softball, Baseball Field
●Setting the generators into place
Athletics/Pool:
●Track Handrail Shoe
●Locker being placed in the PE Locker Rooms
●Pool painting
●Window caulking
Administration/Commons:
●Level 3 framing
●Level 1 slab on grade pour
●Prepping slab on grade in the Public Square/Dining
Academics/Social Studies:
●Framing of classrooms and display cases
●Drywall around the skylights
●Frames and glazing on the stair tower
●Finish paint on Levels 2 and 3
Performing Arts:
●Curtain wall and glazing around the Lobby
Recent Photos:
Academics Building
the Academics Building
Status of Projects February 2024 – Cyprus High School
Updates:
Site Work:
●Planter boxes behind the home side bleachers and between Athletics and Administrative Suite
●Fencing fabric stretched between posts
●Visitor side bleachers under construction
Athletics:
● Tile in the restrooms
Pool:
●Painting
Mechanical Yard:
● Slab on grade
● Set steel
Administration:
● Slab under electric
Academics:
● Paint on 2nd and 3rd levels
● Skylights in corridor
Social Studies:
● Rough Plumbing on levels 2 and 3
● Painting accent walls and classrooms
Performing Arts:
● Painting on the stage and scenery storage
● Ceiling grid in the Band room
Recent Photos:
Administrative Suite
Cyprus High Construction Update Video
Status of Projects January 2024 – Cyprus High School
Updates:
Site Work:
● Fencing and flat work on the North side of the site
Athletics:
● Drops ceiling grid level 1 of athletics
Pool:
●Locker room framing, drywall and plumbing
●Tile in the lifeguard room
Mechanical Yard:
● Tilt walls stood in place
● Steel erection
CTE Buildings:
● Steel stud and metal decking on the breezeway
Academics:
● Paint and drywall 2nd and 3rd levels
● Exterior kiln walls stood into place
● Testing center cement poured
Social Studies:
● Curtain wall glass installation
● Drywall and insulation 2ndand 3rdfloor
Performing Arts:
● Vestibule curtain wall installation
● Concrete pour backs in the vestibule area
Recent Photos:
Status of Projects December 2023 – Cyprus High School
Updates:
Site Work:
● Asphalt paving Southwest parking lot
Athletics:
● Drop ceiling grid, light installation level 1
● 2ndlevel bathroom tile
Pool:
●Locker room framing, drywall and plumbing
●Acid etched glass installed
CTE Buildings:
● Tilt panels connecting CTE building with the main building
Administration:
● Drywall 3rd and 4th floor
Cafeteria/Common Area:
● Skylight on the 3rd floor
Social Studies:
●Framing 3rd and 4th floor
●Rough electrical 3rd and 4th floor
●Air handler set on the 4th floor
Performing Arts:
● Fin tube heaters set into place
● Dressing room framing
Recent Photos:
Status of Projects November 2023 – Cyprus High School
Updates:
Site Work:
● Asphalt paved on the North end of the site
● Asphalt prep for the Southwest parking lot
● Outbuildings concrete floors poured
Athletics:
● Basketball standards installed
● Tile in the PE locker rooms
Pool:
● Locker room framing and plumbing
CTE Buildings:
● Tilt panels stood into place
Administration:
● Framing drywall throughout classroom spaces
Social Studies:
● Exterior glass installed
● Exterior framing
Cafeteria/Common Area:
● Level 3 concrete floor poured
● Exterior framing
Performing Arts:
● HVAC in corridors and Scenery/shop storage
● Glass installation in the Choral and Band room
Recent Photos:
Status of Projects October 2023 – Cyprus High School
Updates:
Site Work:
● Curbing and asphalt prep at the North end of the site
● Football stadium footings have been poured
● Light poles have been installed throughout the North end of the site
Athletics:
● Tile and waterproofing on-going in the PE Locker rooms
● Glass installation in the vestibule
● Glass installation in the Weight room
● Paint in the Dance room
Pool:
● Gallery seating has been poured on the observation deck
● Concrete floors in the locker room area
Administration:
● Steel erection
Academics:
● Framing, electrical rough in throughout classroom spaces
● Cement floors on levels 2,3 and 4.
● Steel stud erection and metal decking
Performing Arts:
● Projector booth concrete has been poured
● Orchestra steps have been formed and poured
Recent Photos:
observation deck of the pool
Status of Projects September 2023 – Cyprus High School
Updates:
Site Work:
- Ongoing site grading is in progress
- Football stadium storage tilt panels raised into position
- Light pole bases have been installed on the north side of the site
Athletics:
- Tile and waterproofing in the public restrooms and coaches’ office ongoing
- PE Locker rooms’ ceiling and paint have been completed
- Curtain walls for the vestibule and wrestling room installed
- Drywall installation is ongoing in the dance room
- Wrestling room benches have been completed
Pool:
- Seating structures have been formed, and cement pouring by sections
Academics:
- Stairs going from athletics to academics and 3rd to 4th floor
- Framing/HVAC on the fourth floor is ongoing
- Steel erection and metal decking are ongoing in the testing center
Performing Arts:
- Framing for the projector room is ongoing
- Scaffolding set in the auditorium for finishes to start
- Concrete poured on the third level of the upper lobby in the auditorium
Recent Photos:
- 1
- 2
- 3
- …
- 5
- Next Page »