GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects May 2023 – Cyprus High School

May, 2023 by Granite School District Communications Office

Panels leading to the auditorium continue to be tilted into place.

Trusses have been set in place above the drama studio/black box theater.

Mezzanine on the third floor has been placed, additional cat walks and storage areas have been fabricated. Stairs have been fabricated between the third and fourth floor mezzanine.

Air handlers have also been placed on the third floor. Underground utilities have been laid out to be buried and have utilities run through them. Cast in place concrete walls are being formed.

Panels and steel decking for the academics area is being tilted and secured in place. Decking has been completed on the second and third floor. Fabricators are working on the roof of the academics building.

Framing for ceiling hard lid has been fabricated in the basement of the gymnasium. Insulation is currently being installed in the basement and second level of the track and gymnasium area. Exhaust fan plumbing has been installed in the team rooms and bathrooms. Air exchanger has been installed and HVAC continues to be installed in the basement. Roof drains have been installed in the gymnasium and in the pool area.

Cyprus C has been formed and is curing.




Panels being placed leading up to the auditorium and the trusses being placed over the drama theater.



Panels being placed leading up to the auditorium and the trusses being placed over the drama theater.



Concrete on the third-floor mezzanine and stairs leading from the third to fourth floor mezzanine.



Concrete on the third-floor mezzanine and stairs leading from the third to fourth floor mezzanine.
Air handlers being placed on the third floor of the auditorium.
Air handlers being placed on the third floor of the auditorium.
Catwalks in the auditorium and underground utilities being placed. 
Catwalk in the corridor of the auditorium. Cast in place concrete walls in the auditorium .
Catwalk in the corridor of the auditorium. Cast in place concrete walls in the auditorium .
Steel decking in the academic’s area. Roof of academics building being installed. 
Steel decking in the academic’s area. Roof of academics building being installed. 
Insulation and hard lid ceiling being installed in the basement of the gymnasium.
Insulation and hard lid ceiling being installed in the basement of the gymnasium.
Exhaust fans in the restrooms and team rooms. Industrial air exchanger in the basement of the gymnasium.  
Exhaust fans in the restrooms and team rooms. Industrial air exchanger in the basement of the gymnasium.  
Roof drains in the gymnasium and pool area.
The Cyprus “C”that is going on the outside of the drama studio.

Filed Under: Cyprus

Status of Projects April 2023 – Cyprus High School

April, 2023 by Granite School District Communications Office

Cyprus High School
Building Construction

Kitchen panels have been erected creating a corridor between athletics and academics. A lecture hall and mechanical room will come off either side of the corridor and the lecture hall will be the next panel erected.

Auditorium – three of the walls have been raised and braced so that heavy equipment can come and go from the area. Steel decking has been installed on the upper levels creating walkable areas.Concrete has been placed on the stage and the landing leading up to the stage. Concrete is currently curing and is covered by tarps.Dressing area/storage has been raised and braced. This area will serve as storage of the performing arts.

Academics structure has been installed and two tilt panels have been raised around the structure. A double decker air handler system will be installed to service the area. Remaining tilt panels are curing, these will be installed on the north side of the structure. Elevator shaft has been erected and braced. This is the only elevator shaft that is tilt up on three sides in the building. This will service all three floors for academics.

Drywall in the basement of gymnasium has progressed to 90%. Masonry work has been completed in the basement of athletics. Copper and steel weld piping have been placed and have passed inspections. Window frames have been installed in athletics. Glass has been ordered and will be installed in the next couple of weeks.




Panels in academics and the elevator shaft.



Auditorium walls and concrete placed on the stage.



Auditorium walls and concrete placed on the stage.



Steel decking and raised walls for dressing area.



Steel decking and raised walls for dressing area.



Structure for academics and remaining tilt panels.



Structure for academics and remaining tilt panels.



Drywall in the team rooms and window frames in athletics.



Drywall in the team rooms and window frames in athletics.



Masonry walls and the copper piping.



Masonry walls and the copper piping.



Panels in academics and the elevator shaft.

Filed Under: Cyprus, Project Updates

Status of Projects March 2023 – Cyprus High School

March, 2023 by Granite School District Communications Office

Cyprus High School
Building Construction

Auditorium roofing, steel in ceilings and back of house 2nd and 3rd floor continues.
Gymnasium and locker rooms have drywall being installed on one side of metal studs.
Electrical, fire sprinkler/alarm and plumbing continues in the locker rooms and gymnasium.
Gymnasium masonry on stairway walls and under the dance room as well as moving up to pool loft and locker rooms.
Pool roof decking installed, and roofing started. Observation upper deck installed.
Tilt walls for choral and band area have been stood. Steel moving to choral area soon.

Band and choral walls in place
Band and choral walls in place
Auditorium steel
Auditorium steel
HVAC ducting over gymnasium
HVAC ducting over gymnasium
Framing and spray foam insulation
Framing and spray foam insulation
Last section of track being placed
Last section of track being placed
Drywall on one side of metal studs in locker room/changing rooms
Drywall on one side of metal studs in locker room/changing rooms
Masonry below dance room
Masonry below dance room
Ducting to air handlers
Ducting to air handlers
Pool upper observation area decking installed
Pool upper observation area decking installed
Pool trusses installed
Pool trusses installed
Site overview
Site overview

Filed Under: Cyprus, Project Updates

Status of Projects February 2023 – Cyprus High School

February, 2023 by Granite School District Communications Office

Cyprus High School
Building Construction

Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.

Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Framing mechanical room
Framing mechanical room
Framing bathrooms
Framing bathrooms
Roof steel decking
Roof steel decking
Auditorium cloud steel
Auditorium cloud steel
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Site Overview
Site Overview

Filed Under: Cyprus, Project Updates

Status of Projects January 2023 – Cyprus High School

January, 2023 by Granite School District Communications Office

Cyprus High School
Building Construction

Auditorium steel trusses, cross bracing and the catwalk are all being installed.
More auditorium tilt panels being prepped to be placed.
Gymnasium steel decking is done around the running track and ½ the concrete has been placed for the track.
Gymnasium floor is being prepped for concrete.
The cardio & wrestling room is being framed, along with HVAC and rough electrical being installed.

Auditorium roof decking and catwalk
Auditorium roof decking and catwalk
Cardio room rough in
Cardio room rough in
Gymnasium stairs
Gymnasium stairs
Gym floor being prepped for concrete
Gym floor being prepped for concrete
Windows have been sealed waiting for frames
Windows have been sealed waiting for frames

Filed Under: Cyprus, Project Updates

Status of Projects November 2022 – Cyprus

November, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls

Filed Under: Cyprus, Project Updates

Status of Projects October 2022 – Cyprus

October, 2022 by Granite Schools

Cyprus High School: Site Preparation

Site preparation is 100% complete.
Mass grading has been completed.
Kennecott site storm water drainage redirection project is completed.

Cyprus Site Work
Cyprus Site Work
Cyprus Site Work
Cyprus Site Work

Cyprus High School: Building Construction

Purchase order was issued to Westland Construction for construction of the new Cyprus High School.
Notice to proceed issued 09/13/2021.
Excavation of footings has begun.

Cyprus Footings
Cyprus Footings
Cyprus Footings
Cyprus Footings

Filed Under: Cyprus, Project Updates

August 2022 Construction Photos

August, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site

Skyline High School

Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site

West Lake STEM Junior High

West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site

Cottonwood High Auditorium Control Booth

Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction

Granite Technical Institute Third Floor Labs

GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction

Security Upgrades

Hartvigsen security upgrade construction
Hartvigsen School
Hartvigsen security upgrade construction
Hartvigsen School
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
William Penn security upgrade construction
William Penn Elementary

Turf Fields

Granger High turf field replacement
Granger High School
Granger High turf field replacement
Granger High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School

Filed Under: Cyprus, Project Updates, Skyline, West Lake

Status of Projects August 2022 – Cyprus

August, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall work continues.
Geothermal drilling continues.
Auditorium tilt walls are being framed with structural steel.
Gymnasium and pool walls have been poured and will be stood into place by the first of August.

Foundation and orchestra pit walls
Foundation and orchestra pit walls
Geothermal drilling continues
Geothermal drilling continues
Steel trusses being delivered and stored on-site
Steel trusses being delivered and stored on-site
Steel door frames being delivered and stored on-site
Steel door frames being delivered and stored on-site
Retaining wall continues around front of site
Retaining wall continues around front of site

Filed Under: Cyprus, Project Updates

July 2022 Construction Photos

July, 2022 by Granite School District Communications Office

Granite Technical Institute – Pharmacy and Animation Labs

Granite Technical Institute construction area
Granite Technical Institute construction area
Granite Technical Institute construction area

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site

West Lake STEM Jr High

West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site

Filed Under: Cyprus, Skyline, West Lake

  • 1
  • 2
  • 3
  • 4
  • Next Page »
 

Loading Comments...