GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects March 2023 – Cyprus High School

March, 2023 by Matthew Sampson

Auditorium roofing, steel in ceilings and back of house 2nd and 3rd floor continues.
Gymnasium and locker rooms have drywall being installed on one side of metal studs.
Electrical, fire sprinkler/alarm and plumbing continues in the locker rooms and gymnasium.
Gymnasium masonry on stairway walls and under the dance room as well as moving up to pool loft and locker rooms.
Pool roof decking installed, and roofing started. Observation upper deck installed.
Tilt walls for choral and band area have been stood. Steel moving to choral area soon.

Band and choral walls in place
Band and choral walls in place
Auditorium steel
Auditorium steel
HVAC ducting over gymnasium
HVAC ducting over gymnasium
Framing and spray foam insulation
Framing and spray foam insulation
Last section of track being placed
Last section of track being placed
Drywall on one side of metal studs in locker room/changing rooms
Drywall on one side of metal studs in locker room/changing rooms
Masonry below dance room
Masonry below dance room
Ducting to air handlers
Ducting to air handlers
Pool upper observation area decking installed
Pool upper observation area decking installed
Pool trusses installed
Pool trusses installed
Site overview
Site overview

Filed Under: Cyprus, Project Updates

Status of Projects February 2023 – Cyprus High School

February, 2023 by Matthew Sampson

Cyprus High School
Building Construction

Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.

Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Framing mechanical room
Framing mechanical room
Framing bathrooms
Framing bathrooms
Roof steel decking
Roof steel decking
Auditorium cloud steel
Auditorium cloud steel
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Site Overview
Site Overview

Filed Under: Cyprus, Project Updates

Status of Projects January 2023 – Cyprus High School

January, 2023 by Matthew Sampson

Cyprus High School
Building Construction

Auditorium steel trusses, cross bracing and the catwalk are all being installed.
More auditorium tilt panels being prepped to be placed.
Gymnasium steel decking is done around the running track and ½ the concrete has been placed for the track.
Gymnasium floor is being prepped for concrete.
The cardio & wrestling room is being framed, along with HVAC and rough electrical being installed.

Auditorium roof decking and catwalk
Auditorium roof decking and catwalk
Cardio room rough in
Cardio room rough in
Gymnasium stairs
Gymnasium stairs
Gym floor being prepped for concrete
Gym floor being prepped for concrete
Windows have been sealed waiting for frames
Windows have been sealed waiting for frames

Filed Under: Cyprus, Project Updates

Status of Projects November 2022 – Cyprus

November, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls

Filed Under: Cyprus, Project Updates

Status of Projects October 2022 – Cyprus

October, 2022 by Granite Schools

Cyprus High School: Site Preparation

Site preparation is 100% complete.
Mass grading has been completed.
Kennecott site storm water drainage redirection project is completed.

Cyprus Site Work
Cyprus Site Work
Cyprus Site Work
Cyprus Site Work

Cyprus High School: Building Construction

Purchase order was issued to Westland Construction for construction of the new Cyprus High School.
Notice to proceed issued 09/13/2021.
Excavation of footings has begun.

Cyprus Footings
Cyprus Footings
Cyprus Footings
Cyprus Footings

Filed Under: Cyprus, Project Updates

August 2022 Construction Photos

August, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site

Skyline High School

Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site

West Lake STEM Junior High

West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site

Cottonwood High Auditorium Control Booth

Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction

Granite Technical Institute Third Floor Labs

GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction

Security Upgrades

Hartvigsen security upgrade construction
Hartvigsen School
Hartvigsen security upgrade construction
Hartvigsen School
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
William Penn security upgrade construction
William Penn Elementary

Turf Fields

Granger High turf field replacement
Granger High School
Granger High turf field replacement
Granger High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School

Filed Under: Cyprus, Project Updates, Skyline, West Lake

Status of Projects August 2022 – Cyprus

August, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall work continues.
Geothermal drilling continues.
Auditorium tilt walls are being framed with structural steel.
Gymnasium and pool walls have been poured and will be stood into place by the first of August.

Foundation and orchestra pit walls
Foundation and orchestra pit walls
Geothermal drilling continues
Geothermal drilling continues
Steel trusses being delivered and stored on-site
Steel trusses being delivered and stored on-site
Steel door frames being delivered and stored on-site
Steel door frames being delivered and stored on-site
Retaining wall continues around front of site
Retaining wall continues around front of site

Filed Under: Cyprus, Project Updates

July 2022 Construction Photos

July, 2022 by Granite School District Communications Office

Granite Technical Institute – Pharmacy and Animation Labs

Granite Technical Institute construction area
Granite Technical Institute construction area
Granite Technical Institute construction area

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site

West Lake STEM Jr High

West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site

Filed Under: Cyprus, Skyline, West Lake

June 2022 Construction Photos

June, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site

West Lake STEM Junior High

West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site

Filed Under: Cyprus, Skyline, West Lake

Status of Projects June 2022 – Cyprus

June, 2022 by Granite Schools

Cyprus High School
Building Construction

Tilt panels for gymnasium have been cast in concrete.
Pool foundation walls are complete.
Other foundation walls are being formed now and waiting for reinforcing steel.
Auditorium and stage walls have been formed, scheduled to pour 6/6/22
Underground electrical in kitchen area is being installed for transformers and generators.
All casting slabs for tilt walls are in place.
Crane and crane paths are in place, in preparation for standing tilt walls which is expected to begin late June.

Cyprus Campus
Cyprus Campus
Electrical conduits from transformers/generators
Electrical conduits from transformers/generators
Fire hydrant in mechanical yard
Fire hydrant in mechanical yard
Casting slab for tilt panels
Casting slab for tilt panels
Athletics and pool panels being prepped
Athletics and pool panels being prepped
Mockup panel
Mockup panel
Preparation for tilt panels
Preparation for tilt panels
Preparation for tilt panels
Preparation for tilt panels
Main underground electrical
Main underground electrical
Geothermal drilling, 80 holes have been drilled
Geothermal drilling, 80 holes have been drilled
Swimming pool area
Swimming pool area

Filed Under: Cyprus, Project Updates

  • 1
  • 2
  • 3
  • 4
  • Next Page »
 

Loading Comments...