West Lake STEM Junior High School
Building Construction
Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.