Status of Projects April 2024 – West Lake STEM
Updates:
- Permanent power to the site is connected. Exterior glazing is 95% complete. The two rooftop air handling units serving the Gymnasium have arrived
- In the Athletic Wing and the Kitchen, the electrical rough-in is 75% complete. The floor and wall tile are also 75% complete.
- The stage rigging in Performing Arts is being installed.
- In the CTE Wing, the mechanical, electrical, plumbing installation and the interior paint work is moving forward.
- The Academic and Administration Wings are progressing with cabinetry installation. The diffusers and grills are 85% complete.
Status of Projects March 2024 – West Lake STEM
Updates:
- The three Academic wings are having countertops installed on cabinets, sinks installed in the restrooms, and wiring and sensors placed in the ceilings.
- The Administration wing has cabinets ready to be installed.
- The Serving area has decorative wall tile being installed.
- HVAC ducts are 90% complete.
Status of Projects February 2024 – West Lake STEM
Updates:
- The three Academic wings have cabinetry, ceiling grid, electrical, and mechanical systems in place
- The Administration wing has been painted and ceiling grid installation is in progress.
- The CTE wing has interior windows installed and ceiling grid installation is in progress.
- Wall tile in corridors and restrooms is 85% complete.
Auditorium ceiling
West Lake STEM Jr. High Construction Tour
Status of Projects January 2024 – West Lake STEM
Updates:
- Glass installation at perimeter of building continues and is over 75% complete.
- Installation of interior finishes such as tile, paint, and ceiling grid with light fixtures continues.
- Final portion of interior slab on grade at north end of commons area has been placed.
Status of Projects December 2023 – West Lake STEM
Updates:
- Roofing membrane is complete, waiting on metal flashing and wall caps to be completed
- Two Rooftop air handling units have been placed.
- Glass is being installed around the perimeter of the building.
- Installation of interior finishes such as tile and paint continue.
- Concrete floor in the auditorium has been placed.
- Millwork, overhead doors, and ceiling grids are being installed in the classrooms.
- Kitchen framing is complete and drywall has begun.
Status of Projects November 2023 – West Lake STEM
Updates:
- Roofing is 90% complete.
- Glass is being installed around the perimeter of the building.
- Installation of interior finishes such as tile and paint continue.
- Landscaping has begun in the area east of the school.
- Rough grading of the athletic field has been completed and the running track is paved and striped.
- Parking, bus, and fire lane paving is complete.
- Millwork, overhead doors, and ceiling grids are being installed in the classrooms.
Status of Projects October 2023 – West Lake STEM
Updates:
- Roofing is 75% complete.
- Glass is being installed around the perimeter of the building.
- Installation of interior finishes such as tile and paint continue.
- Landscaping has begun in the area east of the school.
- Rough grading of the athletic field and running track is progressing.
Status of Projects May 2023 – West Lake STEM
Rough-ins in three of the academic wings are nearly complete, roofing has begun, and drywall will begin soon.
Decking for running track in gymnasium is being installed.
Interior masonry walls in auditorium are in progress.
Structural masonry is mostly complete and veneer facing is in progress.
Brick veneer facing on gymnasium.
Masonry walls for service courtyard.
Interior metal stud framing in academics.
Running track in gymnasium.
Acoustic roof decking over commons corridor.
Roofing trusses over choral room.
Interior masonry walls in auditorium.
Brick veneer facing on gymnasium.