West Lake
Status of Projects June 2024 – West Lake STEM
Updates:
- Administrative staff has moved in.
- Furniture and appliance delivery continues.
- We are moving in and setting up classrooms.
Recent Pictures:
West Lake Construction Update – June 2024
Status of Projects June 2024 – West Lake STEM
Updates:
- Grading, landscaping, irrigation piping, and site concrete installation continues.
- Exterior finishes are approximately 90% complete.
- Interior finishes in the Science and Academic Wings are 75% complete.
- Interior finishes in the Auditorium and CTE Wings are 50% complete.
installed
West Lake STEM Jr. High Construction Tour – April 2024
Status of Projects April 2024 – West Lake STEM
Updates:
- Permanent power to the site is connected. Exterior glazing is 95% complete. The two rooftop air handling units serving the Gymnasium have arrived
- In the Athletic Wing and the Kitchen, the electrical rough-in is 75% complete. The floor and wall tile are also 75% complete.
- The stage rigging in Performing Arts is being installed.
- In the CTE Wing, the mechanical, electrical, plumbing installation and the interior paint work is moving forward.
- The Academic and Administration Wings are progressing with cabinetry installation. The diffusers and grills are 85% complete.
Status of Projects March 2024 – West Lake STEM
Updates:
- The three Academic wings are having countertops installed on cabinets, sinks installed in the restrooms, and wiring and sensors placed in the ceilings.
- The Administration wing has cabinets ready to be installed.
- The Serving area has decorative wall tile being installed.
- HVAC ducts are 90% complete.
Status of Projects February 2024 – West Lake STEM
Updates:
- The three Academic wings have cabinetry, ceiling grid, electrical, and mechanical systems in place
- The Administration wing has been painted and ceiling grid installation is in progress.
- The CTE wing has interior windows installed and ceiling grid installation is in progress.
- Wall tile in corridors and restrooms is 85% complete.
Auditorium ceiling
West Lake STEM Jr. High Construction Tour
Status of Projects January 2024 – West Lake STEM
Updates:
- Glass installation at perimeter of building continues and is over 75% complete.
- Installation of interior finishes such as tile, paint, and ceiling grid with light fixtures continues.
- Final portion of interior slab on grade at north end of commons area has been placed.