• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Skyline

Status of Projects December 2023 – Skyline High School

December 2023

Recent Pictures:

Aerial photo of main Academics building, taken from the east.
Stair tower steel progress where the Academics and the Performing Arts Buildings meet.
Interior of the Athletics Vestibule. Lights
on, ceiling tile being dropped.
Hard lid ceilings being framed on level 2 outside of general classrooms. Walls are painted and walls ready for tile.
Main Kitchen with tile on walls and hood equipment mounted on walls.
Curtain wall glass being installed at north stair tower where Athletics and Academics connect.
Skylights getting drywall hung on level 3.
Teacher’s Lounge accent colors
painted, exterior door installed.
Media Center walls framed and ready for drywall.

Filed Under: Skyline

Status of Projects November 2023 – Skyline High School

November 2023

Updates:

Site Work:

  • Underground utility work nearing completion in the central courtyard

Academics:

  • Cafeteria steel complete minus the activity stairs
  • Glass on main Academics Building 90 percent complete
  • Roof completed on the entire building
  • Final paint started in the Administration Suite
  • Athletics Vestibule life safety is complete, finishes (tile, paint, flooring) starting soon
  • Drywall ongoing on all floors, 90 percent complete on the second floor
  • In wall electrical, plumbing nearing completion on all floors 
  • Steel at the south stair tower nearing completion
Main Academics Building, as seen from the west parking lot
Stair tower steel progress where the Academics and the Performing Arts Buildings meet
Concrete paving in the Art Yard on the southwest side of the Academics Building
Accent walls and final paint in the Administration Suite
Classroom pod adjacent to the new cafeteria, level 2. Drywall nearing completion
Eagle’s Head that was salvaged from the old gymnasium, now installed in the new Athletics Vestibule
Athletics Vestibule, ready for wall finishes to start. Trophy Case framing on the left of the photo
Freezers/Coolers being set in the new Kitchen area.
Level 2 main corridor. Drywall nearing completion
Roof complete over the main cafeteria space
Main entrance to the building sheeted and ready for exterior finishes.

Filed Under: Skyline

Status of Projects October 2023 – Skyline High School

October 2023

Updates:

Site Work:

  • West parking lot has been paved and striped
  • Retaining walls are complete

Academics:

  • Cafeteria and study hall steel is complete minus the main staircase
  • Administration suite is nearing completion with drywall
  • Roof is being completed above the cafeteria area
  • Glass is going in on the remaining openings on the east side of the building
  • Framing is nearing completion on all floors in the main building
  • Rough in-wall electrical and plumbing has started on the second and third floors, and is almost complete on the second floor
  • Canopies for the manufacturing yard and the art yard have been erected
  • The athletics vestibule is starting drywall and will be weather tight by the end of this week
View of the entire project from the northwest. The central building in the photo is the Academics phase
View of the entire project from the southeast.
Completed west parking lot with striping
Canopy over the new manufacturing yard with some of the equipment set
Glass going into the large openings on the south-east side of the Academics Building
New air handlers on level 4 getting final duct connections
Concrete stem wall that goes below the grand staircase in the cafeteria
Concessions in the Athletics Lobby.
New slab and tilt panel where Academics transitions to the Performing Arts Building
Framing progress in the Ceramics Lab on Level 2
Typical drywall progress on levels 3 and 4 in the General Classrooms
Main Entrance and New Athletic Entrance

Filed Under: Skyline

Status of Projects September 2023 – Skyline High School

September 2023

Academics Phase Updates:​

  • Preparation for asphalt paving in the west lot the first week of September. ​
  • Retaining walls are nearly complete and curb and gutter is being poured. ​
  • The Cafeteria and Study Hall steel is nearing completion. ​
  • Framing is nearly complete in the main Academics building and drywall has started.​
  • In the north administration suite, they have started taping and finishing the drywall.​
  • Window frames have gone into most of the small openings. The larger openings started getting frames this week. ​
  • Overhead duct work, plumbing and electrical is almost complete in the Academics building and in wall rough in has started in most areas where framing is done. ​
  • The Manufacturing Lab block walls are installed and finishes will start in that area. The larger equipment has been loaded into the area and steel has started on the yard portion.​

Recent Photos:

View of the entire project from the west, the central building in the photo is the Academics phase
View of the entire project from the southeast, the large metal roof is the cafeteria (level 2) and the Study Hall (level 3)​
Manufacturing lab block is complete on level 1​
Manufacturing lab yard slab being placed and finished with prep started for steel erection​
View of the Athletics building lobby, metal panels and window frame install is almost complete​
Typical progress of an office in the Administration Suite
Overhead duct work and plumbing almost complete on level 2 Special Education and art classrooms
View into the cafeteria area from the study hall
Biology and physics classrooms showing typical framing progress on all 3 floors in the academics building
Athletics building lobby window frames will install in the next few weeks
Tilt panels are up on the transition area between academics and performing arts with the slab placed to allow steel erection to begin
Framing and duct progress on the general classrooms just north of the cafeteria above the administration suite

​

Filed Under: Skyline

Status of Projects May 2023 – Skyline High School

May 2023

Significant progress has been made on the structure of the project now that the weather has been improving. The majority of levels 1-4 have had the structural steel completed and they have started installing the decking throughout to prepare for several pours on May 2nd, 3rd and 4th.

The framer has almost finished the north half of the administrative suite and the in wall electrical and plumbing has started. The roof was also completed in this area.

The south half of the administration area slab was poured and the tilt panels that go along the west end of this area have been formed and prepped to be placed next week.

The kitchen area is almost completed with framing and in wall electrical and plumbing. The mechanical duct work is also near completion.

With the nicer weather, the sports fields have almost dried out and are getting close to being available for use. The north pathway on the property should also be open to the public in the next week.




View of the main academics building looking from the west side of the property
4/3/23.



Same view of the building but with significant progress to the structural framing
4/20/23.



Administration area with the framing starting. 



Administration area north half. Framing is almost complete, and the duct work is installed. In wall plumbing and electrical has started as well.



Administration offices south slab being prepared for pouring.



Administration offices slab poured. North walls being formed, and rebar installed for a pour next week. These will go along the east wall.



New cafeteria slab being prepared for pouring. This will also be used to pour tilt panels.



New cafeteria slab being poured and finished.



Level 3 looking into the new classrooms and student collaboration areas. Decking almost complete.



Level 4 of the academics building looking into the new chemistry lab and student collaboration areas. Decking almost complete.



Looking west at the new academics building. This is looking into special education (ground level), general classrooms (floor 2) and STEM labs and classrooms (floor 3).



Looking north down the main academics building hallway.

Filed Under: Skyline

Status of Projects April 2023 – Skyline High School

April 2023

Skyline High School
Building Construction

Progress is ongoing in the academics and administration buildings despite the challenges with weather.

Administration building tilt panels have been stood and steel framing and deck erected. Framing has started on the office spaces as well as some mechanical, electrical,and plumbing rough in.

The south end of the administration slab prep started this week and is looking to pour next week.

Minimal progress has been made in academics the last few weeks because of weather. Once the weather gets warmer, slab prep will begin on the cafeteria area.

Manufacturing lab framing, mechanical, electrical, and plumbing rough in have continued in the testing center. Duct work and framing has been hung in the kitchen. Concrete decking has been poured and the air handlers set in the mechanical room so that the remaining roof steel can be set. Additionally, the remaining slab has been poured in the manufacturing area to allow for the final tilts to be set.

Tilt panels for the arts classrooms have been stood and the steel framing has started erection. The north half classrooms have been stood and braced.




Slab prep ongoing for the south half of administration offices.



Tilt panels on the west side of the project academics. These encompass classrooms, visual arts, special education, and culinary arts.



Final roof joist being flown in above manufacturing lab mechanical rooms and the health science lab.



Steel being erected for culinary arts.



Steel framing being erected for classrooms, business lab, biology lab, TV production.



New duct work and framing being installed in kitchen.



Framing, duct work, backing, rough plumbing being installed in girls bathroom.



Slab prep and pour for remaining manufacturing lab.



Now that this is complete the remaining tilt panels in this area can go up and steel framing can begin in this area



Air handlers set in academics mechanical room on level 4.



New corridor steel being set outside of the new kitchen area. This will tie into sewing and graphics to the west as well.



New Framing being installed in the administration area.

Filed Under: Project Updates, Skyline

Status of Projects March 2023 – Skyline High School

March 2023

Skyline High School
Athletics Complex

Softball batting cages installed.
Concessions and press box are painted with finishes being installed now.
Manufacturing lab and kitchen steel erection continues.
Academics tilt walls continue to be stood.

Softball batting cages
Softball batting cages
Softball dugouts
Softball dugouts
Concessions interior finishes
Concessions interior finishes
Sidewalk prep around the pool connecting the softball complex to the athletics building
Sidewalk prep around the pool connecting the softball complex to the athletics building
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Steel for manufacturing lab / kitchen
Steel for manufacturing lab / kitchen
Tilt walls in academics
Tilt walls in academics
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects February 2023 – Skyline High School

February 2023

Skyline High School
Athletics Complex

Softball building is currently being painted and tile is being installed.
Kitchen and testing center walls continue to be stood.
Steel continues with roof joists and decking.
Looking into options to strengthen existing auditorium wall exposed by gymnasium demolition as this will be the exterior wall for next 3 years.

Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium
Softball exterior walls heated prepping for paint
Softball exterior walls heated prepping for paint
Softball interior walls prepping for paint
Softball interior walls prepping for paint
Bathroom tile being installed
Bathroom tile being installed
Testing center roof joists with decking installed
Testing center roof joists with decking installed
Manufacturing lab / kitchen stairs being installed
Manufacturing lab / kitchen stairs being installed
Graphics and sewing rooms
Graphics and sewing rooms
Tilt wall ready to be stood
Tilt wall ready to be stood
Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium

Filed Under: Project Updates, Skyline

Status of Projects January 2023 – Skyline High School

January 2023

Skyline High School
Athletics Complex

Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.

Classroom steel trusses
Classroom steel trusses
Demolition of gymnasium from auditorium.
Demolition of gymnasium from auditorium
Pathway emergency phones
Pathway emergency phones
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – Skyline High School

November 2022

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab

Filed Under: Project Updates, Skyline

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Interim pages omitted …
  • Page 6
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2025 Granite School District

 

Loading Comments...