GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects June 2022 – Skyline

June, 2022 by Granite Schools

Skyline High School
Athletics Complex & Academics Building

Mechanical, electrical, and plumbing continues throughout athletics building.
Pool equipment is energized and circulating water.
Flooring ongoing throughout athletics building.
Base is being placed at artificial turf field.
West concrete panel fencing is 85% complete.
Chain link fencing is ongoing at north property line.
Academics underground mechanical, electrical, and plumbing is being installed.
Salt Lake City Public Utilities water main is being sanitized for testing.
Softball backstop footings and fencing is underway.

Dance room finished floor
Dance room finished floor
Hallway south of gym
Hallway south of gym
Installation of wood floor at gym
Installation of wood floor at gym
Temporary mechanical for auditorium
Temporary mechanical for auditorium
West fence line at Laurel Crest
West fence line at Laurel Crest
West fence line/softball outfield fence
West fence line/softball outfield fence
Ramp north of main gym and south of tennis courts
Ramp north of main gym and south of tennis courts
West entrance to pool and field house
West entrance to pool and field house
Rock base being placed at turf field
Rock base being placed at turf field
Rock base being placed at turf field
Rock base being placed at turf field

Filed Under: Project Updates, Skyline

May 2022 Construction Photos

May, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Aerial photo of Skyline High School
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site

West Lake STEM Jr High

West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site

Filed Under: Cyprus, Skyline, West Lake

Status of Projects May 2022 – Skyline

May, 2022 by Granite Schools

Skyline High School Athletics Complex & Academics Building

Field Turf has commenced work on the synthetic turf field.
Forming walls at the Millcreek pedestrian staircase.
MEP finish work ongoing.
Main entrance storefront and doors installed.
Flooring has commenced in locker rooms, weight room, gymnasium, and dance room.
Site work continues at the playing fields.
Fencing continues at the west and north fence lines.
Pool has been drained, cleaned, and refilled. Pool deck is complete.
Training and commissioning of the pool scheduled for May.
Mechanical room work ongoing.

Skyline Campus

Millcreek stair
Millcreek stair
West property line retaining wall
West property line retaining wall
North property line utilities
North property line utilities
North property line looking east
North property line looking east
North property line looking west
North property line looking west
Turf field drainage
Turf field drainage
North fencing next to turf field
North fencing next to turf field
Weight room
Weight room
Dance room
Dance room
Skyline overview looking northwest
Skyline overview looking northwest
Skyline overview looking northeast
Skyline overview looking northeast
Floor being prepped in gym
Floor being prepped in gym
Team locker rooms
Team locker rooms

Filed Under: Project Updates, Skyline

April 2022 Construction Photos

April, 2022 by Granite School District Communications Office

Cyprus High School

Skyline High School

West Lake Jr High

Filed Under: Cyprus, Skyline, West Lake

Status of Projects April 2022 – Skyline

April, 2022 by Granite Schools

Skyline High School
Athletics Complex & Academics Building

New pool has been filled and is circulating water.
Existing pool was drained and is being tested for asbestos and abatement.
Boilers are operational and air handling units are providing warm air.
Gymnasium floor has been acclimating to building temperature and humidity.
Field Turf mobilized the week of 04/04/22.
Tiling at bathrooms and pool is ongoing.
Site work continues, including perimeter and athletic field fencing.

Tile work progressing in locker room
Tile work progressing in locker room
Grading for turf field
Grading for turf field
Fencing posts next to turf field
Fencing posts next to turf field
New pool circulating water
New pool circulating water
Hardwood flooring acclimatizing
Hardwood flooring acclimatizing
Sidewalk at tennis court retaining wall
Sidewalk at tennis court retaining wall
Lockers being installed in locker room
Lockers being installed in locker room

Filed Under: Project Updates, Skyline

March 2022 Construction Photos

March, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School interior construction site
Skyline High School interior construction site
Skyline High School construction site
Skyline High School interior construction site

Filed Under: Cyprus, Skyline

Status of Projects March 2022 – Skyline

March, 2022 by Granite Schools

Skyline High School Athletics Complex & Academics Building

Finishing tile work in locker rooms, lockers onsite.
Start up of air handlers has begun, boilers to be started first week of March.
Earthwork continues on athletic fields.
Retaining walls and fences on north and west property lines are under way.
Foundation poured for softball press box.
Footings have been formed for the east wall of the academics building.
Metal siding is being installed on the mechanical penthouse.
Pool lining is being installed.

Softball concessions footings
Softball concessions footings
Footing and foundation wall for academics
Footing and foundation wall for academics
Fieldhouse scoreboard
Fieldhouse scoreboard
Coach’s office millwork
Coach’s office millwork
pool
pool
Temporary fencing in place as preparation for new fence / wall occurs
Temporary fencing in place as preparation for new fence / wall occurs
Softball field dugout
Softball field dugout

Filed Under: Project Updates, Skyline

February 2022 Construction Photos

February, 2022 by Granite School District Communications Office

Cyprus High School

Skyline High School

Oakridge Elementary Security/Elevator Remodel

Filed Under: Cyprus, Skyline

Status of Projects February 2022 – Skyline

February, 2022 by Granite Schools

Skyline High School: Athletics Complex

Backfilling around pool in progress.
Mechanical, plumbing, and fire sprinkler work ongoing.
Permanent electrical and gas services have been connected to the athletics building.
Installation of gym equipment has begun.
Tile work is progressing.
Site work, including footing excavation on the west side of the existing academic building, is underway for the new academic wing.
Work continues at the north athletic fields.
Asbestos surveys for the existing pool and auditorium/gymnasium buildings are almost complete.

Painted dance studio
Painted dance studio
Softball press box tilt panels
Softball press box tilt panels
Graded earthwork for the academic wing.
Graded earthwork for the academic wing.
Construction Sites
Construction Sites
Construction
Construction
Removed Cafeteria Section
Removed Cafeteria Section
Backfilling of the pool
Backfilling of the pool

Filed Under: Project Updates, Skyline

Status of Projects January 2022 – Skyline

January, 2022 by Granite Schools

Skyline High School – Athletics Complex

Mount Olympus sewer main work at north property line complete.
MEP continues throughout building.
Tile work is ongoing in all locker rooms.
Boiler room work ongoing.
Dominion Energy installing the gas main to the building.
Rocky Mountain Power installing the main electrical service.
Swimming pool excavation complete. Installation underway.
Work in weight room and dance studio continues.

Weight Room
Weight Room
Dance Studio
Dance Studio
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus
Skyline Campus

Filed Under: Project Updates, Skyline

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • 5
  • Next Page »
 

Loading Comments...