Skyline High School
Athletics Complex
Softball batting cages installed.
Concessions and press box are painted with finishes being installed now.
Manufacturing lab and kitchen steel erection continues.
Academics tilt walls continue to be stood.
Skyline High School
Athletics Complex
Softball batting cages installed.
Concessions and press box are painted with finishes being installed now.
Manufacturing lab and kitchen steel erection continues.
Academics tilt walls continue to be stood.
Skyline High School
Athletics Complex
Softball building is currently being painted and tile is being installed.
Kitchen and testing center walls continue to be stood.
Steel continues with roof joists and decking.
Looking into options to strengthen existing auditorium wall exposed by gymnasium demolition as this will be the exterior wall for next 3 years.
Skyline High School
Athletics Complex
Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.
Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.
Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.
Skyline High School: Athletics Complex
Athletics phase is 60% complete.
Baseball diamond and football stadium are complete.
Interior painting is in progress.
Excavation for the pool is scheduled to begin in October.
Grading is underway for the athletic fields.
Cyprus High School
Skyline High School
West Lake STEM Junior High
Cottonwood High Auditorium Control Booth
Granite Technical Institute Third Floor Labs
Security Upgrades
Turf Fields
Skyline High School
Athletics Complex
Owner training is ongoing for all systems.
Turf field to be turned over on July 25, the school can start using August 1.
Grading continues at softball field, grass field, tennis courts, and west fence line.
Sod for softball field expected in September.
Bleacher installation is ongoing.
Granite security, AV, and IT installations are ongoing.
Old pool building demolition is complete.
Track installation is complete.
Cyprus High School
Skyline High School
West Lake STEM Junior High