Granite Technical Institute – Pharmacy and Animation Labs



Cyprus High School





Skyline High School





West Lake STEM Jr High





Cyprus High School
Skyline High School
West Lake STEM Junior High
Skyline High School
Athletics Complex & Academics Building
Mechanical, electrical, and plumbing continues throughout athletics building.
Pool equipment is energized and circulating water.
Flooring ongoing throughout athletics building.
Base is being placed at artificial turf field.
West concrete panel fencing is 85% complete.
Chain link fencing is ongoing at north property line.
Academics underground mechanical, electrical, and plumbing is being installed.
Salt Lake City Public Utilities water main is being sanitized for testing.
Softball backstop footings and fencing is underway.
Skyline High School Athletics Complex & Academics Building
Field Turf has commenced work on the synthetic turf field.
Forming walls at the Millcreek pedestrian staircase.
MEP finish work ongoing.
Main entrance storefront and doors installed.
Flooring has commenced in locker rooms, weight room, gymnasium, and dance room.
Site work continues at the playing fields.
Fencing continues at the west and north fence lines.
Pool has been drained, cleaned, and refilled. Pool deck is complete.
Training and commissioning of the pool scheduled for May.
Mechanical room work ongoing.
Skyline Campus
Skyline High School
Athletics Complex & Academics Building
New pool has been filled and is circulating water.
Existing pool was drained and is being tested for asbestos and abatement.
Boilers are operational and air handling units are providing warm air.
Gymnasium floor has been acclimating to building temperature and humidity.
Field Turf mobilized the week of 04/04/22.
Tiling at bathrooms and pool is ongoing.
Site work continues, including perimeter and athletic field fencing.
Skyline High School Athletics Complex & Academics Building
Finishing tile work in locker rooms, lockers onsite.
Start up of air handlers has begun, boilers to be started first week of March.
Earthwork continues on athletic fields.
Retaining walls and fences on north and west property lines are under way.
Foundation poured for softball press box.
Footings have been formed for the east wall of the academics building.
Metal siding is being installed on the mechanical penthouse.
Pool lining is being installed.