GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects January 2023 – Skyline High School

January, 2023 by Matthew Sampson

Skyline High School
Athletics Complex

Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.

Classroom steel trusses
Classroom steel trusses
Demolition of gymnasium from auditorium.
Demolition of gymnasium from auditorium
Pathway emergency phones
Pathway emergency phones
Site overview
Site overview