• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List

Skyline

Status of Projects April 2023 – Skyline High School

April 2023

Skyline High School
Building Construction

Progress is ongoing in the academics and administration buildings despite the challenges with weather.

Administration building tilt panels have been stood and steel framing and deck erected. Framing has started on the office spaces as well as some mechanical, electrical,and plumbing rough in.

The south end of the administration slab prep started this week and is looking to pour next week.

Minimal progress has been made in academics the last few weeks because of weather. Once the weather gets warmer, slab prep will begin on the cafeteria area.

Manufacturing lab framing, mechanical, electrical, and plumbing rough in have continued in the testing center. Duct work and framing has been hung in the kitchen. Concrete decking has been poured and the air handlers set in the mechanical room so that the remaining roof steel can be set. Additionally, the remaining slab has been poured in the manufacturing area to allow for the final tilts to be set.

Tilt panels for the arts classrooms have been stood and the steel framing has started erection. The north half classrooms have been stood and braced.




Slab prep ongoing for the south half of administration offices.



Tilt panels on the west side of the project academics. These encompass classrooms, visual arts, special education, and culinary arts.



Final roof joist being flown in above manufacturing lab mechanical rooms and the health science lab.



Steel being erected for culinary arts.



Steel framing being erected for classrooms, business lab, biology lab, TV production.



New duct work and framing being installed in kitchen.



Framing, duct work, backing, rough plumbing being installed in girls bathroom.



Slab prep and pour for remaining manufacturing lab.



Now that this is complete the remaining tilt panels in this area can go up and steel framing can begin in this area



Air handlers set in academics mechanical room on level 4.



New corridor steel being set outside of the new kitchen area. This will tie into sewing and graphics to the west as well.



New Framing being installed in the administration area.

Filed Under: Project Updates, Skyline

Status of Projects March 2023 – Skyline High School

March 2023

Skyline High School
Athletics Complex

Softball batting cages installed.
Concessions and press box are painted with finishes being installed now.
Manufacturing lab and kitchen steel erection continues.
Academics tilt walls continue to be stood.

Softball batting cages
Softball batting cages
Softball dugouts
Softball dugouts
Concessions interior finishes
Concessions interior finishes
Sidewalk prep around the pool connecting the softball complex to the athletics building
Sidewalk prep around the pool connecting the softball complex to the athletics building
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Steel for manufacturing lab / kitchen
Steel for manufacturing lab / kitchen
Tilt walls in academics
Tilt walls in academics
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects February 2023 – Skyline High School

February 2023

Skyline High School
Athletics Complex

Softball building is currently being painted and tile is being installed.
Kitchen and testing center walls continue to be stood.
Steel continues with roof joists and decking.
Looking into options to strengthen existing auditorium wall exposed by gymnasium demolition as this will be the exterior wall for next 3 years.

Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium
Softball exterior walls heated prepping for paint
Softball exterior walls heated prepping for paint
Softball interior walls prepping for paint
Softball interior walls prepping for paint
Bathroom tile being installed
Bathroom tile being installed
Testing center roof joists with decking installed
Testing center roof joists with decking installed
Manufacturing lab / kitchen stairs being installed
Manufacturing lab / kitchen stairs being installed
Graphics and sewing rooms
Graphics and sewing rooms
Tilt wall ready to be stood
Tilt wall ready to be stood
Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium

Filed Under: Project Updates, Skyline

Status of Projects January 2023 – Skyline High School

January 2023

Skyline High School
Athletics Complex

Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.

Classroom steel trusses
Classroom steel trusses
Demolition of gymnasium from auditorium.
Demolition of gymnasium from auditorium
Pathway emergency phones
Pathway emergency phones
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – Skyline High School

November 2022

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – Skyline

October 2022

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.

Floor boxes for testing center
Floor boxes for testing center
Underground utilities
Underground utilities
Grading at softball field
Grading at softball field
Grading at tennis courts
Grading at tennis courts
Sod on practice field
Sod on practice field
Concrete pour and tilt panels being formed
Concrete pour and tilt panels being formed
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
West pool stairs graphic
West pool stairs graphic

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – Skyline

October 2022

Skyline High School: Athletics Complex

Athletics phase is 60% complete.
Baseball diamond and football stadium are complete.
Interior painting is in progress.
Excavation for the pool is scheduled to begin in October.
Grading is underway for the athletic fields.

Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool

Filed Under: Project Updates, Skyline

August 2022 Construction Photos

August 2022

Cyprus High School

Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site

Skyline High School

Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site

West Lake STEM Junior High

West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site

Cottonwood High Auditorium Control Booth

Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction

Granite Technical Institute Third Floor Labs

GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction

Security Upgrades

Hartvigsen security upgrade construction
Hartvigsen School
Hartvigsen security upgrade construction
Hartvigsen School
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
William Penn security upgrade construction
William Penn Elementary

Turf Fields

Granger High turf field replacement
Granger High School
Granger High turf field replacement
Granger High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School

Filed Under: Cyprus, Project Updates, Skyline, West Lake

Status of Projects August 2022 – Skyline

August 2022

Skyline High School
Athletics Complex

Owner training is ongoing for all systems.
Turf field to be turned over on July 25, the school can start using August 1.
Grading continues at softball field, grass field, tennis courts, and west fence line.
Sod for softball field expected in September.
Bleacher installation is ongoing.
Granite security, AV, and IT installations are ongoing.
Old pool building demolition is complete.
Track installation is complete.

Academic footings
Academic footings
Academic footings
Academic footings
Existing pool demolition
Existing pool demolition
Grading at tennis court
Grading at tennis court
Indoor track
Indoor track
Indoor track
Indoor track
Bleachers in fieldhouse
Bleachers in fieldhouse
Playfields
Playfields
Playfields
Playfields
Locker room
Locker room
Accessible shower
Accessible shower
Coach offices
Coach offices

Filed Under: Project Updates, Skyline

July 2022 Construction Photos

July 2022

Granite Technical Institute – Pharmacy and Animation Labs

Granite Technical Institute construction area
Granite Technical Institute construction area
Granite Technical Institute construction area

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site

West Lake STEM Jr High

West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site

Filed Under: Cyprus, Skyline, West Lake

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Page 5
  • Interim pages omitted …
  • Page 7
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

Loading Comments...