• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Status of Projects January 2023 – Cyprus High School

January 2023

Cyprus High School
Building Construction

Auditorium steel trusses, cross bracing and the catwalk are all being installed.
More auditorium tilt panels being prepped to be placed.
Gymnasium steel decking is done around the running track and ½ the concrete has been placed for the track.
Gymnasium floor is being prepped for concrete.
The cardio & wrestling room is being framed, along with HVAC and rough electrical being installed.

Auditorium roof decking and catwalk
Auditorium roof decking and catwalk
Cardio room rough in
Cardio room rough in
Gymnasium stairs
Gymnasium stairs
Gym floor being prepped for concrete
Gym floor being prepped for concrete
Windows have been sealed waiting for frames
Windows have been sealed waiting for frames

Filed Under: Cyprus, Project Updates

Status of Projects January 2023 – Skyline High School

January 2023

Skyline High School
Athletics Complex

Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.

Classroom steel trusses
Classroom steel trusses
Demolition of gymnasium from auditorium.
Demolition of gymnasium from auditorium
Pathway emergency phones
Pathway emergency phones
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – West Lake

November 2022

West Lake STEM Junior High School
Building Construction

Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.

Gymnasium
Gymnasium
Academic wing
Academic wing
Interior framing in academic wing
Interior framing in academic wing
Exterior sheathing
Exterior sheathing
Stairs at south commons
Stairs at south commons
Stairs at south commons
Stairs at south commons
Preparation for paving of north parking lot –October 27
Preparation for paving of north parking lot –October 27
Library and teacher collaboration steel structure
Library and teacher collaboration steel structure
Roof decking and structural steel for sheer wall –southwest wing
Roof decking and structural steel for sheer wall –southwest wing
West elevation -gymnasium
West elevation -gymnasium
East elevation –gymnasium reaching top out height
East elevation –gymnasium reaching top out height

Filed Under: Project Updates, West Lake

Status of Projects November 2022 – Skyline High School

November 2022

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – Cyprus

November 2022

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls

Filed Under: Cyprus, Project Updates

Status of Projects October 2022 – West Lake

October 2022

West Lake STEM Junior High School
Building Construction

Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.

Site overview
Site overview
Site overview
Site overview
Gymnasium masonry walls
Gymnasium masonry walls
Gymnasium and locker room masonry walls
Gymnasium and locker room masonry walls
Classroom floor decking
Classroom floor decking
Classroom floor decking
Classroom floor decking
FACS concrete slab
FACS concrete slab
Mechanical equipment
Mechanical equipment

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October 2022

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.

Floor boxes for testing center
Floor boxes for testing center
Underground utilities
Underground utilities
Grading at softball field
Grading at softball field
Grading at tennis courts
Grading at tennis courts
Sod on practice field
Sod on practice field
Concrete pour and tilt panels being formed
Concrete pour and tilt panels being formed
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
West pool stairs graphic
West pool stairs graphic

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – West Lake

October 2022

West Lake Junior High School STEM (Westbrook Campus): FACS Modular Building

Building is 100% complete.

Backordered furniture is shipping as available.

West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building

West Lake STEM Junior High School: Abatement / Demolition

Building abatement is 100% complete.
Demolition is at 40%, with completion scheduled for mid November.
Classroom wings have been demolished and debris hauled away.
Demolition of the auditorium and gymnasium is on going.

West Lake Demolition
West Lake Demolition
West Lake Demolition
West Lake Demolition

West Lake STEM Junior High School: Replacement

Estimated project completion is 2024.
Design is in process with bidding in December 2021.
New West Lake is based on existing Utah middle school buildings using 21 st century design with flexibility to support current and future learning activities.

Preliminary West Lake Floor Plan

Sample Floor Plan (First Floor)
Sample Floor Plan (First Floor)
Sample Floor Plan (Second Floor)
Sample Floor Plan (Second Floor)

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October 2022

Skyline High School: Athletics Complex

Athletics phase is 60% complete.
Baseball diamond and football stadium are complete.
Interior painting is in progress.
Excavation for the pool is scheduled to begin in October.
Grading is underway for the athletic fields.

Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – Cyprus

October 2022

Cyprus High School: Site Preparation

Site preparation is 100% complete.
Mass grading has been completed.
Kennecott site storm water drainage redirection project is completed.

Cyprus Site Work
Cyprus Site Work
Cyprus Site Work
Cyprus Site Work

Cyprus High School: Building Construction

Purchase order was issued to Westland Construction for construction of the new Cyprus High School.
Notice to proceed issued 09/13/2021.
Excavation of footings has begun.

Cyprus Footings
Cyprus Footings
Cyprus Footings
Cyprus Footings

Filed Under: Cyprus, Project Updates

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 6
  • Page 7
  • Page 8
  • Page 9
  • Page 10
  • Interim pages omitted …
  • Page 18
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

 

Loading Comments...