• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Status of Projects April 2023 – Cyprus High School

April 2023

Cyprus High School
Building Construction

Kitchen panels have been erected creating a corridor between athletics and academics. A lecture hall and mechanical room will come off either side of the corridor and the lecture hall will be the next panel erected.

Auditorium – three of the walls have been raised and braced so that heavy equipment can come and go from the area. Steel decking has been installed on the upper levels creating walkable areas.Concrete has been placed on the stage and the landing leading up to the stage. Concrete is currently curing and is covered by tarps.Dressing area/storage has been raised and braced. This area will serve as storage of the performing arts.

Academics structure has been installed and two tilt panels have been raised around the structure. A double decker air handler system will be installed to service the area. Remaining tilt panels are curing, these will be installed on the north side of the structure. Elevator shaft has been erected and braced. This is the only elevator shaft that is tilt up on three sides in the building. This will service all three floors for academics.

Drywall in the basement of gymnasium has progressed to 90%. Masonry work has been completed in the basement of athletics. Copper and steel weld piping have been placed and have passed inspections. Window frames have been installed in athletics. Glass has been ordered and will be installed in the next couple of weeks.




Panels in academics and the elevator shaft.



Auditorium walls and concrete placed on the stage.



Auditorium walls and concrete placed on the stage.



Steel decking and raised walls for dressing area.



Steel decking and raised walls for dressing area.



Structure for academics and remaining tilt panels.



Structure for academics and remaining tilt panels.



Drywall in the team rooms and window frames in athletics.



Drywall in the team rooms and window frames in athletics.



Masonry walls and the copper piping.



Masonry walls and the copper piping.



Panels in academics and the elevator shaft.

Filed Under: Cyprus, Project Updates

Status of Projects April 2023 – Skyline High School

April 2023

Skyline High School
Building Construction

Progress is ongoing in the academics and administration buildings despite the challenges with weather.

Administration building tilt panels have been stood and steel framing and deck erected. Framing has started on the office spaces as well as some mechanical, electrical,and plumbing rough in.

The south end of the administration slab prep started this week and is looking to pour next week.

Minimal progress has been made in academics the last few weeks because of weather. Once the weather gets warmer, slab prep will begin on the cafeteria area.

Manufacturing lab framing, mechanical, electrical, and plumbing rough in have continued in the testing center. Duct work and framing has been hung in the kitchen. Concrete decking has been poured and the air handlers set in the mechanical room so that the remaining roof steel can be set. Additionally, the remaining slab has been poured in the manufacturing area to allow for the final tilts to be set.

Tilt panels for the arts classrooms have been stood and the steel framing has started erection. The north half classrooms have been stood and braced.




Slab prep ongoing for the south half of administration offices.



Tilt panels on the west side of the project academics. These encompass classrooms, visual arts, special education, and culinary arts.



Final roof joist being flown in above manufacturing lab mechanical rooms and the health science lab.



Steel being erected for culinary arts.



Steel framing being erected for classrooms, business lab, biology lab, TV production.



New duct work and framing being installed in kitchen.



Framing, duct work, backing, rough plumbing being installed in girls bathroom.



Slab prep and pour for remaining manufacturing lab.



Now that this is complete the remaining tilt panels in this area can go up and steel framing can begin in this area



Air handlers set in academics mechanical room on level 4.



New corridor steel being set outside of the new kitchen area. This will tie into sewing and graphics to the west as well.



New Framing being installed in the administration area.

Filed Under: Project Updates, Skyline

Status of Projects April 2023 – West Lake STEM

April 2023

West Lake STEM Junior High School
Building Construction

Masonry walls for band, choral, and the auditorium are 95% complete.

Masons are placing veneer brick at exterior walls in the mechanical/cafeteria wing.

Structural steel placement in the administrative area is nearly complete.Roof decking is 65% in place. Once the roof is in place, drywall installation will begin in the two south wings.

Metal stud framing, plumbing, electrical, and mechanical systems are nearly complete on the first floor in the south wings of the academic building.




South academics wing.



Brick veneer facing.



HVAC systems.



Main office structural steel.

Filed Under: Project Updates, West Lake

Status of Projects March 2023 – West Lake STEM

March 2023

West Lake STEM Junior High School
Building Construction

Steel beams being installed over kitchen and mechanical area.
Interior framing, plumbing, electrical, and mechanical system installation continues in academic classrooms.
Roof decking and steel erecting in progress in entry and commons area.
Boilers and chiller are set in place.
Auditorium and athletics walls are 90% complete.

Boilers and chiller are set in place
Boilers and chiller are set in place
Boilers and chiller are set in place
Boilers and chiller are set in place
Auditorium walls in progress
Auditorium walls in progress
Site overview
Site overview
Mechanical, plumbing, electrical, and framing in classroom wing
Mechanical, plumbing, electrical, and framing in classroom wing
Steel beams being installed
Steel beams being installed
Mechanical, plumbing, electrical, and framing in classroom wing
Mechanical, plumbing, electrical, and framing in classroom wing

Filed Under: Project Updates, West Lake

Status of Projects March 2023 – Cyprus High School

March 2023

Cyprus High School
Building Construction

Auditorium roofing, steel in ceilings and back of house 2nd and 3rd floor continues.
Gymnasium and locker rooms have drywall being installed on one side of metal studs.
Electrical, fire sprinkler/alarm and plumbing continues in the locker rooms and gymnasium.
Gymnasium masonry on stairway walls and under the dance room as well as moving up to pool loft and locker rooms.
Pool roof decking installed, and roofing started. Observation upper deck installed.
Tilt walls for choral and band area have been stood. Steel moving to choral area soon.

Band and choral walls in place
Band and choral walls in place
Auditorium steel
Auditorium steel
HVAC ducting over gymnasium
HVAC ducting over gymnasium
Framing and spray foam insulation
Framing and spray foam insulation
Last section of track being placed
Last section of track being placed
Drywall on one side of metal studs in locker room/changing rooms
Drywall on one side of metal studs in locker room/changing rooms
Masonry below dance room
Masonry below dance room
Ducting to air handlers
Ducting to air handlers
Pool upper observation area decking installed
Pool upper observation area decking installed
Pool trusses installed
Pool trusses installed
Site overview
Site overview

Filed Under: Cyprus, Project Updates

Status of Projects March 2023 – Skyline High School

March 2023

Skyline High School
Athletics Complex

Softball batting cages installed.
Concessions and press box are painted with finishes being installed now.
Manufacturing lab and kitchen steel erection continues.
Academics tilt walls continue to be stood.

Softball batting cages
Softball batting cages
Softball dugouts
Softball dugouts
Concessions interior finishes
Concessions interior finishes
Sidewalk prep around the pool connecting the softball complex to the athletics building
Sidewalk prep around the pool connecting the softball complex to the athletics building
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Shotcrete on existing exterior auditorium wall installed to provide structural resiliency and weather barrier
Steel for manufacturing lab / kitchen
Steel for manufacturing lab / kitchen
Tilt walls in academics
Tilt walls in academics
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects February 2023 – West Lake STEM

February 2023

West Lake STEM Junior High School
Building Construction

Band and choral room masonry walls are 90% complete and were scheduled to top out the week of January 30th upon which masons will move to auditorium area.
Contractor is placing decking for second floor in northwest academic wing and preparing to place roof decking on southeast academic wing.
Metal stud, framing, interior, plumbing, electrical, lighting, power, and mechanical system installation continues in south wings.

Southwest academic wing exterior sheathing
Southwest academic wing exterior sheathing
Gymnasium roof decking
Gymnasium roof decking
Southeast academic steel trusses
Southeast academic steel trusses
Southeast academic framing 1st floor
Southeast academic framing 1st floor
Site overview auditorium and administration walls started
Site overview auditorium and administration walls started

Filed Under: Project Updates, West Lake

Status of Projects February 2023 – Cyprus High School

February 2023

Cyprus High School
Building Construction

Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.

Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Framing mechanical room
Framing mechanical room
Framing bathrooms
Framing bathrooms
Roof steel decking
Roof steel decking
Auditorium cloud steel
Auditorium cloud steel
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Site Overview
Site Overview

Filed Under: Cyprus, Project Updates

Status of Projects February 2023 – Skyline High School

February 2023

Skyline High School
Athletics Complex

Softball building is currently being painted and tile is being installed.
Kitchen and testing center walls continue to be stood.
Steel continues with roof joists and decking.
Looking into options to strengthen existing auditorium wall exposed by gymnasium demolition as this will be the exterior wall for next 3 years.

Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium
Softball exterior walls heated prepping for paint
Softball exterior walls heated prepping for paint
Softball interior walls prepping for paint
Softball interior walls prepping for paint
Bathroom tile being installed
Bathroom tile being installed
Testing center roof joists with decking installed
Testing center roof joists with decking installed
Manufacturing lab / kitchen stairs being installed
Manufacturing lab / kitchen stairs being installed
Graphics and sewing rooms
Graphics and sewing rooms
Tilt wall ready to be stood
Tilt wall ready to be stood
Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium

Filed Under: Project Updates, Skyline

Status of Projects January 2023 – West Lake STEM

January 2023

West Lake STEM Junior High School
Building Construction

Gymnasium roof trusses and 90% of roof decking is in place.
Locker room masonry walls 90% complete.
Kitchen and mechanical rooms masonry walls 50% complete.
Southwest academic wing framing is complete, exterior sheathing is 75% first floor utilities are 50% complete.
Southeast academic wing second floor decking and teacher hub/commons area concrete slab ready to be placed.

Masonry for kitchen and mechanical rooms
Masonry for kitchen and mechanical rooms
Gymnasium steel roofing
Gymnasium steel roofing
Commons area near teacher’s hub
Commons area near teacher’s hub
Academic building and gymnasium
Academic building and gymnasium
Southwest academic wing utilities and framing
Southwest academic wing utilities and framing

Filed Under: Project Updates, West Lake

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 5
  • Page 6
  • Page 7
  • Page 8
  • Page 9
  • Interim pages omitted …
  • Page 18
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.