• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List

Project Updates

Status of Projects February 2022 – West Lake

February 2022

West Lake STEM Junior High School: School Design

Contract awarded to Hogan.
Pre-construction meeting with Hogan was01/24/22.
Perimeter security fencing installed and job trailer delivered to site on 1/28/22.
Groundbreaking – Concept to hold on March 18 – anniversary of earthquake.

Filed Under: Project Updates, West Lake

Status of Projects February 2022 – Skyline

February 2022

Skyline High School: Athletics Complex

Backfilling around pool in progress.
Mechanical, plumbing, and fire sprinkler work ongoing.
Permanent electrical and gas services have been connected to the athletics building.
Installation of gym equipment has begun.
Tile work is progressing.
Site work, including footing excavation on the west side of the existing academic building, is underway for the new academic wing.
Work continues at the north athletic fields.
Asbestos surveys for the existing pool and auditorium/gymnasium buildings are almost complete.

Painted dance studio
Painted dance studio
Softball press box tilt panels
Softball press box tilt panels
Graded earthwork for the academic wing.
Graded earthwork for the academic wing.
Construction Sites
Construction Sites
Construction
Construction
Removed Cafeteria Section
Removed Cafeteria Section
Backfilling of the pool
Backfilling of the pool

Filed Under: Project Updates, Skyline

Status of Projects February 2022 – Cyprus

February 2022

Cyprus High School: Building Construction

Continuing underground plumbing and underground electrical.
Concrete footings continue to be poured.
Casting slabs have been placed so precast walls can be formed and poured.
Drilling of heat source wells has begun.

Cyprus footing / foundation & underground utility construction

Casting slab where walls will
be formed and poured
Casting slab where walls will
be formed and poured
Construction site
Construction site
Mockup panels for review and approval
Mockup panels for review and approval
Mockup panels for review and approval
Mockup panels for review and approval
Plumbing wall of cafeteria kitchen
Plumbing wall of cafeteria kitchen
Plumbing wall of cafeteria kitchen
Plumbing wall of cafeteria kitchen

Filed Under: Cyprus, Project Updates

Status of Projects January 2022 – West Lake

January 2022

West Lake STEM Junior High School
School Design

Documents have gone out for bid.
Contractor bids due Thursday, January 6, 2022.

Filed Under: Project Updates, West Lake

Status of Projects January 2022 – Skyline

January 2022

Skyline High School – Athletics Complex

Mount Olympus sewer main work at north property line complete.
MEP continues throughout building.
Tile work is ongoing in all locker rooms.
Boiler room work ongoing.
Dominion Energy installing the gas main to the building.
Rocky Mountain Power installing the main electrical service.
Swimming pool excavation complete. Installation underway.
Work in weight room and dance studio continues.

Weight Room
Weight Room
Dance Studio
Dance Studio
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus
Skyline Campus

Filed Under: Project Updates, Skyline

Status of Projects January 2022 – Cyprus

January 2022

Cyprus High School Building Construction

Continuing underground plumbing for locker rooms and gymnasium.
Locker rooms and gymnasium rebar being installed and concrete footings being poured.

Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction

Filed Under: Cyprus, Project Updates

Status of Projects December 2021 – West Lake

December 2021

West Lake STEM Junior High School: School Design

West Lake Junior Community Council reviewed the new school floor plan, elevations and color schemes. The exterior colors were sent out to the community at large for feedback.

Pre-bid meeting was 12/01/21.

Mountain Red / Pearl Taupe was the
top choice with 51% of the votes.
Mountain Red / Pearl Taupe was the top choice with 51% of the votes.
Platinum / Cimarron was the second
choice with 31% of the votes.
Platinum / Cimarron was the second choice with 31% of the votes.
Ochre Buff / Colonial Tan was the
third
choice with 17% of the votes.
Ochre Buff / Colonial Tan was the third choice with 17% of the votes.

Filed Under: Project Updates, West Lake

Status of Projects December 2021 – Skyline

December 2021

Skyline High School: Athletics Complex

  • Pool excavation complete.
  • Kitchen and cafeteria demolished.
  • Mount Olympus sewer main work at north property line has started.
  • Electrical work at north pedestrian walkway is progressing.
  • The tilt panel casting slab at the softball complex has been placed.
  • Earth work at demolished art building in progress.
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Shared north drive verti-block retaining wall  Hughes General Contractors
Demolition of arts building
Pool lobby storefront
Locker room tiling

Filed Under: Project Updates, Skyline

Status of Projects December 2021 – Cyprus

December 2021

Cyprus High School: Builing Construction

Continuing underground plumbing for gymnasium and locker rooms.

Gymnasium and locker rooms rebar is being installed and concrete footings are being poured.

The New Cyprus High School

  • Project Timeline
    • 11/04 – Submittal List Returned to Architect with Requested Revisions Incorporated
    • 11/19 – First Pour of Concrete Footings
    • 11/22 – U/G Sewer Utility Work Started
    • 11/29 – Building Site Preparation Continues
    • 11/29 – U/G MEP Installation Continues
    • 11/29 – Geothermal Drilling Work Planned to Begin, pending materials procurement
  • Manpower Onsite
    • Snapshot from Total = Westland (4), Suntec (5), KSC (6), US Mech (8), CR Lighting (4)
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Constructionf
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction

Filed Under: Cyprus, Project Updates

Ground Breaks on New Cyprus High School

November 2021

Construction has commenced on the new Cyprus High School, and the Magna community and Granite School District are celebrating this momentous step in the school’s 100+ year history.

Cyprus students joined Granite board members, local elected officials, alumni, and community members at the school’s new site (8400 W. 4000 South) to ceremonially turn the dirt that will eventually serve as a foundation for the Home of Pirates.

Filed Under: Cyprus

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 10
  • Page 11
  • Page 12
  • Page 13
  • Page 14
  • Interim pages omitted …
  • Page 18
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

 

Loading Comments...