• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List

Project Updates

Status of Projects May 2022 – Cyprus

May 2022

Cyprus High School Building Construction

Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.

Auto shop footings, hillside drainage finished
Auto shop footings, hillside drainage finished
Orchestra pit underground electrical
Orchestra pit underground electrical
Foundation walls and columns being formed up in pool area
Foundation walls and columns being formed up in pool area
View of site crane paths
View of site crane paths
Crane onsite being built
Crane onsite being built
Casting slabs, framing tilt walls, and crane paths
Casting slabs, framing tilt walls, and crane paths

Filed Under: Cyprus, Project Updates

April 2022 Construction Photos

April 2022

Cyprus High School

Skyline High School

West Lake Jr High

Filed Under: Cyprus, Skyline, West Lake

Status of Projects April 2022 – West Lake

April 2022

West Lake STEM Junior High School
Building Construction

Soil pad compaction under the building footprint is complete.
Excavation for underground utilities and footings has begun.
Reinforcing and forms placement for footings is in progress.
First footing concrete placement occurred 04/01/22.

Forms and reinforcing for footings
Forms and reinforcing for footings
Pouring footing for southwest corner area
Pouring footing for southwest corner area
Forms and reinforcement in progress
Forms and reinforcement in progress
Compacting soil for footings
Compacting soil for footings

Filed Under: Project Updates, West Lake

Status of Projects April 2022 – Skyline

April 2022

Skyline High School
Athletics Complex & Academics Building

New pool has been filled and is circulating water.
Existing pool was drained and is being tested for asbestos and abatement.
Boilers are operational and air handling units are providing warm air.
Gymnasium floor has been acclimating to building temperature and humidity.
Field Turf mobilized the week of 04/04/22.
Tiling at bathrooms and pool is ongoing.
Site work continues, including perimeter and athletic field fencing.

Tile work progressing in locker room
Tile work progressing in locker room
Grading for turf field
Grading for turf field
Fencing posts next to turf field
Fencing posts next to turf field
New pool circulating water
New pool circulating water
Hardwood flooring acclimatizing
Hardwood flooring acclimatizing
Sidewalk at tennis court retaining wall
Sidewalk at tennis court retaining wall
Lockers being installed in locker room
Lockers being installed in locker room

Filed Under: Project Updates, Skyline

Status of Projects April 2022 – Cyprus

April 2022

Cyprus High School
Building Construction

Gymnasium slab on grade is being poured for locker rooms, wrestling room, coaches’ offices, along with PE locker rooms.
Framing up tilt walls, prepping for rebar and electrical construction. Tilt walls concrete pouring to begin 04/11/22.
Pool footing has been installed, excavated and filled in with structural fill dirt and made into a crane path for tilt panels.
Geo Energy drilling will be ongoing for the next year.
Building footings have been installed, underground plumbing and electrical installation areongoing.
Retaining walls are currently being installed along Cordero Drive.

Casting slabs, framing tilt walls and crane paths
Casting slabs, framing tilt walls and crane paths
Site overview
Site overview
Site overview
Site overview
Orchestra pit footings
Orchestra pit footings
Retaining wall
Retaining wall
Retaining wall
Retaining wall
Casting slabs, framing tilt walls and crane paths
Casting slabs, framing tilt walls and crane paths

Filed Under: Cyprus, Project Updates

March 2022 Construction Photos

March 2022

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School interior construction site
Skyline High School interior construction site
Skyline High School construction site
Skyline High School interior construction site

Filed Under: Cyprus, Skyline

Status of Projects March 2022 – West Lake

March 2022

West Lake STEM Junior High School Building Construction

Removing remaining grass and parking lot asphalt in building footprint.

construction site
construction site
construction site
construction site
Hogan trailer onsite
Hogan trailer onsite

Filed Under: Project Updates

Status of Projects March 2022 – Skyline

March 2022

Skyline High School Athletics Complex & Academics Building

Finishing tile work in locker rooms, lockers onsite.
Start up of air handlers has begun, boilers to be started first week of March.
Earthwork continues on athletic fields.
Retaining walls and fences on north and west property lines are under way.
Foundation poured for softball press box.
Footings have been formed for the east wall of the academics building.
Metal siding is being installed on the mechanical penthouse.
Pool lining is being installed.

Softball concessions footings
Softball concessions footings
Footing and foundation wall for academics
Footing and foundation wall for academics
Fieldhouse scoreboard
Fieldhouse scoreboard
Coach’s office millwork
Coach’s office millwork
pool
pool
Temporary fencing in place as preparation for new fence / wall occurs
Temporary fencing in place as preparation for new fence / wall occurs
Softball field dugout
Softball field dugout

Filed Under: Project Updates, Skyline

Status of Projects March 2022 – Cyprus

March 2022

Cyprus High School Building Construction

Excavating orchestra pit.
Placing footings for automotive shops and kitchen areas.
Installing retaining wall along Cordero Drive.
Several casting slabs placed.
Framing tilt walls for athletics.
Installing drainage for southeast portion of lot.
Continuing with underground plumbing and electrical.

Casting slabs for tilt up wall construction
Casting slabs for tilt up wall construction
Material storage
Material storage
Material storage
Material storage
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Retaining wall
Retaining wall
Retaining wall
Retaining wall
Mockup panels for approval
Mockup panels for approval
Tilt walls framed, prepped for rebar and electrical
Tilt walls framed, prepped for rebar and electrical
Casting slabs for tilt up wall construction
Casting slabs for tilt up wall construction

Filed Under: Cyprus, Project Updates

February 2022 Construction Photos

February 2022

Cyprus High School

Skyline High School

Oakridge Elementary Security/Elevator Remodel

Filed Under: Cyprus, Skyline

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 9
  • Page 10
  • Page 11
  • Page 12
  • Page 13
  • Interim pages omitted …
  • Page 18
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

 

Loading Comments...