Updates:
Site Work:
- Underground utility work nearing completion in the central courtyard
Academics:
- Cafeteria steel complete minus the activity stairs
- Glass on main Academics Building 90 percent complete
- Roof completed on the entire building
- Final paint started in the Administration Suite
- Athletics Vestibule life safety is complete, finishes (tile, paint, flooring) starting soon
- Drywall ongoing on all floors, 90 percent complete on the second floor
- In wall electrical, plumbing nearing completion on all floors
- Steel at the south stair tower nearing completion