GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects May 2022 – Skyline

May, 2022 by Granite Schools

Skyline High School Athletics Complex & Academics Building

Field Turf has commenced work on the synthetic turf field.
Forming walls at the Millcreek pedestrian staircase.
MEP finish work ongoing.
Main entrance storefront and doors installed.
Flooring has commenced in locker rooms, weight room, gymnasium, and dance room.
Site work continues at the playing fields.
Fencing continues at the west and north fence lines.
Pool has been drained, cleaned, and refilled. Pool deck is complete.
Training and commissioning of the pool scheduled for May.
Mechanical room work ongoing.

Skyline Campus

Millcreek stair
Millcreek stair
West property line retaining wall
West property line retaining wall
North property line utilities
North property line utilities
North property line looking east
North property line looking east
North property line looking west
North property line looking west
Turf field drainage
Turf field drainage
North fencing next to turf field
North fencing next to turf field
Weight room
Weight room
Dance room
Dance room
Skyline overview looking northwest
Skyline overview looking northwest
Skyline overview looking northeast
Skyline overview looking northeast
Floor being prepped in gym
Floor being prepped in gym
Team locker rooms
Team locker rooms

Filed Under: Project Updates, Skyline

Status of Projects May 2022 – Cyprus

May, 2022 by Granite Schools

Cyprus High School Building Construction

Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.

Auto shop footings, hillside drainage finished
Auto shop footings, hillside drainage finished
Orchestra pit underground electrical
Orchestra pit underground electrical
Foundation walls and columns being formed up in pool area
Foundation walls and columns being formed up in pool area
View of site crane paths
View of site crane paths
Crane onsite being built
Crane onsite being built
Casting slabs, framing tilt walls, and crane paths
Casting slabs, framing tilt walls, and crane paths

Filed Under: Cyprus, Project Updates

Historic Cost Escalations Delay Start of Projects

April, 2022 by Granite School District Communications Office

Historic increases in construction costs have impacted the original timeline for school rebuilds and remodels. As such, many Phase 1 projects have been delayed by 7-9 years.

  • Annual cost increases since 2016 have been higher than previous trends.
  • Increases are related to labor shortages, material costs, tariffs, and supply chain issues.
  • Local market conditions have out-paced national trends due to growth.
  • Cost increases are anticipated to be near 10% for the next few years.

The Phase 1 timeline is still based on a ‘worst first’ schedule. In addition to these major projects, security upgrades and small scale remodels will continue. Read more about the impacts of cost escalations on school projects.

The anticipated start dates for Phase 1 projects are listed below.

SCHOOLPROJECTORIGINAL PROJECTED START DATEUPDATED PROJECTED START DATE
Roosevelt (Olene Walker Elementary)Rebuild20182019
South KearnsRebuild20182019
Hunter High School Addition20182019
Evergreen Jr. HighRemodel20182018
Valley Jr. HighRemodel20182018
Howard Driggs ElementaryRemodel20192019
Rosecrest ElementaryRemodel20192019
West Kearns ElementaryRebuild20192027
Cyprus High SchoolRebuild20202020
Skyline High SchoolRebuild20202020
Calvin Smith ElementaryRemodel20212028
Moss ElementaryRemodel20212028
Plymouth ElementaryRemodel20212028
Arcadia Rebuild20222029
Taylorsville High SchoolAddition20222028
Orchard ElementaryRebuild20232031
Hillsdale ElementaryRemodel20232029
Kennedy Jr. HighRemodel20232029
Academy Park ElementaryRebuild20242034
Kearns Jr. HighRebuild20242033
Magna ElementaryRemodel20242032
Valley Crest ElementaryRemodel20242032
Sandburg ElementaryRebuild20252034
Lincoln ElementaryRemodel20252033
Pioneer ElementaryRemodel20252033
Eastwood ElementaryRebuild20262035
Crestview ElementaryRemodel20262034
Spring Lane ElementaryRebuild20272036
Cottonwood ElementaryRemodel20272035
Evergreen Jr. HighRebuild20282037
Valley Jr. HighRebuild20282036
Oakridge ElementaryRebuild20282037

Filed Under: Feature

April 2022 Construction Photos

April, 2022 by Granite School District Communications Office

Cyprus High School

Skyline High School

West Lake Jr High

Filed Under: Cyprus, Skyline, West Lake

Status of Projects April 2022 – West Lake

April, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Soil pad compaction under the building footprint is complete.
Excavation for underground utilities and footings has begun.
Reinforcing and forms placement for footings is in progress.
First footing concrete placement occurred 04/01/22.

Forms and reinforcing for footings
Forms and reinforcing for footings
Pouring footing for southwest corner area
Pouring footing for southwest corner area
Forms and reinforcement in progress
Forms and reinforcement in progress
Compacting soil for footings
Compacting soil for footings

Filed Under: Project Updates, West Lake

Status of Projects April 2022 – Skyline

April, 2022 by Granite Schools

Skyline High School
Athletics Complex & Academics Building

New pool has been filled and is circulating water.
Existing pool was drained and is being tested for asbestos and abatement.
Boilers are operational and air handling units are providing warm air.
Gymnasium floor has been acclimating to building temperature and humidity.
Field Turf mobilized the week of 04/04/22.
Tiling at bathrooms and pool is ongoing.
Site work continues, including perimeter and athletic field fencing.

Tile work progressing in locker room
Tile work progressing in locker room
Grading for turf field
Grading for turf field
Fencing posts next to turf field
Fencing posts next to turf field
New pool circulating water
New pool circulating water
Hardwood flooring acclimatizing
Hardwood flooring acclimatizing
Sidewalk at tennis court retaining wall
Sidewalk at tennis court retaining wall
Lockers being installed in locker room
Lockers being installed in locker room

Filed Under: Project Updates, Skyline

Status of Projects April 2022 – Cyprus

April, 2022 by Granite Schools

Cyprus High School
Building Construction

Gymnasium slab on grade is being poured for locker rooms, wrestling room, coaches’ offices, along with PE locker rooms.
Framing up tilt walls, prepping for rebar and electrical construction. Tilt walls concrete pouring to begin 04/11/22.
Pool footing has been installed, excavated and filled in with structural fill dirt and made into a crane path for tilt panels.
Geo Energy drilling will be ongoing for the next year.
Building footings have been installed, underground plumbing and electrical installation areongoing.
Retaining walls are currently being installed along Cordero Drive.

Casting slabs, framing tilt walls and crane paths
Casting slabs, framing tilt walls and crane paths
Site overview
Site overview
Site overview
Site overview
Orchestra pit footings
Orchestra pit footings
Retaining wall
Retaining wall
Retaining wall
Retaining wall
Casting slabs, framing tilt walls and crane paths
Casting slabs, framing tilt walls and crane paths

Filed Under: Cyprus, Project Updates

March 2022 Construction Photos

March, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School interior construction site
Skyline High School interior construction site
Skyline High School construction site
Skyline High School interior construction site

Filed Under: Cyprus, Skyline

Status of Projects March 2022 – West Lake

March, 2022 by Granite Schools

West Lake STEM Junior High School Building Construction

Removing remaining grass and parking lot asphalt in building footprint.

construction site
construction site
construction site
construction site
Hogan trailer onsite
Hogan trailer onsite

Filed Under: Project Updates

Status of Projects March 2022 – Skyline

March, 2022 by Granite Schools

Skyline High School Athletics Complex & Academics Building

Finishing tile work in locker rooms, lockers onsite.
Start up of air handlers has begun, boilers to be started first week of March.
Earthwork continues on athletic fields.
Retaining walls and fences on north and west property lines are under way.
Foundation poured for softball press box.
Footings have been formed for the east wall of the academics building.
Metal siding is being installed on the mechanical penthouse.
Pool lining is being installed.

Softball concessions footings
Softball concessions footings
Footing and foundation wall for academics
Footing and foundation wall for academics
Fieldhouse scoreboard
Fieldhouse scoreboard
Coach’s office millwork
Coach’s office millwork
pool
pool
Temporary fencing in place as preparation for new fence / wall occurs
Temporary fencing in place as preparation for new fence / wall occurs
Softball field dugout
Softball field dugout

Filed Under: Project Updates, Skyline