West Lake STEM Junior High School Building Construction
Removing remaining grass and parking lot asphalt in building footprint.
West Lake STEM Junior High School Building Construction
Removing remaining grass and parking lot asphalt in building footprint.
Skyline High School Athletics Complex & Academics Building
Finishing tile work in locker rooms, lockers onsite.
Start up of air handlers has begun, boilers to be started first week of March.
Earthwork continues on athletic fields.
Retaining walls and fences on north and west property lines are under way.
Foundation poured for softball press box.
Footings have been formed for the east wall of the academics building.
Metal siding is being installed on the mechanical penthouse.
Pool lining is being installed.
Cyprus High School Building Construction
Excavating orchestra pit.
Placing footings for automotive shops and kitchen areas.
Installing retaining wall along Cordero Drive.
Several casting slabs placed.
Framing tilt walls for athletics.
Installing drainage for southeast portion of lot.
Continuing with underground plumbing and electrical.
West Lake STEM Junior High School: School Design
Contract awarded to Hogan.
Pre-construction meeting with Hogan was01/24/22.
Perimeter security fencing installed and job trailer delivered to site on 1/28/22.
Groundbreaking – Concept to hold on March 18 – anniversary of earthquake.
Skyline High School: Athletics Complex
Backfilling around pool in progress.
Mechanical, plumbing, and fire sprinkler work ongoing.
Permanent electrical and gas services have been connected to the athletics building.
Installation of gym equipment has begun.
Tile work is progressing.
Site work, including footing excavation on the west side of the existing academic building, is underway for the new academic wing.
Work continues at the north athletic fields.
Asbestos surveys for the existing pool and auditorium/gymnasium buildings are almost complete.
Cyprus High School: Building Construction
Continuing underground plumbing and underground electrical.
Concrete footings continue to be poured.
Casting slabs have been placed so precast walls can be formed and poured.
Drilling of heat source wells has begun.
Cyprus footing / foundation & underground utility construction
West Lake STEM Junior High School
School Design
Documents have gone out for bid.
Contractor bids due Thursday, January 6, 2022.
Skyline High School – Athletics Complex
Mount Olympus sewer main work at north property line complete.
MEP continues throughout building.
Tile work is ongoing in all locker rooms.
Boiler room work ongoing.
Dominion Energy installing the gas main to the building.
Rocky Mountain Power installing the main electrical service.
Swimming pool excavation complete. Installation underway.
Work in weight room and dance studio continues.
Cyprus High School Building Construction
Continuing underground plumbing for locker rooms and gymnasium.
Locker rooms and gymnasium rebar being installed and concrete footings being poured.