Cyprus High School





Skyline High School





West Lake STEM Junior High





Cyprus High School
Skyline High School
West Lake STEM Junior High
West Lake STEM Junior High School Building Construction
Continued placement of footings and foundations which are 40% complete.
Utilities, including plumbing drain lines, are 10% complete.
Electrical floor outlet installation is 10% complete.
Site storm drain is complete.
Fire and water lines have been tied into the existing Granger/Hunter Water Improvement District lines in the street.
Skyline High School
Athletics Complex & Academics Building
Mechanical, electrical, and plumbing continues throughout athletics building.
Pool equipment is energized and circulating water.
Flooring ongoing throughout athletics building.
Base is being placed at artificial turf field.
West concrete panel fencing is 85% complete.
Chain link fencing is ongoing at north property line.
Academics underground mechanical, electrical, and plumbing is being installed.
Salt Lake City Public Utilities water main is being sanitized for testing.
Softball backstop footings and fencing is underway.
Cyprus High School
Building Construction
Tilt panels for gymnasium have been cast in concrete.
Pool foundation walls are complete.
Other foundation walls are being formed now and waiting for reinforcing steel.
Auditorium and stage walls have been formed, scheduled to pour 6/6/22
Underground electrical in kitchen area is being installed for transformers and generators.
All casting slabs for tilt walls are in place.
Crane and crane paths are in place, in preparation for standing tilt walls which is expected to begin late June.
West Lake STEM Junior High School Building Construction
40% of excavation for footings has been completed.
Footings and foundation walls are in progress.
Storm water drainage system has begun.
Skyline High School Athletics Complex & Academics Building
Field Turf has commenced work on the synthetic turf field.
Forming walls at the Millcreek pedestrian staircase.
MEP finish work ongoing.
Main entrance storefront and doors installed.
Flooring has commenced in locker rooms, weight room, gymnasium, and dance room.
Site work continues at the playing fields.
Fencing continues at the west and north fence lines.
Pool has been drained, cleaned, and refilled. Pool deck is complete.
Training and commissioning of the pool scheduled for May.
Mechanical room work ongoing.
Skyline Campus
Cyprus High School Building Construction
Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.
Historic increases in construction costs have impacted the original timeline for school rebuilds and remodels. As such, many Phase 1 projects have been delayed by 7-9 years.
The Phase 1 timeline is still based on a ‘worst first’ schedule. In addition to these major projects, security upgrades and small scale remodels will continue. Read more about the impacts of cost escalations on school projects.
The anticipated start dates for Phase 1 projects are listed below.
SCHOOL | PROJECT | ORIGINAL PROJECTED START DATE | UPDATED PROJECTED START DATE |
---|---|---|---|
Roosevelt (Olene Walker Elementary) | Rebuild | 2018 | 2019 |
South Kearns | Rebuild | 2018 | 2019 |
Hunter High School | Addition | 2018 | 2019 |
Evergreen Jr. High | Remodel | 2018 | 2018 |
Valley Jr. High | Remodel | 2018 | 2018 |
Howard Driggs Elementary | Remodel | 2019 | 2019 |
Rosecrest Elementary | Remodel | 2019 | 2019 |
West Kearns Elementary | Rebuild | 2019 | 2027 |
Cyprus High School | Rebuild | 2020 | 2020 |
Skyline High School | Rebuild | 2020 | 2020 |
Calvin Smith Elementary | Remodel | 2021 | 2028 |
Moss Elementary | Remodel | 2021 | 2028 |
Plymouth Elementary | Remodel | 2021 | 2028 |
Arcadia | Rebuild | 2022 | 2029 |
Taylorsville High School | Addition | 2022 | 2028 |
Orchard Elementary | Rebuild | 2023 | 2031 |
Hillsdale Elementary | Remodel | 2023 | 2029 |
Kennedy Jr. High | Remodel | 2023 | 2029 |
Academy Park Elementary | Rebuild | 2024 | 2034 |
Kearns Jr. High | Rebuild | 2024 | 2033 |
Magna Elementary | Remodel | 2024 | 2032 |
Valley Crest Elementary | Remodel | 2024 | 2032 |
Sandburg Elementary | Rebuild | 2025 | Closed - 2023 |
Lincoln Elementary | Remodel | 2025 | 2033 |
Pioneer Elementary | Remodel | 2025 | 2033 |
Eastwood Elementary | Rebuild | 2026 | 2035 |
Crestview Elementary | Remodel | 2026 | 2034 |
Spring Lane Elementary | Rebuild | 2027 | Closed - 2023 |
Cottonwood Elementary | Remodel | 2027 | 2035 |
Evergreen Jr. High | Rebuild | 2028 | 2037 |
Valley Jr. High | Rebuild | 2028 | 2036 |
Oakridge Elementary | Rebuild | 2028 | 2037 |