Skyline High School





West Lake Jr High




West Lake STEM Junior High School
Building Construction
Soil pad compaction under the building footprint is complete.
Excavation for underground utilities and footings has begun.
Reinforcing and forms placement for footings is in progress.
First footing concrete placement occurred 04/01/22.
Skyline High School
Athletics Complex & Academics Building
New pool has been filled and is circulating water.
Existing pool was drained and is being tested for asbestos and abatement.
Boilers are operational and air handling units are providing warm air.
Gymnasium floor has been acclimating to building temperature and humidity.
Field Turf mobilized the week of 04/04/22.
Tiling at bathrooms and pool is ongoing.
Site work continues, including perimeter and athletic field fencing.
Cyprus High School
Building Construction
Gymnasium slab on grade is being poured for locker rooms, wrestling room, coaches’ offices, along with PE locker rooms.
Framing up tilt walls, prepping for rebar and electrical construction. Tilt walls concrete pouring to begin 04/11/22.
Pool footing has been installed, excavated and filled in with structural fill dirt and made into a crane path for tilt panels.
Geo Energy drilling will be ongoing for the next year.
Building footings have been installed, underground plumbing and electrical installation areongoing.
Retaining walls are currently being installed along Cordero Drive.
West Lake STEM Junior High School Building Construction
Removing remaining grass and parking lot asphalt in building footprint.
Skyline High School Athletics Complex & Academics Building
Finishing tile work in locker rooms, lockers onsite.
Start up of air handlers has begun, boilers to be started first week of March.
Earthwork continues on athletic fields.
Retaining walls and fences on north and west property lines are under way.
Foundation poured for softball press box.
Footings have been formed for the east wall of the academics building.
Metal siding is being installed on the mechanical penthouse.
Pool lining is being installed.
Cyprus High School Building Construction
Excavating orchestra pit.
Placing footings for automotive shops and kitchen areas.
Installing retaining wall along Cordero Drive.
Several casting slabs placed.
Framing tilt walls for athletics.
Installing drainage for southeast portion of lot.
Continuing with underground plumbing and electrical.
West Lake STEM Junior High School: School Design
Contract awarded to Hogan.
Pre-construction meeting with Hogan was01/24/22.
Perimeter security fencing installed and job trailer delivered to site on 1/28/22.
Groundbreaking – Concept to hold on March 18 – anniversary of earthquake.