• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

All Updates

December 2021 Construction Photos

December 2021

Cyprus High School

Skyline High School

Filed Under: Uncategorized

Status of Projects December 2021 – West Lake

December 2021

West Lake STEM Junior High School: School Design

West Lake Junior Community Council reviewed the new school floor plan, elevations and color schemes. The exterior colors were sent out to the community at large for feedback.

Pre-bid meeting was 12/01/21.

Mountain Red / Pearl Taupe was the
top choice with 51% of the votes.
Mountain Red / Pearl Taupe was the top choice with 51% of the votes.
Platinum / Cimarron was the second
choice with 31% of the votes.
Platinum / Cimarron was the second choice with 31% of the votes.
Ochre Buff / Colonial Tan was the
third
choice with 17% of the votes.
Ochre Buff / Colonial Tan was the third choice with 17% of the votes.

Filed Under: Project Updates, West Lake

Status of Projects December 2021 – Skyline

December 2021

Skyline High School: Athletics Complex

  • Pool excavation complete.
  • Kitchen and cafeteria demolished.
  • Mount Olympus sewer main work at north property line has started.
  • Electrical work at north pedestrian walkway is progressing.
  • The tilt panel casting slab at the softball complex has been placed.
  • Earth work at demolished art building in progress.
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Shared north drive verti-block retaining wall  Hughes General Contractors
Demolition of arts building
Pool lobby storefront
Locker room tiling

Filed Under: Project Updates, Skyline

Status of Projects December 2021 – Cyprus

December 2021

Cyprus High School: Builing Construction

Continuing underground plumbing for gymnasium and locker rooms.

Gymnasium and locker rooms rebar is being installed and concrete footings are being poured.

The New Cyprus High School

  • Project Timeline
    • 11/04 – Submittal List Returned to Architect with Requested Revisions Incorporated
    • 11/19 – First Pour of Concrete Footings
    • 11/22 – U/G Sewer Utility Work Started
    • 11/29 – Building Site Preparation Continues
    • 11/29 – U/G MEP Installation Continues
    • 11/29 – Geothermal Drilling Work Planned to Begin, pending materials procurement
  • Manpower Onsite
    • Snapshot from Total = Westland (4), Suntec (5), KSC (6), US Mech (8), CR Lighting (4)
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Constructionf
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction

Filed Under: Cyprus, Project Updates

Ground Breaks on New Cyprus High School

November 2021

Construction has commenced on the new Cyprus High School, and the Magna community and Granite School District are celebrating this momentous step in the school’s 100+ year history.

Cyprus students joined Granite board members, local elected officials, alumni, and community members at the school’s new site (8400 W. 4000 South) to ceremonially turn the dirt that will eventually serve as a foundation for the Home of Pirates.

Filed Under: Cyprus

November 2021 Construction Photos

November 2021

Cyprus High School

Skyline High School

West Lake STEM Jr. High

Filed Under: Cyprus, Skyline, West Lake

Status of Projects November 2021 – West Lake

November 2021

West Lake STEM J unior High School – Demolition / Site Preperation

  • The demolition of the building is done
  • Soils are being imported, compacted and site is being staged for construction.
  • Soil compaction testing is being conducted and all tests so far have passed inspection.

West Lake Demolition

West Lake Demolition
West Lake Demolition
West Lake Demolition
West Lake Demolition

West Lake STEM Junior High School – Replacement

  • Project is in design.
  • 90% plan review was held on 12//03/2021.
  • Request for Proposal has been issued fo contractors for pre-qualification.
  • Bid release 11/29/2021.
West Lake Site Plan map
West Lake Site Plan
First Floor map
First Floor
Second Floor map
Second Floor
School diagram
west lake jhs replacement diagram

Filed Under: Project Updates, West Lake

Status of Projects November 2021 – Skyline

November 2021

Skyline High School – Athletics Complex

  • Mechanical, electrical and plumbing are ongoing
  • Interior painting and locker room tile are underway.
  • Retaining walls and perimeter fencing to begin early November.
  • Demolition contractor will mobilize mid November for woodshop / arts building and cafeteria.

Skyline Campus & Pool

Skyline Campus & Pool construction
Skyline Campus & Pool construction

Filed Under: Project Updates, Skyline

Status of Projects November 2021 – Cyprus

November 2021

Cyprus High School – Building Construction

  • Groundbreaking ceremony was held 11/01/2021.
  • Contractors are preparing footings, starting in the gymnasium, locker rooms, and swimming pool.
  • Underground plumbing is progressing for the gymnasium locker rooms.

Cyprus Building Construction

Cyprus Building Construction
Cyprus Building Construction

Filed Under: Cyprus, Project Updates

Campus Expansion Projects – October 2021

October 2021

West Lake Family & Consumer Sciences Building

The project is complete and backordered furniture is being shipped as available. This modular building is located on the temporary West Lake campus (formerly Westbrook Elementary).

Taylorsville High School Relocatable Classroom Complex

The project is complete and backordered furniture is shipping. This complex is located on the eastern portion of the campus to accommodate the added students from grade reconfiguration. It features 16 classrooms as well as restrooms. It has colloquially been dubbed ‘The Villa’ by students.

Filed Under: Feature, West Lake

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 10
  • Page 11
  • Page 12
  • Page 13
  • Page 14
  • Interim pages omitted …
  • Page 18
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2025 Granite School District

 

Loading Comments...