West Lake STEM Junior High School
Building Construction
Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.
West Lake STEM Junior High School
Building Construction
Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.
West Lake Junior High School STEM (Westbrook Campus): FACS Modular Building
Building is 100% complete.
Backordered furniture is shipping as available.
West Lake STEM Junior High School: Abatement / Demolition
Building abatement is 100% complete.
Demolition is at 40%, with completion scheduled for mid November.
Classroom wings have been demolished and debris hauled away.
Demolition of the auditorium and gymnasium is on going.
West Lake STEM Junior High School: Replacement
Estimated project completion is 2024.
Design is in process with bidding in December 2021.
New West Lake is based on existing Utah middle school buildings using 21 st century design with flexibility to support current and future learning activities.
Preliminary West Lake Floor Plan
Cyprus High School
Skyline High School
West Lake STEM Junior High
Cottonwood High Auditorium Control Booth
Granite Technical Institute Third Floor Labs
Security Upgrades
Turf Fields
West Lake STEM Junior High School
Building Construction
Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.
Cyprus High School
Skyline High School
West Lake STEM Junior High
West Lake STEM Junior High School Building Construction
Continued placement of footings and foundations which are 40% complete.
Utilities, including plumbing drain lines, are 10% complete.
Electrical floor outlet installation is 10% complete.
Site storm drain is complete.
Fire and water lines have been tied into the existing Granger/Hunter Water Improvement District lines in the street.
West Lake STEM Junior High School Building Construction
40% of excavation for footings has been completed.
Footings and foundation walls are in progress.
Storm water drainage system has begun.