• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List

West Lake

Status of Projects January 2024 – West Lake STEM

January 2024

Updates:

  • Glass installation at perimeter of building continues and is over 75% complete.
  • Installation of interior finishes such as tile, paint, and ceiling grid with light fixtures continues.
  • Final portion of interior slab on grade at north end of commons area has been placed.
Glass installation at building exterior
Insulation and decorative metal panels
Wall tile and painting in CTE wing
Pumps and piping in boiler room
Concrete slab in commons area

Filed Under: West Lake

Status of Projects December 2023 – West Lake STEM

December 2023

Updates:

  • Roofing membrane is complete, waiting on metal flashing and wall caps to be completed
  • Two Rooftop air handling units have been placed.
  • Glass is being installed around the perimeter of the building.
  • Installation of interior finishes such as tile and paint continue.
  • Concrete floor in the auditorium has been placed.
  • Millwork, overhead doors, and ceiling grids are being installed in the classrooms.
  • Kitchen framing is complete and drywall has begun.
Library and Teachers hub weathered in.
Front entrance looking East.
Auditorium slab has been placed.
Auditorium risers have been placed.
Kitchen framing complete.
Rooftop air handlers placed.

Filed Under: West Lake

Status of Projects November 2023 – West Lake STEM

November 2023

Updates:

  • Roofing is 90% complete.
  • Glass is being installed around the perimeter of the building.
  • Installation of interior finishes such as tile and paint continue.
  • Landscaping has begun in the area east of the school.
  • Rough grading of the athletic field has been completed and the running track is paved and striped.
  • Parking, bus, and fire lane paving is complete.
  • Millwork, overhead doors, and ceiling grids are being installed in the classrooms.
Commons Area
Track Paved and Striped
Millwork, overhead door, and ceiling grids.
Millwork in science lab rooms.

Filed Under: West Lake

Status of Projects October 2023 – West Lake STEM

October 2023

Updates:

  • Roofing is 75% complete.
  • Glass is being installed around the perimeter of the building.
  • Installation of interior finishes such as tile and paint continue.
  • Landscaping has begun in the area east of the school.
  • Rough grading of the athletic field and running track is progressing.
Exterior metal finish panel installation
Running track concrete placement complete
Large curtain wall window at commons area
Metal stud framing installed in kitchen area

Filed Under: West Lake

Status of Projects May 2023 – West Lake STEM

May 2023

Rough-ins in three of the academic wings are nearly complete, roofing has begun, and drywall will begin soon.

Decking for running track in gymnasium is being installed.

Interior masonry walls in auditorium are in progress.

Structural masonry is mostly complete and veneer facing is in progress.




Brick veneer facing on gymnasium.



Masonry walls for service courtyard.



Interior metal stud framing in academics.



Running track in gymnasium.



Acoustic roof decking over commons corridor.



Roofing trusses over choral room.



Interior masonry walls in auditorium.



Brick veneer facing on gymnasium.

Filed Under: West Lake

Status of Projects April 2023 – West Lake STEM

April 2023

West Lake STEM Junior High School
Building Construction

Masonry walls for band, choral, and the auditorium are 95% complete.

Masons are placing veneer brick at exterior walls in the mechanical/cafeteria wing.

Structural steel placement in the administrative area is nearly complete.Roof decking is 65% in place. Once the roof is in place, drywall installation will begin in the two south wings.

Metal stud framing, plumbing, electrical, and mechanical systems are nearly complete on the first floor in the south wings of the academic building.




South academics wing.



Brick veneer facing.



HVAC systems.



Main office structural steel.

Filed Under: Project Updates, West Lake

Status of Projects March 2023 – West Lake STEM

March 2023

West Lake STEM Junior High School
Building Construction

Steel beams being installed over kitchen and mechanical area.
Interior framing, plumbing, electrical, and mechanical system installation continues in academic classrooms.
Roof decking and steel erecting in progress in entry and commons area.
Boilers and chiller are set in place.
Auditorium and athletics walls are 90% complete.

Boilers and chiller are set in place
Boilers and chiller are set in place
Boilers and chiller are set in place
Boilers and chiller are set in place
Auditorium walls in progress
Auditorium walls in progress
Site overview
Site overview
Mechanical, plumbing, electrical, and framing in classroom wing
Mechanical, plumbing, electrical, and framing in classroom wing
Steel beams being installed
Steel beams being installed
Mechanical, plumbing, electrical, and framing in classroom wing
Mechanical, plumbing, electrical, and framing in classroom wing

Filed Under: Project Updates, West Lake

Status of Projects February 2023 – West Lake STEM

February 2023

West Lake STEM Junior High School
Building Construction

Band and choral room masonry walls are 90% complete and were scheduled to top out the week of January 30th upon which masons will move to auditorium area.
Contractor is placing decking for second floor in northwest academic wing and preparing to place roof decking on southeast academic wing.
Metal stud, framing, interior, plumbing, electrical, lighting, power, and mechanical system installation continues in south wings.

Southwest academic wing exterior sheathing
Southwest academic wing exterior sheathing
Gymnasium roof decking
Gymnasium roof decking
Southeast academic steel trusses
Southeast academic steel trusses
Southeast academic framing 1st floor
Southeast academic framing 1st floor
Site overview auditorium and administration walls started
Site overview auditorium and administration walls started

Filed Under: Project Updates, West Lake

Status of Projects January 2023 – West Lake STEM

January 2023

West Lake STEM Junior High School
Building Construction

Gymnasium roof trusses and 90% of roof decking is in place.
Locker room masonry walls 90% complete.
Kitchen and mechanical rooms masonry walls 50% complete.
Southwest academic wing framing is complete, exterior sheathing is 75% first floor utilities are 50% complete.
Southeast academic wing second floor decking and teacher hub/commons area concrete slab ready to be placed.

Masonry for kitchen and mechanical rooms
Masonry for kitchen and mechanical rooms
Gymnasium steel roofing
Gymnasium steel roofing
Commons area near teacher’s hub
Commons area near teacher’s hub
Academic building and gymnasium
Academic building and gymnasium
Southwest academic wing utilities and framing
Southwest academic wing utilities and framing

Filed Under: Project Updates, West Lake

Status of Projects November 2022 – West Lake

November 2022

West Lake STEM Junior High School
Building Construction

Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.

Gymnasium
Gymnasium
Academic wing
Academic wing
Interior framing in academic wing
Interior framing in academic wing
Exterior sheathing
Exterior sheathing
Stairs at south commons
Stairs at south commons
Stairs at south commons
Stairs at south commons
Preparation for paving of north parking lot –October 27
Preparation for paving of north parking lot –October 27
Library and teacher collaboration steel structure
Library and teacher collaboration steel structure
Roof decking and structural steel for sheer wall –southwest wing
Roof decking and structural steel for sheer wall –southwest wing
West elevation -gymnasium
West elevation -gymnasium
East elevation –gymnasium reaching top out height
East elevation –gymnasium reaching top out height

Filed Under: Project Updates, West Lake

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Kearns Elementary
  • All Updates
  • Phase 1 Project List


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

Loading Comments...