Granite Technical Institute – Pharmacy and Animation Labs



Cyprus High School





Skyline High School





West Lake STEM Jr High





Cyprus High School
Skyline High School
West Lake STEM Junior High
West Lake STEM Junior High School Building Construction
Continued placement of footings and foundations which are 40% complete.
Utilities, including plumbing drain lines, are 10% complete.
Electrical floor outlet installation is 10% complete.
Site storm drain is complete.
Fire and water lines have been tied into the existing Granger/Hunter Water Improvement District lines in the street.
West Lake STEM Junior High School Building Construction
40% of excavation for footings has been completed.
Footings and foundation walls are in progress.
Storm water drainage system has begun.
West Lake STEM Junior High School
Building Construction
Soil pad compaction under the building footprint is complete.
Excavation for underground utilities and footings has begun.
Reinforcing and forms placement for footings is in progress.
First footing concrete placement occurred 04/01/22.
West Lake STEM Junior High School: School Design
Contract awarded to Hogan.
Pre-construction meeting with Hogan was01/24/22.
Perimeter security fencing installed and job trailer delivered to site on 1/28/22.
Groundbreaking – Concept to hold on March 18 – anniversary of earthquake.
West Lake STEM Junior High School
School Design
Documents have gone out for bid.
Contractor bids due Thursday, January 6, 2022.
West Lake STEM Junior High School: School Design
West Lake Junior Community Council reviewed the new school floor plan, elevations and color schemes. The exterior colors were sent out to the community at large for feedback.
Pre-bid meeting was 12/01/21.