Cyprus High School





Skyline High School





West Lake STEM Junior High





Cottonwood High Auditorium Control Booth




Granite Technical Institute Third Floor Labs




Security Upgrades





Turf Fields





Cyprus High School
Skyline High School
West Lake STEM Junior High
Cottonwood High Auditorium Control Booth
Granite Technical Institute Third Floor Labs
Security Upgrades
Turf Fields
West Lake STEM Junior High School
Building Construction
Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.
Cyprus High School
Skyline High School
West Lake STEM Junior High
West Lake STEM Junior High School Building Construction
Continued placement of footings and foundations which are 40% complete.
Utilities, including plumbing drain lines, are 10% complete.
Electrical floor outlet installation is 10% complete.
Site storm drain is complete.
Fire and water lines have been tied into the existing Granger/Hunter Water Improvement District lines in the street.
West Lake STEM Junior High School Building Construction
40% of excavation for footings has been completed.
Footings and foundation walls are in progress.
Storm water drainage system has begun.
West Lake STEM Junior High School
Building Construction
Soil pad compaction under the building footprint is complete.
Excavation for underground utilities and footings has begun.
Reinforcing and forms placement for footings is in progress.
First footing concrete placement occurred 04/01/22.
West Lake STEM Junior High School: School Design
Contract awarded to Hogan.
Pre-construction meeting with Hogan was01/24/22.
Perimeter security fencing installed and job trailer delivered to site on 1/28/22.
Groundbreaking – Concept to hold on March 18 – anniversary of earthquake.