West Lake STEM Junior High School
Building Construction
Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.
![Footings](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-75-300x170.png)
![Floor slab for teacher’s common area](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-76-300x224.png)
![North parking lot curb & gutter](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-77-300x226.png)
![North parking lot curb & gutter](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-78-300x168.png)
![Structural steel framing being erected](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-79-300x188.png)
![Structural steel framing being erected](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-80-300x135.png)