Watch the presentation in the video below for updates about Granite School District construction projects (0:00 – 23:15). This presentation was given in the January 2024 Board of Education Administrative Session. Click here for a copy of the slides.
Project Updates
West Lake STEM Jr. High Construction Tour
Cyprus High Construction Update Video
Status of Projects January 2024 – Skyline High School
Updates:
Academics
- Activity Stair steel has started in the Cafeteria Space
- Curtain wall framing (Glass wall) has started around the exterior of the Cafeteria
- Accent wall paint has started throughout the building
- Tile is nearing completion in the Kitchen
- Tile has started in main corridors on Level 2
- Grid ceiling complete in Administration Suite
- Athletics Lobby is now open to public for use, with some finishes that still need completing
- Paint started on Level 3 of the main Academics Building
- Structure completed on the stair tower on south end of the main Academics building
Recent Pictures:
Status of Projects January 2024 – Cyprus High School
Updates:
Site Work:
● Fencing and flat work on the North side of the site
Athletics:
● Drops ceiling grid level 1 of athletics
Pool:
●Locker room framing, drywall and plumbing
●Tile in the lifeguard room
Mechanical Yard:
● Tilt walls stood in place
● Steel erection
CTE Buildings:
● Steel stud and metal decking on the breezeway
Academics:
● Paint and drywall 2nd and 3rd levels
● Exterior kiln walls stood into place
● Testing center cement poured
Social Studies:
● Curtain wall glass installation
● Drywall and insulation 2ndand 3rdfloor
Performing Arts:
● Vestibule curtain wall installation
● Concrete pour backs in the vestibule area
Recent Photos:
Status of Projects January 2024 – West Lake STEM
Updates:
- Glass installation at perimeter of building continues and is over 75% complete.
- Installation of interior finishes such as tile, paint, and ceiling grid with light fixtures continues.
- Final portion of interior slab on grade at north end of commons area has been placed.
Status of Projects December 2023 – West Lake STEM
Updates:
- Roofing membrane is complete, waiting on metal flashing and wall caps to be completed
- Two Rooftop air handling units have been placed.
- Glass is being installed around the perimeter of the building.
- Installation of interior finishes such as tile and paint continue.
- Concrete floor in the auditorium has been placed.
- Millwork, overhead doors, and ceiling grids are being installed in the classrooms.
- Kitchen framing is complete and drywall has begun.
Status of Projects December 2023 – Skyline High School
Recent Pictures:
on, ceiling tile being dropped.
painted, exterior door installed.
Status of Projects December 2023 – Cyprus High School
Updates:
Site Work:
● Asphalt paving Southwest parking lot
Athletics:
● Drop ceiling grid, light installation level 1
● 2ndlevel bathroom tile
Pool:
●Locker room framing, drywall and plumbing
●Acid etched glass installed
CTE Buildings:
● Tilt panels connecting CTE building with the main building
Administration:
● Drywall 3rd and 4th floor
Cafeteria/Common Area:
● Skylight on the 3rd floor
Social Studies:
●Framing 3rd and 4th floor
●Rough electrical 3rd and 4th floor
●Air handler set on the 4th floor
Performing Arts:
● Fin tube heaters set into place
● Dressing room framing
Recent Photos:
Status of Projects November 2023 – Cyprus High School
Updates:
Site Work:
● Asphalt paved on the North end of the site
● Asphalt prep for the Southwest parking lot
● Outbuildings concrete floors poured
Athletics:
● Basketball standards installed
● Tile in the PE locker rooms
Pool:
● Locker room framing and plumbing
CTE Buildings:
● Tilt panels stood into place
Administration:
● Framing drywall throughout classroom spaces
Social Studies:
● Exterior glass installed
● Exterior framing
Cafeteria/Common Area:
● Level 3 concrete floor poured
● Exterior framing
Performing Arts:
● HVAC in corridors and Scenery/shop storage
● Glass installation in the Choral and Band room