GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects February 2023 – Cyprus High School

February, 2023 by Granite School District Communications Office

Cyprus High School
Building Construction

Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.

Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Gymnasium floor ready for concrete
Framing mechanical room
Framing mechanical room
Framing bathrooms
Framing bathrooms
Roof steel decking
Roof steel decking
Auditorium cloud steel
Auditorium cloud steel
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Athletics framing, HVAC, fire sprinkler, plumbing
Site Overview
Site Overview

Filed Under: Cyprus, Project Updates

Status of Projects February 2023 – Skyline High School

February, 2023 by Granite School District Communications Office

Skyline High School
Athletics Complex

Softball building is currently being painted and tile is being installed.
Kitchen and testing center walls continue to be stood.
Steel continues with roof joists and decking.
Looking into options to strengthen existing auditorium wall exposed by gymnasium demolition as this will be the exterior wall for next 3 years.

Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium
Softball exterior walls heated prepping for paint
Softball exterior walls heated prepping for paint
Softball interior walls prepping for paint
Softball interior walls prepping for paint
Bathroom tile being installed
Bathroom tile being installed
Testing center roof joists with decking installed
Testing center roof joists with decking installed
Manufacturing lab / kitchen stairs being installed
Manufacturing lab / kitchen stairs being installed
Graphics and sewing rooms
Graphics and sewing rooms
Tilt wall ready to be stood
Tilt wall ready to be stood
Demolition of gymnasium from auditorium
Demolition of gymnasium from auditorium

Filed Under: Project Updates, Skyline

Status of Projects January 2023 – West Lake STEM

January, 2023 by Granite School District Communications Office

West Lake STEM Junior High School
Building Construction

Gymnasium roof trusses and 90% of roof decking is in place.
Locker room masonry walls 90% complete.
Kitchen and mechanical rooms masonry walls 50% complete.
Southwest academic wing framing is complete, exterior sheathing is 75% first floor utilities are 50% complete.
Southeast academic wing second floor decking and teacher hub/commons area concrete slab ready to be placed.

Masonry for kitchen and mechanical rooms
Masonry for kitchen and mechanical rooms
Gymnasium steel roofing
Gymnasium steel roofing
Commons area near teacher’s hub
Commons area near teacher’s hub
Academic building and gymnasium
Academic building and gymnasium
Southwest academic wing utilities and framing
Southwest academic wing utilities and framing

Filed Under: Project Updates, West Lake

Status of Projects January 2023 – Cyprus High School

January, 2023 by Granite School District Communications Office

Cyprus High School
Building Construction

Auditorium steel trusses, cross bracing and the catwalk are all being installed.
More auditorium tilt panels being prepped to be placed.
Gymnasium steel decking is done around the running track and ½ the concrete has been placed for the track.
Gymnasium floor is being prepped for concrete.
The cardio & wrestling room is being framed, along with HVAC and rough electrical being installed.

Auditorium roof decking and catwalk
Auditorium roof decking and catwalk
Cardio room rough in
Cardio room rough in
Gymnasium stairs
Gymnasium stairs
Gym floor being prepped for concrete
Gym floor being prepped for concrete
Windows have been sealed waiting for frames
Windows have been sealed waiting for frames

Filed Under: Cyprus, Project Updates

Status of Projects January 2023 – Skyline High School

January, 2023 by Granite School District Communications Office

Skyline High School
Athletics Complex

Tennis court edges have been tensioned and poured in concrete.
Softball building drywall has been hung.
Pathway along north walkway opening in January.
Demolition and separation of gymnasium from the auditorium continues.
Tilt panels for academics building continue to be placed.
Classroom steel trusses are being installed.

Classroom steel trusses
Classroom steel trusses
Demolition of gymnasium from auditorium.
Demolition of gymnasium from auditorium
Pathway emergency phones
Pathway emergency phones
Site overview
Site overview

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – West Lake

November, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Structural steel and decking for the second floor of the southwest classroom wing is complete.
Exterior sheathing of walls has begun.
Masonry walls for gymnasium currently at 28’.
Slab on grade placement continues, approximately 75% complete.
Concrete curbing for north parking lot complete.

Gymnasium
Gymnasium
Academic wing
Academic wing
Interior framing in academic wing
Interior framing in academic wing
Exterior sheathing
Exterior sheathing
Stairs at south commons
Stairs at south commons
Stairs at south commons
Stairs at south commons
Preparation for paving of north parking lot –October 27
Preparation for paving of north parking lot –October 27
Library and teacher collaboration steel structure
Library and teacher collaboration steel structure
Roof decking and structural steel for sheer wall –southwest wing
Roof decking and structural steel for sheer wall –southwest wing
West elevation -gymnasium
West elevation -gymnasium
East elevation –gymnasium reaching top out height
East elevation –gymnasium reaching top out height

Filed Under: Project Updates, West Lake

Status of Projects November 2022 – Skyline High School

November, 2022 by Granite Schools

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – Cyprus

November, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls

Filed Under: Cyprus, Project Updates

Status of Projects October 2022 – West Lake

October, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.

Site overview
Site overview
Site overview
Site overview
Gymnasium masonry walls
Gymnasium masonry walls
Gymnasium and locker room masonry walls
Gymnasium and locker room masonry walls
Classroom floor decking
Classroom floor decking
Classroom floor decking
Classroom floor decking
FACS concrete slab
FACS concrete slab
Mechanical equipment
Mechanical equipment

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October, 2022 by Granite Schools

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.

Floor boxes for testing center
Floor boxes for testing center
Underground utilities
Underground utilities
Grading at softball field
Grading at softball field
Grading at tennis courts
Grading at tennis courts
Sod on practice field
Sod on practice field
Concrete pour and tilt panels being formed
Concrete pour and tilt panels being formed
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
West pool stairs graphic
West pool stairs graphic

Filed Under: Project Updates, Skyline

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • …
  • 11
  • Next Page »
 

Loading Comments...