GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects November 2022 – Skyline High School

November, 2022 by Granite Schools

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.

Athletic building in background, new academic phase under construction
Athletic building in background, new academic phase under construction
Tennis courts in progress
Tennis courts in progress
Sod on softball field
Sod on softball field
Sod on softball field
Sod on softball field
Tennis court post-tension slab
Tennis court post-tension slab

Filed Under: Project Updates, Skyline

Status of Projects November 2022 – Cyprus

November, 2022 by Granite Schools

Cyprus High School
Building Construction

Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.

Steel truss placement over athletics and gymnasium

Steel truss placement over athletics and gymnasium
Steel truss placement over athletics and gymnasium
Future stage, orchestra pit, and seating
Future stage, orchestra pit, and seating
Roof decking over locker rooms
Roof decking over locker rooms
Storm water retention chambers
Storm water retention chambers
Retaining walls
Retaining walls

Filed Under: Cyprus, Project Updates

Status of Projects October 2022 – West Lake

October, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.

Site overview
Site overview
Site overview
Site overview
Gymnasium masonry walls
Gymnasium masonry walls
Gymnasium and locker room masonry walls
Gymnasium and locker room masonry walls
Classroom floor decking
Classroom floor decking
Classroom floor decking
Classroom floor decking
FACS concrete slab
FACS concrete slab
Mechanical equipment
Mechanical equipment

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October, 2022 by Granite Schools

Skyline High School
Athletics Complex

Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.

Floor boxes for testing center
Floor boxes for testing center
Underground utilities
Underground utilities
Grading at softball field
Grading at softball field
Grading at tennis courts
Grading at tennis courts
Sod on practice field
Sod on practice field
Concrete pour and tilt panels being formed
Concrete pour and tilt panels being formed
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
Tilt panels for academic phase
West pool stairs graphic
West pool stairs graphic

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – West Lake

October, 2022 by Granite Schools

West Lake Junior High School STEM (Westbrook Campus): FACS Modular Building

Building is 100% complete.

Backordered furniture is shipping as available.

West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building
West Lake FACS Modular Building

West Lake STEM Junior High School: Abatement / Demolition

Building abatement is 100% complete.
Demolition is at 40%, with completion scheduled for mid November.
Classroom wings have been demolished and debris hauled away.
Demolition of the auditorium and gymnasium is on going.

West Lake Demolition
West Lake Demolition
West Lake Demolition
West Lake Demolition

West Lake STEM Junior High School: Replacement

Estimated project completion is 2024.
Design is in process with bidding in December 2021.
New West Lake is based on existing Utah middle school buildings using 21 st century design with flexibility to support current and future learning activities.

Preliminary West Lake Floor Plan

Sample Floor Plan (First Floor)
Sample Floor Plan (First Floor)
Sample Floor Plan (Second Floor)
Sample Floor Plan (Second Floor)

Filed Under: Project Updates, West Lake

Status of Projects October 2022 – Skyline

October, 2022 by Granite Schools

Skyline High School: Athletics Complex

Athletics phase is 60% complete.
Baseball diamond and football stadium are complete.
Interior painting is in progress.
Excavation for the pool is scheduled to begin in October.
Grading is underway for the athletic fields.

Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool
Skyline Campus & Pool

Filed Under: Project Updates, Skyline

Status of Projects October 2022 – Cyprus

October, 2022 by Granite Schools

Cyprus High School: Site Preparation

Site preparation is 100% complete.
Mass grading has been completed.
Kennecott site storm water drainage redirection project is completed.

Cyprus Site Work
Cyprus Site Work
Cyprus Site Work
Cyprus Site Work

Cyprus High School: Building Construction

Purchase order was issued to Westland Construction for construction of the new Cyprus High School.
Notice to proceed issued 09/13/2021.
Excavation of footings has begun.

Cyprus Footings
Cyprus Footings
Cyprus Footings
Cyprus Footings

Filed Under: Cyprus, Project Updates

August 2022 Construction Photos

August, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site
Cyprus High construction site

Skyline High School

Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site
Skyline High construction site

West Lake STEM Junior High

West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site
West Lake Junior High construction site

Cottonwood High Auditorium Control Booth

Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction
Cottonwood High control booth construction

Granite Technical Institute Third Floor Labs

GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction
GTI 3rd floor lab construction

Security Upgrades

Hartvigsen security upgrade construction
Hartvigsen School
Hartvigsen security upgrade construction
Hartvigsen School
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
Rolling Meadows security upgrade construction
Rolling Meadows Elementary
William Penn security upgrade construction
William Penn Elementary

Turf Fields

Granger High turf field replacement
Granger High School
Granger High turf field replacement
Granger High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School
Taylorsville High turf field replacement
Taylorsville High School

Filed Under: Cyprus, Project Updates, Skyline, West Lake

Status of Projects August 2022 – West Lake

August, 2022 by Granite Schools

West Lake STEM Junior High School
Building Construction

Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.

Footings
Footings
Floor slab for teacher’s common area
Floor slab for teacher’s common area
North parking lot curb & gutter
North parking lot curb & gutter
North parking lot curb & gutter
North parking lot curb & gutter
Structural steel framing being erected
Structural steel framing being erected
Structural steel framing being erected
Structural steel framing being erected

Filed Under: Project Updates, West Lake

Status of Projects August 2022 – Skyline

August, 2022 by Granite Schools

Skyline High School
Athletics Complex

Owner training is ongoing for all systems.
Turf field to be turned over on July 25, the school can start using August 1.
Grading continues at softball field, grass field, tennis courts, and west fence line.
Sod for softball field expected in September.
Bleacher installation is ongoing.
Granite security, AV, and IT installations are ongoing.
Old pool building demolition is complete.
Track installation is complete.

Academic footings
Academic footings
Academic footings
Academic footings
Existing pool demolition
Existing pool demolition
Grading at tennis court
Grading at tennis court
Indoor track
Indoor track
Indoor track
Indoor track
Bleachers in fieldhouse
Bleachers in fieldhouse
Playfields
Playfields
Playfields
Playfields
Locker room
Locker room
Accessible shower
Accessible shower
Coach offices
Coach offices

Filed Under: Project Updates, Skyline

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • …
  • 11
  • Next Page »
 

Loading Comments...