Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.





Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities ongoing in academics.
Tilt up panels starting to be placed for academics.
Structural steel going up in manufacturing lab and kitchen area.
Cyprus High School
Building Construction
Retaining wall installation at 90%.
Retaining wallcap installation along with fencing on top of thewall at northside ofthe propertyhas begun.
Storm water retentionchambers along retaining wall installed.
Gymnasium and pool tilt walls have been erected and placement of associatedsteel and framing has begun.
Orchestra pit floor has been placed.
Auditorium tilt walls erected on 10/24/22.
West Lake STEM Junior High School
Building Construction
Steel for the second floor of the southwest
classroom wing is complete. Decking has been
placed in preparation for slab.
Masonry walls are being erected.
FACS lab concrete slab has been placed.
Skyline High School
Athletics Complex
Punch list work ongoing at athletic complex.
Underground utilities continue at testing center and kitchen.
Temporary utilities being tied into the existing auditorium.
Tilt up panels being poured for academics.
Crane mobilized to set tilts in mid-October.
Sprinklers being installed at softball field.
Sod at softball field to be placed within the first half of October.
West Lake Junior High School STEM (Westbrook Campus): FACS Modular Building
Building is 100% complete.
Backordered furniture is shipping as available.
West Lake STEM Junior High School: Abatement / Demolition
Building abatement is 100% complete.
Demolition is at 40%, with completion scheduled for mid November.
Classroom wings have been demolished and debris hauled away.
Demolition of the auditorium and gymnasium is on going.
West Lake STEM Junior High School: Replacement
Estimated project completion is 2024.
Design is in process with bidding in December 2021.
New West Lake is based on existing Utah middle school buildings using 21 st century design with flexibility to support current and future learning activities.
Preliminary West Lake Floor Plan
Skyline High School: Athletics Complex
Athletics phase is 60% complete.
Baseball diamond and football stadium are complete.
Interior painting is in progress.
Excavation for the pool is scheduled to begin in October.
Grading is underway for the athletic fields.
Cyprus High School: Site Preparation
Site preparation is 100% complete.
Mass grading has been completed.
Kennecott site storm water drainage redirection project is completed.
Cyprus High School: Building Construction
Purchase order was issued to Westland Construction for construction of the new Cyprus High School.
Notice to proceed issued 09/13/2021.
Excavation of footings has begun.
Cyprus High School
Skyline High School
West Lake STEM Junior High
Cottonwood High Auditorium Control Booth
Granite Technical Institute Third Floor Labs
Security Upgrades
Turf Fields
West Lake STEM Junior High School
Building Construction
Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.
Skyline High School
Athletics Complex
Owner training is ongoing for all systems.
Turf field to be turned over on July 25, the school can start using August 1.
Grading continues at softball field, grass field, tennis courts, and west fence line.
Sod for softball field expected in September.
Bleacher installation is ongoing.
Granite security, AV, and IT installations are ongoing.
Old pool building demolition is complete.
Track installation is complete.