Watch the presentation in the video below for updates about Granite School District construction projects (1:05:50 – 1:19:21). This presentation was given in the April 2024 Board of Education Meeting. Click here for a copy of the slides.
Skyline Construction Update Video – March 2024
Status of Projects March 2024 – Skyline High School
Updates:
Academics
●High ceiling in Cafeteria painted
●Exterior glass complete at Main Entrance
●Metal wood look soffits near completion in Cafeteria
●Storefront glass frames installed at Media Center
●Interior glass in classroom groups started
●Carpet and electrical trim started in Level 2 general classrooms
●Cabinet installation ongoing in Level 3 Science classrooms
●Painting on Level 2 near completion
●Main Corridor tile complete on Levels 2 and 3
●Tile at the Smoothie Bar complete
●Plumbing fixtures set in Administration Suite bathrooms
Recent Pictures:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-5.jpg)
Cafeteria/Commons
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Skyline-11.jpg)
Status of Projects March 2024 – West Lake STEM
Updates:
- The three Academic wings are having countertops installed on cabinets, sinks installed in the restrooms, and wiring and sensors placed in the ceilings.
- The Administration wing has cabinets ready to be installed.
- The Serving area has decorative wall tile being installed.
- HVAC ducts are 90% complete.
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-9.jpg)
Status of Projects March 2024 – Cyprus High School
Updates:
Site Work/Mechanical Yard:
●Footings/foundation at the Softball, Baseball Field
●Setting the generators into place
Athletics/Pool:
●Track Handrail Shoe
●Locker being placed in the PE Locker Rooms
●Pool painting
●Window caulking
Administration/Commons:
●Level 3 framing
●Level 1 slab on grade pour
●Prepping slab on grade in the Public Square/Dining
Academics/Social Studies:
●Framing of classrooms and display cases
●Drywall around the skylights
●Frames and glazing on the stair tower
●Finish paint on Levels 2 and 3
Performing Arts:
●Curtain wall and glazing around the Lobby
Recent Photos:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-7.jpg)
Academics Building
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-8.jpg)
the Academics Building
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/Cyprus-11.jpg)
Status of Projects February 2024 – West Lake STEM
Updates:
- The three Academic wings have cabinetry, ceiling grid, electrical, and mechanical systems in place
- The Administration wing has been painted and ceiling grid installation is in progress.
- The CTE wing has interior windows installed and ceiling grid installation is in progress.
- Wall tile in corridors and restrooms is 85% complete.
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-4.jpg)
Auditorium ceiling
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/West-Lake-7.jpg)
Status of Projects February 2024 – Skyline High School
Updates:
Academics
●Activity Stairs in the cafeteria are fully erected.
●Drywall and framing are nearing completion in the cafeteria area.
●All in-wall utilities are near completion throughout the entire building.
●Ceiling grid is being worked on in all general classrooms and is complete in the Administration Suite. ●Casework/cabinets are being installed in the lab classrooms on level 4.
●Fixed glass walls have started in the general classroom groups on level 3.
●Curtain wall glass is nearing completion on the Cafeteria.
●Testing Center is now drywalled and taped.
●Trophy shelving is being installed in the new Athletics Vestibule.
●Tile is nearing completion in the Administration bathrooms.
●Fire sprinkler systems are nearing completion on 3 floors.
●Framing in the south stair tower has started.
Recent Pictures:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-11.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Skyline-12.jpg)
framed and drywalled
Status of Projects February 2024 – Cyprus High School
Updates:
Site Work:
●Planter boxes behind the home side bleachers and between Athletics and Administrative Suite
●Fencing fabric stretched between posts
●Visitor side bleachers under construction
Athletics:
● Tile in the restrooms
Pool:
●Painting
Mechanical Yard:
● Slab on grade
● Set steel
Administration:
● Slab under electric
Academics:
● Paint on 2nd and 3rd levels
● Skylights in corridor
Social Studies:
● Rough Plumbing on levels 2 and 3
● Painting accent walls and classrooms
Performing Arts:
● Painting on the stage and scenery storage
● Ceiling grid in the Band room
Recent Photos:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-2.jpg)
Administrative Suite
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-11.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-12.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-13.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/02/Cyprus-14.jpg)
Status of Projects Update: February 2024
Watch the presentation in the video below for updates about Granite School District construction projects (0:00 – 20:37). This presentation was given in the February 2024 Board of Education Administrative Session. Click here for a copy of the slides.
Status of Projects Update: January 2024
Watch the presentation in the video below for updates about Granite School District construction projects (0:00 – 23:15). This presentation was given in the January 2024 Board of Education Administrative Session. Click here for a copy of the slides.