• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Project Updates

Status of Projects February 2024 – Skyline High School

February 2024

Updates:

Academics

●Activity Stairs in the cafeteria are fully erected.
●Drywall and framing are nearing completion in the cafeteria area.
●All in-wall utilities are near completion throughout the entire building.
●Ceiling grid is being worked on in all general classrooms and is complete in the Administration Suite. ●Casework/cabinets are being installed in the lab classrooms on level 4.
●Fixed glass walls have started in the general classroom groups on level 3.
●Curtain wall glass is nearing completion on the Cafeteria.
●Testing Center is now drywalled and taped.
●Trophy shelving is being installed in the new Athletics Vestibule.
●Tile is nearing completion in the Administration bathrooms.
●Fire sprinkler systems are nearing completion on 3 floors.
●Framing in the south stair tower has started.

Recent Pictures:

Main academics building and Cafeteria as viewed from the Courtyard
Main academics building and Cafeteria as viewed from the Courtyard
Main academics building and Cafeteria as viewed from the Courtyard
Main academics building and Cafeteria as viewed from the Courtyard
Main Activity staircase and Cafeteria progress
Main Activity staircase and Cafeteria progress
Trophy case glass being installed in Athletics Vestibule
Trophy case glass being installed in Athletics Vestibule
Millwork being installed in the Chemistry Labs on level 3
Millwork being installed in the Chemistry Labs on level 3
Millwork being installed in the Chemistry Labs on level 3
Millwork being installed in the Chemistry Labs on level 3
Grid installed and fixed glass walls in progress in Level 3 classroom group
Grid installed and fixed glass walls in progress in Level 3 classroom group
Testing Center with drywall
Testing Center with drywall
Main Entrance Vestibule being framed in
Main Entrance Vestibule being framed in
Tile installed in the Administration Suite bathrooms
Tile installed in the Administration Suite bathrooms
Wall tile in Main Corridor on Level 2
Wall tile in Main Corridor on Level 2
Large soffits outside of classroom groups
framed and drywalled
Large soffits outside of classroom groups
framed and drywalled

Filed Under: Skyline

Status of Projects February 2024 – Cyprus High School

February 2024

Updates:

Site Work:
●Planter boxes behind the home side bleachers and between   Athletics and Administrative Suite
●Fencing fabric stretched between posts
●Visitor side bleachers under construction

Athletics:
● Tile in the restrooms

Pool:
●Painting

Mechanical Yard:
● Slab on grade
● Set steel

Administration:
● Slab under electric

Academics:
● Paint on 2nd and 3rd levels
● Skylights in corridor

Social Studies:
● Rough Plumbing on levels 2 and 3
● Painting accent walls and classrooms

Performing Arts:
● Painting on the stage and scenery storage
● Ceiling grid in the Band room

Recent Photos:

Planter boxes behind the home side bleachers
Planter boxes behind the home side bleachers
Planter boxes between Athletics and
Administrative Suite
Planter boxes between Athletics and
Administrative Suite
Site fencing
Site fencing
Visitor side bleachers in stadium
Visitor side bleachers in stadium
Restroom tile, Athletic building level 1
Restroom tile, Athletic building level 1
Painting in the Pool
Painting in the Pool
Slab on grade and steel setting Mechanical yard
Slab on grade and steel setting Mechanical yard
Under slab electrical in the Administrative suite
Under slab electrical in the Administrative suite
Painting in a Science classroom
Painting in a Science classroom
Skylights installed in the Academic building
Skylights installed in the Academic building
Rough plumbing level 2
Rough plumbing level 2
Painting and accents level 2
Painting and accents level 2
Painting in the scenery room of the Auditorium
Painting in the scenery room of the Auditorium
Band Room ceiling grid, Performing Arts building
Band Room ceiling grid, Performing Arts building

Filed Under: Cyprus

Status of Projects Update: February 2024

February 2024

Watch the presentation in the video below for updates about Granite School District construction projects (0:00 – 20:37). This presentation was given in the February 2024 Board of Education Administrative Session. Click here for a copy of the slides.

Filed Under: Project Updates

Status of Projects Update: January 2024

January 2024

Watch the presentation in the video below for updates about Granite School District construction projects (0:00 – 23:15). This presentation was given in the January 2024 Board of Education Administrative Session. Click here for a copy of the slides.

Filed Under: Project Updates

West Lake STEM Jr. High Construction Tour

January 2024

Filed Under: Project Updates, West Lake

Cyprus High Construction Update Video

January 2024

Filed Under: Cyprus, Project Updates

Status of Projects January 2024 – Skyline High School

January 2024

Updates:

Academics

  • Activity Stair steel has started in the Cafeteria Space
  • Curtain wall framing (Glass wall) has started around the exterior of the Cafeteria
  • Accent wall paint has started throughout the building
  • Tile is nearing completion in the Kitchen
  • Tile has started in main corridors on Level 2
  • Grid ceiling complete in Administration Suite
  • Athletics Lobby is now open to public for use, with some finishes that still need completing
  • Paint started on Level 3 of the main Academics Building
  • Structure completed on the stair tower on south end of the main Academics building

Recent Pictures:

View of the west side of the main Academics Building
Glass being installed at the northwest stair tower of the main Academics Building
Steel being installed for main staircase in
the Cafeteria
Curtain wall framing being installed on the south side of the Cafeteria
Tile installed in Culinary Arts classroom on Level 1
Tile being installed in the serving area of the Cafeteria
Metal panels being installed on the north side of the main Academics Building
Large soffits being framed in outside
of the classroom groups on level 2
LVT Flooring as it was being
installed in the Athletics Entrance
Media Center walls insulated, ready for sheetrock
Kitchen being painted above the tile, getting ready for finish equipment

Filed Under: Skyline

Status of Projects January 2024 – Cyprus High School

January 2024

Updates:

Site Work:
● Fencing and flat work on the North side of the site

Athletics:
● Drops ceiling grid level 1 of athletics

Pool:
●Locker room framing, drywall and plumbing
●Tile in the lifeguard room

Mechanical Yard:
● Tilt walls stood in place
● Steel erection

CTE Buildings:
● Steel stud and metal decking on the breezeway

Academics:
● Paint and drywall 2nd and 3rd levels
● Exterior kiln walls stood into place
● Testing center cement poured

Social Studies:
● Curtain wall glass installation
● Drywall and insulation 2ndand 3rdfloor

Performing Arts:
● Vestibule curtain wall installation
● Concrete pour backs in the vestibule area

Recent Photos:

Fencing and flat work on the north side of the site
Drops ceiling grid level 1 of athletics
Locker room framing, drywall, and plumbing
Tile in the lifeguard room
Mechanical yard tilt walls stood in place, steel erection
Steel stud and metal decking on the breezeway
Paint and drywall 2nd and 3rd levels
Exterior kiln walls stood into place
Testing center cement poured
Curtain wall glass installation
Drywall and insulation 2nd and 3rd floor
Vestibule curtain wall installation
Concrete pour backs in the vestibule area

Filed Under: Cyprus

Status of Projects January 2024 – West Lake STEM

January 2024

Updates:

  • Glass installation at perimeter of building continues and is over 75% complete.
  • Installation of interior finishes such as tile, paint, and ceiling grid with light fixtures continues.
  • Final portion of interior slab on grade at north end of commons area has been placed.
Glass installation at building exterior
Insulation and decorative metal panels
Wall tile and painting in CTE wing
Pumps and piping in boiler room
Concrete slab in commons area

Filed Under: West Lake

Status of Projects December 2023 – West Lake STEM

December 2023

Updates:

  • Roofing membrane is complete, waiting on metal flashing and wall caps to be completed
  • Two Rooftop air handling units have been placed.
  • Glass is being installed around the perimeter of the building.
  • Installation of interior finishes such as tile and paint continue.
  • Concrete floor in the auditorium has been placed.
  • Millwork, overhead doors, and ceiling grids are being installed in the classrooms.
  • Kitchen framing is complete and drywall has begun.
Library and Teachers hub weathered in.
Front entrance looking East.
Auditorium slab has been placed.
Auditorium risers have been placed.
Kitchen framing complete.
Rooftop air handlers placed.

Filed Under: West Lake

  • « Go to Previous Page
  • Page 1
  • Interim pages omitted …
  • Page 3
  • Page 4
  • Page 5
  • Page 6
  • Page 7
  • Interim pages omitted …
  • Page 17
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2026 Granite School District

 

Loading Comments...