Historic increases in construction costs have impacted the original timeline for school rebuilds and remodels. As such, many Phase 1 projects have been delayed by 7-9 years.
The Phase 1 timeline is still based on a ‘worst first’ schedule. In addition to these major projects, security upgrades and small scale remodels will continue. Read more about the impacts of cost escalations on school projects.
The anticipated start dates for Phase 1 projects are listed below.
SCHOOL | PROJECT | ORIGINAL PROJECTED START DATE | UPDATED PROJECTED START DATE | Status |
---|---|---|---|---|
Evergreen Jr. High | Remodel | 2018 | 2018 | Completed |
Valley Jr. High | Remodel | 2018 | 2018 | Completed |
Roosevelt (Olene Walker Elementary) | Rebuild | 2018 | 2019 | Completed |
South Kearns | Rebuild | 2018 | 2019 | Completed |
Hunter High School | Addition | 2018 | 2019 | Completed |
Howard Driggs Elementary | Remodel | 2019 | 2019 | Completed |
Rosecrest Elementary | Remodel | 2019 | 2019 | Completed |
Cyprus High School | Rebuild | 2020 | 2020 | Under construction |
Skyline High School | Rebuild | 2020 | 2020 | Under construction |
West Kearns Elementary | Rebuild | 2019 | 2027 | |
Calvin Smith Elementary | Remodel | 2021 | 2028 | |
Moss Elementary | Remodel | 2021 | 2028 | |
Plymouth Elementary | Remodel | 2021 | 2028 | |
Taylorsville High School | Addition | 2022 | 2028 | |
Arcadia | Rebuild | 2022 | 2029 | |
Hillsdale Elementary | Remodel | 2023 | 2029 | |
Kennedy Jr. High | Remodel | 2023 | 2029 | |
Orchard Elementary | Rebuild | 2023 | 2031 | |
Magna Elementary | Remodel | 2024 | 2032 | |
Valley Crest Elementary | Remodel | 2024 | 2032 | |
Kearns Jr. High | Rebuild | 2024 | 2033 | |
Sandburg Elementary | Rebuild | 2025 | 2033 | Closed - 2019 |
Lincoln Elementary | Remodel | 2025 | 2033 | |
Pioneer Elementary | Remodel | 2025 | 2033 | |
Academy Park Elementary | Rebuild | 2024 | 2034 | |
Crestview Elementary | Remodel | 2026 | 2034 | |
Eastwood Elementary | Rebuild | 2026 | 2035 | |
Cottonwood Elementary | Remodel | 2027 | 2035 | |
Spring Lane Elementary | Rebuild | 2027 | 2036 | Closed - 2023 |
Valley Jr. High | Rebuild | 2028 | 2036 | |
Evergreen Jr. High | Rebuild | 2028 | 2037 | |
Oakridge Elementary | Rebuild | 2028 | 2037 |
Cyprus High School
Skyline High School
Construction has commenced on the new Cyprus High School, and the Magna community and Granite School District are celebrating this momentous step in the school’s 100+ year history.
Cyprus students joined Granite board members, local elected officials, alumni, and community members at the school’s new site (8400 W. 4000 South) to ceremonially turn the dirt that will eventually serve as a foundation for the Home of Pirates.
West Lake Family & Consumer Sciences Building
The project is complete and backordered furniture is being shipped as available. This modular building is located on the temporary West Lake campus (formerly Westbrook Elementary).
Taylorsville High School Relocatable Classroom Complex
The project is complete and backordered furniture is shipping. This complex is located on the eastern portion of the campus to accommodate the added students from grade reconfiguration. It features 16 classrooms as well as restrooms. It has colloquially been dubbed ‘The Villa’ by students.