West Lake STEM Junior High School
Building Construction
Gymnasium roof trusses and 90% of roof decking is in place.
Locker room masonry walls 90% complete.
Kitchen and mechanical rooms masonry walls 50% complete.
Southwest academic wing framing is complete, exterior sheathing is 75% first floor utilities are 50% complete.
Southeast academic wing second floor decking and teacher hub/commons area concrete slab ready to be placed.