Cyprus High School
Skyline High School
West Lake STEM Junior High
Cottonwood High Auditorium Control Booth
Granite Technical Institute Third Floor Labs
Security Upgrades
Turf Fields
Cyprus High School
Skyline High School
West Lake STEM Junior High
Cottonwood High Auditorium Control Booth
Granite Technical Institute Third Floor Labs
Security Upgrades
Turf Fields
West Lake STEM Junior High School
Building Construction
Parking lot is being prepped to move cars off the street.
Perimeter footings are 95% complete and interior footings are 85% complete.
Approximately 26,000 sq ft of slab on grade has been placed.
Structural steel on south-west classroom wing being erected.
Skyline High School
Athletics Complex
Owner training is ongoing for all systems.
Turf field to be turned over on July 25, the school can start using August 1.
Grading continues at softball field, grass field, tennis courts, and west fence line.
Sod for softball field expected in September.
Bleacher installation is ongoing.
Granite security, AV, and IT installations are ongoing.
Old pool building demolition is complete.
Track installation is complete.
Cyprus High School
Building Construction
Retaining wall work continues.
Geothermal drilling continues.
Auditorium tilt walls are being framed with structural steel.
Gymnasium and pool walls have been poured and will be stood into place by the first of August.
West Lake STEM Junior High School Building Construction
Perimeter footings and foundations are 75% complete.
Approximately 20,000 sq. ft. of slab has been placed.
More gymnasium tilt panels have been formed and poured
Pool foundation walls have been poured. Others are being formed
Auditorium foundation radius wall and orchestra pit back wall have been poured
Kitchen main underground electrical being installed for transformers and generators.
All crane paths have been installed.
Cyprus High School
Skyline High School
West Lake STEM Junior High
West Lake STEM Junior High School Building Construction
Continued placement of footings and foundations which are 40% complete.
Utilities, including plumbing drain lines, are 10% complete.
Electrical floor outlet installation is 10% complete.
Site storm drain is complete.
Fire and water lines have been tied into the existing Granger/Hunter Water Improvement District lines in the street.
Skyline High School
Athletics Complex & Academics Building
Mechanical, electrical, and plumbing continues throughout athletics building.
Pool equipment is energized and circulating water.
Flooring ongoing throughout athletics building.
Base is being placed at artificial turf field.
West concrete panel fencing is 85% complete.
Chain link fencing is ongoing at north property line.
Academics underground mechanical, electrical, and plumbing is being installed.
Salt Lake City Public Utilities water main is being sanitized for testing.
Softball backstop footings and fencing is underway.