Cyprus High School
Building Construction
Auditorium steel trusses, cross bracing and the catwalk are all being installed.
More auditorium tilt panels being prepped to be placed.
Gymnasium steel decking is done around the running track and ½ the concrete has been placed for the track.
Gymnasium floor is being prepped for concrete.
The cardio & wrestling room is being framed, along with HVAC and rough electrical being installed.