Cyprus
Status of Projects January 2024 – Cyprus High School
Updates:
Site Work:
● Fencing and flat work on the North side of the site
Athletics:
● Drops ceiling grid level 1 of athletics
Pool:
●Locker room framing, drywall and plumbing
●Tile in the lifeguard room
Mechanical Yard:
● Tilt walls stood in place
● Steel erection
CTE Buildings:
● Steel stud and metal decking on the breezeway
Academics:
● Paint and drywall 2nd and 3rd levels
● Exterior kiln walls stood into place
● Testing center cement poured
Social Studies:
● Curtain wall glass installation
● Drywall and insulation 2ndand 3rdfloor
Performing Arts:
● Vestibule curtain wall installation
● Concrete pour backs in the vestibule area
Recent Photos:
Status of Projects December 2023 – Cyprus High School
Updates:
Site Work:
● Asphalt paving Southwest parking lot
Athletics:
● Drop ceiling grid, light installation level 1
● 2ndlevel bathroom tile
Pool:
●Locker room framing, drywall and plumbing
●Acid etched glass installed
CTE Buildings:
● Tilt panels connecting CTE building with the main building
Administration:
● Drywall 3rd and 4th floor
Cafeteria/Common Area:
● Skylight on the 3rd floor
Social Studies:
●Framing 3rd and 4th floor
●Rough electrical 3rd and 4th floor
●Air handler set on the 4th floor
Performing Arts:
● Fin tube heaters set into place
● Dressing room framing
Recent Photos:
Status of Projects November 2023 – Cyprus High School
Updates:
Site Work:
● Asphalt paved on the North end of the site
● Asphalt prep for the Southwest parking lot
● Outbuildings concrete floors poured
Athletics:
● Basketball standards installed
● Tile in the PE locker rooms
Pool:
● Locker room framing and plumbing
CTE Buildings:
● Tilt panels stood into place
Administration:
● Framing drywall throughout classroom spaces
Social Studies:
● Exterior glass installed
● Exterior framing
Cafeteria/Common Area:
● Level 3 concrete floor poured
● Exterior framing
Performing Arts:
● HVAC in corridors and Scenery/shop storage
● Glass installation in the Choral and Band room
Recent Photos:
Status of Projects October 2023 – Cyprus High School
Updates:
Site Work:
● Curbing and asphalt prep at the North end of the site
● Football stadium footings have been poured
● Light poles have been installed throughout the North end of the site
Athletics:
● Tile and waterproofing on-going in the PE Locker rooms
● Glass installation in the vestibule
● Glass installation in the Weight room
● Paint in the Dance room
Pool:
● Gallery seating has been poured on the observation deck
● Concrete floors in the locker room area
Administration:
● Steel erection
Academics:
● Framing, electrical rough in throughout classroom spaces
● Cement floors on levels 2,3 and 4.
● Steel stud erection and metal decking
Performing Arts:
● Projector booth concrete has been poured
● Orchestra steps have been formed and poured
Recent Photos:
observation deck of the pool
Status of Projects September 2023 – Cyprus High School
Updates:
Site Work:
- Ongoing site grading is in progress
- Football stadium storage tilt panels raised into position
- Light pole bases have been installed on the north side of the site
Athletics:
- Tile and waterproofing in the public restrooms and coaches’ office ongoing
- PE Locker rooms’ ceiling and paint have been completed
- Curtain walls for the vestibule and wrestling room installed
- Drywall installation is ongoing in the dance room
- Wrestling room benches have been completed
Pool:
- Seating structures have been formed, and cement pouring by sections
Academics:
- Stairs going from athletics to academics and 3rd to 4th floor
- Framing/HVAC on the fourth floor is ongoing
- Steel erection and metal decking are ongoing in the testing center
Performing Arts:
- Framing for the projector room is ongoing
- Scaffolding set in the auditorium for finishes to start
- Concrete poured on the third level of the upper lobby in the auditorium
Recent Photos:
Status of Projects May 2023 – Cyprus High School
Panels leading to the auditorium continue to be tilted into place.
Trusses have been set in place above the drama studio/black box theater.
Mezzanine on the third floor has been placed, additional cat walks and storage areas have been fabricated. Stairs have been fabricated between the third and fourth floor mezzanine.
Air handlers have also been placed on the third floor. Underground utilities have been laid out to be buried and have utilities run through them. Cast in place concrete walls are being formed.
Panels and steel decking for the academics area is being tilted and secured in place. Decking has been completed on the second and third floor. Fabricators are working on the roof of the academics building.
Framing for ceiling hard lid has been fabricated in the basement of the gymnasium. Insulation is currently being installed in the basement and second level of the track and gymnasium area. Exhaust fan plumbing has been installed in the team rooms and bathrooms. Air exchanger has been installed and HVAC continues to be installed in the basement. Roof drains have been installed in the gymnasium and in the pool area.
Cyprus C has been formed and is curing.
Panels being placed leading up to the auditorium and the trusses being placed over the drama theater.
Panels being placed leading up to the auditorium and the trusses being placed over the drama theater.
Concrete on the third-floor mezzanine and stairs leading from the third to fourth floor mezzanine.
Concrete on the third-floor mezzanine and stairs leading from the third to fourth floor mezzanine.
Status of Projects April 2023 – Cyprus High School
Cyprus High School
Building Construction
Kitchen panels have been erected creating a corridor between athletics and academics. A lecture hall and mechanical room will come off either side of the corridor and the lecture hall will be the next panel erected.
Auditorium – three of the walls have been raised and braced so that heavy equipment can come and go from the area. Steel decking has been installed on the upper levels creating walkable areas.Concrete has been placed on the stage and the landing leading up to the stage. Concrete is currently curing and is covered by tarps.Dressing area/storage has been raised and braced. This area will serve as storage of the performing arts.
Academics structure has been installed and two tilt panels have been raised around the structure. A double decker air handler system will be installed to service the area. Remaining tilt panels are curing, these will be installed on the north side of the structure. Elevator shaft has been erected and braced. This is the only elevator shaft that is tilt up on three sides in the building. This will service all three floors for academics.
Drywall in the basement of gymnasium has progressed to 90%. Masonry work has been completed in the basement of athletics. Copper and steel weld piping have been placed and have passed inspections. Window frames have been installed in athletics. Glass has been ordered and will be installed in the next couple of weeks.
Panels in academics and the elevator shaft.
Auditorium walls and concrete placed on the stage.
Auditorium walls and concrete placed on the stage.
Steel decking and raised walls for dressing area.
Steel decking and raised walls for dressing area.
Structure for academics and remaining tilt panels.
Structure for academics and remaining tilt panels.
Drywall in the team rooms and window frames in athletics.
Drywall in the team rooms and window frames in athletics.
Masonry walls and the copper piping.
Masonry walls and the copper piping.
Panels in academics and the elevator shaft.
Status of Projects March 2023 – Cyprus High School
Cyprus High School
Building Construction
Auditorium roofing, steel in ceilings and back of house 2nd and 3rd floor continues.
Gymnasium and locker rooms have drywall being installed on one side of metal studs.
Electrical, fire sprinkler/alarm and plumbing continues in the locker rooms and gymnasium.
Gymnasium masonry on stairway walls and under the dance room as well as moving up to pool loft and locker rooms.
Pool roof decking installed, and roofing started. Observation upper deck installed.
Tilt walls for choral and band area have been stood. Steel moving to choral area soon.
Status of Projects February 2023 – Cyprus High School
Cyprus High School
Building Construction
Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.