• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Cyprus

Status of Projects March 2024 – Cyprus High School

March 2024

Updates:

Site Work/Mechanical Yard:
●Footings/foundation at the Softball, Baseball Field
●Setting the generators into place

Athletics/Pool:
●Track Handrail Shoe
●Locker being placed in the PE Locker Rooms
●Pool painting
●Window caulking

Administration/Commons:
●Level 3 framing
●Level 1 slab on grade pour
●Prepping slab on grade in the Public Square/Dining

Academics/Social Studies:
●Framing of classrooms and display cases
●Drywall around the skylights
●Frames and glazing on the stair tower
●Finish paint on Levels 2 and 3

Performing Arts:
●Curtain wall and glazing around the Lobby

Recent Photos:

Softball Field footings/foundation
Softball Field footings/foundation
Setting the generators into place
Setting the generators into place
Track handrail shoe
Track handrail shoe
Lockers being placed in the PE Locker Room
Lockers being placed in the PE Locker Room
Pool painting and window caulking
Pool painting and window caulking
Framing on Level 3 of the Administration Building
Framing on Level 3 of the Administration Building
Framing of classrooms and display cases in the
Academics Building
Framing of classrooms and display cases in the
Academics Building
Drywall around the skylights in
the Academics Building
Drywall around the skylights in
the Academics Building
Frames and glazing, Social Studies
Frames and glazing, Social Studies
Paint on Level 2 of the Social Studies wing
Paint on Level 2 of the Social Studies wing
Curtain wall and glazing around the Auditorium Lobby
Curtain wall and glazing around the Auditorium Lobby

Filed Under: Cyprus

Status of Projects February 2024 – Cyprus High School

February 2024

Updates:

Site Work:
●Planter boxes behind the home side bleachers and between   Athletics and Administrative Suite
●Fencing fabric stretched between posts
●Visitor side bleachers under construction

Athletics:
● Tile in the restrooms

Pool:
●Painting

Mechanical Yard:
● Slab on grade
● Set steel

Administration:
● Slab under electric

Academics:
● Paint on 2nd and 3rd levels
● Skylights in corridor

Social Studies:
● Rough Plumbing on levels 2 and 3
● Painting accent walls and classrooms

Performing Arts:
● Painting on the stage and scenery storage
● Ceiling grid in the Band room

Recent Photos:

Planter boxes behind the home side bleachers
Planter boxes behind the home side bleachers
Planter boxes between Athletics and
Administrative Suite
Planter boxes between Athletics and
Administrative Suite
Site fencing
Site fencing
Visitor side bleachers in stadium
Visitor side bleachers in stadium
Restroom tile, Athletic building level 1
Restroom tile, Athletic building level 1
Painting in the Pool
Painting in the Pool
Slab on grade and steel setting Mechanical yard
Slab on grade and steel setting Mechanical yard
Under slab electrical in the Administrative suite
Under slab electrical in the Administrative suite
Painting in a Science classroom
Painting in a Science classroom
Skylights installed in the Academic building
Skylights installed in the Academic building
Rough plumbing level 2
Rough plumbing level 2
Painting and accents level 2
Painting and accents level 2
Painting in the scenery room of the Auditorium
Painting in the scenery room of the Auditorium
Band Room ceiling grid, Performing Arts building
Band Room ceiling grid, Performing Arts building

Filed Under: Cyprus

Cyprus High Construction Update Video

January 2024

Filed Under: Cyprus, Project Updates

Status of Projects January 2024 – Cyprus High School

January 2024

Updates:

Site Work:
● Fencing and flat work on the North side of the site

Athletics:
● Drops ceiling grid level 1 of athletics

Pool:
●Locker room framing, drywall and plumbing
●Tile in the lifeguard room

Mechanical Yard:
● Tilt walls stood in place
● Steel erection

CTE Buildings:
● Steel stud and metal decking on the breezeway

Academics:
● Paint and drywall 2nd and 3rd levels
● Exterior kiln walls stood into place
● Testing center cement poured

Social Studies:
● Curtain wall glass installation
● Drywall and insulation 2ndand 3rdfloor

Performing Arts:
● Vestibule curtain wall installation
● Concrete pour backs in the vestibule area

Recent Photos:

Fencing and flat work on the north side of the site
Drops ceiling grid level 1 of athletics
Locker room framing, drywall, and plumbing
Tile in the lifeguard room
Mechanical yard tilt walls stood in place, steel erection
Steel stud and metal decking on the breezeway
Paint and drywall 2nd and 3rd levels
Exterior kiln walls stood into place
Testing center cement poured
Curtain wall glass installation
Drywall and insulation 2nd and 3rd floor
Vestibule curtain wall installation
Concrete pour backs in the vestibule area

Filed Under: Cyprus

Status of Projects December 2023 – Cyprus High School

December 2023

Updates:

Site Work:
● Asphalt paving Southwest parking lot

Athletics:
● Drop ceiling grid, light installation level 1
● 2ndlevel bathroom tile

Pool:
●Locker room framing, drywall and plumbing
●Acid etched glass installed

CTE Buildings:
● Tilt panels connecting CTE building with the main building 

Administration:
● Drywall 3rd and 4th floor

Cafeteria/Common Area:
● Skylight on the 3rd floor

Social Studies:
●Framing 3rd and 4th floor
●Rough electrical 3rd and 4th floor
●Air handler set on the 4th floor

Performing Arts:
● Fin tube heaters set into place
● Dressing room framing

Recent Photos:

Asphalt Southeast Parking lot
Drop ceiling grid
1st level restroom in athletics
Framing, drywall and plumbing in the locker room
Drywall 2nd and 3rd floor academics
Framing/electrical rough in Social Studies 3rd floor
Social studies, 3rdfloor air handler
Fin tube heaters laid out in the auditorium
Dressing room framing in the auditorium

Filed Under: Cyprus

Status of Projects November 2023 – Cyprus High School

November 2023

Updates:

Site Work:
● Asphalt paved on the North end of the site
● Asphalt prep for the Southwest parking lot
● Outbuildings concrete floors poured

Athletics:
● Basketball standards installed
● Tile in the PE locker rooms

Pool:
● Locker room framing and plumbing

CTE Buildings:
● Tilt panels stood into place  

Administration:
● Framing drywall throughout classroom spaces

Social Studies:
● Exterior glass installed
● Exterior framing

Cafeteria/Common Area:
● Level 3 concrete floor poured
● Exterior framing

Performing Arts:
● HVAC in corridors and Scenery/shop storage
● Glass installation in the Choral and Band room

Recent Photos:

Parking lot on the North end of the site
Concrete floors in the outbuildings
Parking lot prep Southeast parking lot
Basketball standards installed
Tile in the PE locker room
Framing in the Pool locker room
CTE Buildings tilted into place
Framing/Drywall in the Classroom spaces 
 Social studies glass installation 
Social studies exterior framing
Commons/Cafeteria Concrete floors level 3 
Commons/Cafeteria learning stairs
Scenery/Storage HVAC 
Band/Orchestra glass installation

Filed Under: Cyprus

Status of Projects October 2023 – Cyprus High School

October 2023

Updates:

Site Work:
● Curbing and asphalt prep at the North end of the site
● Football stadium footings have been poured
● Light poles have been installed throughout the North end of the site

Athletics:
● Tile and waterproofing on-going in the PE Locker rooms
● Glass installation in the vestibule
● Glass installation in the Weight room
● Paint in the Dance room

Pool:
● Gallery seating has been poured on the observation deck
● Concrete floors in the locker room area

Administration:
● Steel erection


Academics:
● Framing, electrical rough in throughout classroom spaces
● Cement floors on levels 2,3 and 4.
● Steel stud erection and metal decking

Performing Arts:
● Projector booth concrete has been poured
● Orchestra steps have been formed and poured

Recent Photos:

Site curbing, light posts and road base
Site curbing, light posts and road base
Football stadium footers
Waterproofing and tile in the PE locker rooms of athletics
Seating on the
observation deck of the pool
Concrete floor in the pool locker room
Steel stud erection in the administrative area
Framing and electrical rough in academics
Seats formed and poured on the observation deck of the pool
Steel stud erection and metal decking cafeteria/commons
Aerial photos of Cyprus High School
Aerial photos of Cyprus High School

Filed Under: Cyprus

Status of Projects September 2023 – Cyprus High School

September 2023

Updates:

Site Work:

  • Ongoing site grading is in progress
  • Football stadium storage tilt panels raised into position
  • Light pole bases have been installed on the north side of the site

Athletics:

  • Tile and waterproofing in the public restrooms and coaches’ office ongoing
  • PE Locker rooms’ ceiling and paint have been completed
  • Curtain walls for the vestibule and wrestling room installed
  • Drywall installation is ongoing in the dance room
  • Wrestling room benches have been completed

Pool:

  • Seating structures have been formed, and cement pouring by sections

Academics:

  • Stairs going from athletics to academics and 3rd to 4th floor
  • Framing/HVAC on the fourth floor is ongoing
  • Steel erection and metal decking are ongoing in the testing center

Performing Arts:

  • Framing for the projector room is ongoing
  • Scaffolding set in the auditorium for finishes to start
  • Concrete poured on the third level of the upper lobby in the auditorium

Recent Photos:

Site work ongoing
Football stadium storage raised into position
Light pole bases on site
Waterproofing and tile in public restroom in athletics 
Ceiling and paint in the PE locker rooms
Patch and paint throughout athletics
Glass frames for the vestibule and weight room
Glass frames for the vestibule and weight room
Stairs from athletics to academics
Gallery seating formed and being poured in sections
Wrestling room benches
Drywall in the dance room

Filed Under: Cyprus

Status of Projects May 2023 – Cyprus High School

May 2023

Panels leading to the auditorium continue to be tilted into place.

Trusses have been set in place above the drama studio/black box theater.

Mezzanine on the third floor has been placed, additional cat walks and storage areas have been fabricated. Stairs have been fabricated between the third and fourth floor mezzanine.

Air handlers have also been placed on the third floor. Underground utilities have been laid out to be buried and have utilities run through them. Cast in place concrete walls are being formed.

Panels and steel decking for the academics area is being tilted and secured in place. Decking has been completed on the second and third floor. Fabricators are working on the roof of the academics building.

Framing for ceiling hard lid has been fabricated in the basement of the gymnasium. Insulation is currently being installed in the basement and second level of the track and gymnasium area. Exhaust fan plumbing has been installed in the team rooms and bathrooms. Air exchanger has been installed and HVAC continues to be installed in the basement. Roof drains have been installed in the gymnasium and in the pool area.

Cyprus C has been formed and is curing.




Panels being placed leading up to the auditorium and the trusses being placed over the drama theater.



Panels being placed leading up to the auditorium and the trusses being placed over the drama theater.



Concrete on the third-floor mezzanine and stairs leading from the third to fourth floor mezzanine.



Concrete on the third-floor mezzanine and stairs leading from the third to fourth floor mezzanine.
Air handlers being placed on the third floor of the auditorium.
Air handlers being placed on the third floor of the auditorium.
Catwalks in the auditorium and underground utilities being placed. 
Catwalk in the corridor of the auditorium. Cast in place concrete walls in the auditorium .
Catwalk in the corridor of the auditorium. Cast in place concrete walls in the auditorium .
Steel decking in the academic’s area. Roof of academics building being installed. 
Steel decking in the academic’s area. Roof of academics building being installed. 
Insulation and hard lid ceiling being installed in the basement of the gymnasium.
Insulation and hard lid ceiling being installed in the basement of the gymnasium.
Exhaust fans in the restrooms and team rooms. Industrial air exchanger in the basement of the gymnasium.  
Exhaust fans in the restrooms and team rooms. Industrial air exchanger in the basement of the gymnasium.  
Roof drains in the gymnasium and pool area.
The Cyprus “C”that is going on the outside of the drama studio.

Filed Under: Cyprus

Status of Projects April 2023 – Cyprus High School

April 2023

Cyprus High School
Building Construction

Kitchen panels have been erected creating a corridor between athletics and academics. A lecture hall and mechanical room will come off either side of the corridor and the lecture hall will be the next panel erected.

Auditorium – three of the walls have been raised and braced so that heavy equipment can come and go from the area. Steel decking has been installed on the upper levels creating walkable areas.Concrete has been placed on the stage and the landing leading up to the stage. Concrete is currently curing and is covered by tarps.Dressing area/storage has been raised and braced. This area will serve as storage of the performing arts.

Academics structure has been installed and two tilt panels have been raised around the structure. A double decker air handler system will be installed to service the area. Remaining tilt panels are curing, these will be installed on the north side of the structure. Elevator shaft has been erected and braced. This is the only elevator shaft that is tilt up on three sides in the building. This will service all three floors for academics.

Drywall in the basement of gymnasium has progressed to 90%. Masonry work has been completed in the basement of athletics. Copper and steel weld piping have been placed and have passed inspections. Window frames have been installed in athletics. Glass has been ordered and will be installed in the next couple of weeks.




Panels in academics and the elevator shaft.



Auditorium walls and concrete placed on the stage.



Auditorium walls and concrete placed on the stage.



Steel decking and raised walls for dressing area.



Steel decking and raised walls for dressing area.



Structure for academics and remaining tilt panels.



Structure for academics and remaining tilt panels.



Drywall in the team rooms and window frames in athletics.



Drywall in the team rooms and window frames in athletics.



Masonry walls and the copper piping.



Masonry walls and the copper piping.



Panels in academics and the elevator shaft.

Filed Under: Cyprus, Project Updates

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Interim pages omitted …
  • Page 6
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2025 Granite School District

 

Loading Comments...