Cyprus High School





Skyline High School





West Lake STEM Junior High





Cyprus High School
Skyline High School
West Lake STEM Junior High
Cyprus High School
Building Construction
Tilt panels for gymnasium have been cast in concrete.
Pool foundation walls are complete.
Other foundation walls are being formed now and waiting for reinforcing steel.
Auditorium and stage walls have been formed, scheduled to pour 6/6/22
Underground electrical in kitchen area is being installed for transformers and generators.
All casting slabs for tilt walls are in place.
Crane and crane paths are in place, in preparation for standing tilt walls which is expected to begin late June.
Cyprus High School Building Construction
Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.
Cyprus High School
Building Construction
Gymnasium slab on grade is being poured for locker rooms, wrestling room, coaches’ offices, along with PE locker rooms.
Framing up tilt walls, prepping for rebar and electrical construction. Tilt walls concrete pouring to begin 04/11/22.
Pool footing has been installed, excavated and filled in with structural fill dirt and made into a crane path for tilt panels.
Geo Energy drilling will be ongoing for the next year.
Building footings have been installed, underground plumbing and electrical installation areongoing.
Retaining walls are currently being installed along Cordero Drive.
Cyprus High School Building Construction
Excavating orchestra pit.
Placing footings for automotive shops and kitchen areas.
Installing retaining wall along Cordero Drive.
Several casting slabs placed.
Framing tilt walls for athletics.
Installing drainage for southeast portion of lot.
Continuing with underground plumbing and electrical.
Cyprus High School: Building Construction
Continuing underground plumbing and underground electrical.
Concrete footings continue to be poured.
Casting slabs have been placed so precast walls can be formed and poured.
Drilling of heat source wells has begun.
Cyprus footing / foundation & underground utility construction