GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

May 2022 Construction Photos

May, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Aerial photo of Skyline High School
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site
Skyline High School construction site

West Lake STEM Jr High

West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site
West Lake Jr High construction site

Filed Under: Cyprus, Skyline, West Lake

Status of Projects May 2022 – Cyprus

May, 2022 by Granite Schools

Cyprus High School Building Construction

Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.

Auto shop footings, hillside drainage finished
Auto shop footings, hillside drainage finished
Orchestra pit underground electrical
Orchestra pit underground electrical
Foundation walls and columns being formed up in pool area
Foundation walls and columns being formed up in pool area
View of site crane paths
View of site crane paths
Crane onsite being built
Crane onsite being built
Casting slabs, framing tilt walls, and crane paths
Casting slabs, framing tilt walls, and crane paths

Filed Under: Cyprus, Project Updates

April 2022 Construction Photos

April, 2022 by Granite School District Communications Office

Cyprus High School

Skyline High School

West Lake Jr High

Filed Under: Cyprus, Skyline, West Lake

Status of Projects April 2022 – Cyprus

April, 2022 by Granite Schools

Cyprus High School
Building Construction

Gymnasium slab on grade is being poured for locker rooms, wrestling room, coaches’ offices, along with PE locker rooms.
Framing up tilt walls, prepping for rebar and electrical construction. Tilt walls concrete pouring to begin 04/11/22.
Pool footing has been installed, excavated and filled in with structural fill dirt and made into a crane path for tilt panels.
Geo Energy drilling will be ongoing for the next year.
Building footings have been installed, underground plumbing and electrical installation areongoing.
Retaining walls are currently being installed along Cordero Drive.

Casting slabs, framing tilt walls and crane paths
Casting slabs, framing tilt walls and crane paths
Site overview
Site overview
Site overview
Site overview
Orchestra pit footings
Orchestra pit footings
Retaining wall
Retaining wall
Retaining wall
Retaining wall
Casting slabs, framing tilt walls and crane paths
Casting slabs, framing tilt walls and crane paths

Filed Under: Cyprus, Project Updates

March 2022 Construction Photos

March, 2022 by Granite School District Communications Office

Cyprus High School

Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site
Cyprus High School construction site

Skyline High School

Skyline High School construction site
Skyline High School interior construction site
Skyline High School interior construction site
Skyline High School construction site
Skyline High School interior construction site

Filed Under: Cyprus, Skyline

Status of Projects March 2022 – Cyprus

March, 2022 by Granite Schools

Cyprus High School Building Construction

Excavating orchestra pit.
Placing footings for automotive shops and kitchen areas.
Installing retaining wall along Cordero Drive.
Several casting slabs placed.
Framing tilt walls for athletics.
Installing drainage for southeast portion of lot.
Continuing with underground plumbing and electrical.

Casting slabs for tilt up wall construction
Casting slabs for tilt up wall construction
Material storage
Material storage
Material storage
Material storage
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Orchestra pit
Retaining wall
Retaining wall
Retaining wall
Retaining wall
Mockup panels for approval
Mockup panels for approval
Tilt walls framed, prepped for rebar and electrical
Tilt walls framed, prepped for rebar and electrical
Casting slabs for tilt up wall construction
Casting slabs for tilt up wall construction

Filed Under: Cyprus, Project Updates

February 2022 Construction Photos

February, 2022 by Granite School District Communications Office

Cyprus High School

Skyline High School

Oakridge Elementary Security/Elevator Remodel

Filed Under: Cyprus, Skyline

Status of Projects February 2022 – Cyprus

February, 2022 by Granite Schools

Cyprus High School: Building Construction

Continuing underground plumbing and underground electrical.
Concrete footings continue to be poured.
Casting slabs have been placed so precast walls can be formed and poured.
Drilling of heat source wells has begun.

Cyprus footing / foundation & underground utility construction

Casting slab where walls will
be formed and poured
Casting slab where walls will
be formed and poured
Construction site
Construction site
Mockup panels for review and approval
Mockup panels for review and approval
Mockup panels for review and approval
Mockup panels for review and approval
Plumbing wall of cafeteria kitchen
Plumbing wall of cafeteria kitchen
Plumbing wall of cafeteria kitchen
Plumbing wall of cafeteria kitchen

Filed Under: Cyprus, Project Updates

Status of Projects January 2022 – Cyprus

January, 2022 by Granite Schools

Cyprus High School Building Construction

Continuing underground plumbing for locker rooms and gymnasium.
Locker rooms and gymnasium rebar being installed and concrete footings being poured.

Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction

Filed Under: Cyprus, Project Updates

Status of Projects December 2021 – Cyprus

December, 2021 by Granite Schools

Cyprus High School: Builing Construction

Continuing underground plumbing for gymnasium and locker rooms.

Gymnasium and locker rooms rebar is being installed and concrete footings are being poured.

The New Cyprus High School

  • Project Timeline
    • 11/04 – Submittal List Returned to Architect with Requested Revisions Incorporated
    • 11/19 – First Pour of Concrete Footings
    • 11/22 – U/G Sewer Utility Work Started
    • 11/29 – Building Site Preparation Continues
    • 11/29 – U/G MEP Installation Continues
    • 11/29 – Geothermal Drilling Work Planned to Begin, pending materials procurement
  • Manpower Onsite
    • Snapshot from Total = Westland (4), Suntec (5), KSC (6), US Mech (8), CR Lighting (4)
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Constructionf
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction

Filed Under: Cyprus, Project Updates

  • « Previous Page
  • 1
  • 2
  • 3
  • 4
  • Next Page »
 

Loading Comments...