Cyprus High School
Building Construction
Auditorium steel trusses and cross bracing continues.
Gymnasium roofing is almost complete. Moving onto the pool and auditorium next.
Locker rooms have been framed. Electrical and plumbing are being installed.
Gymnasium floor was placed the week of January 30th.
Tilt walls framed for classrooms, coral, and band area.
![Gymnasium floor ready for concrete](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-24.png)
![Gymnasium floor ready for concrete](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-25.png)
![Framing mechanical room](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-26.png)
![Framing bathrooms](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-27.png)
![Roof steel decking](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-28.png)
![Auditorium cloud steel](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-29.png)
![Athletics framing, HVAC, fire sprinkler, plumbing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-30.png)
![Athletics framing, HVAC, fire sprinkler, plumbing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-31.png)
![Site Overview](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-23.png)