West Lake STEM Junior High School Building Construction
Continued placement of footings and foundations which are 40% complete.
Utilities, including plumbing drain lines, are 10% complete.
Electrical floor outlet installation is 10% complete.
Site storm drain is complete.
Fire and water lines have been tied into the existing Granger/Hunter Water Improvement District lines in the street.
![Insulation on interior of foundation walls](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-115-300x224.png)
![Elevator pit in athletics wing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-116-300x225.png)
![Elevator pit in commons area](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-117-300x224.png)
![Slab on grade in southwest academic wing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-118-300x225.png)
![Restroom drain lines in southwest academic wing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-119-300x225.png)
![Insulation on interior of foundation walls](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-114-300x224.png)