Skyline High School
Athletics Complex & Academics Building
New pool has been filled and is circulating water.
Existing pool was drained and is being tested for asbestos and abatement.
Boilers are operational and air handling units are providing warm air.
Gymnasium floor has been acclimating to building temperature and humidity.
Field Turf mobilized the week of 04/04/22.
Tiling at bathrooms and pool is ongoing.
Site work continues, including perimeter and athletic field fencing.