Skyline High School: Athletics Complex
Backfilling around pool in progress.
Mechanical, plumbing, and fire sprinkler work ongoing.
Permanent electrical and gas services have been connected to the athletics building.
Installation of gym equipment has begun.
Tile work is progressing.
Site work, including footing excavation on the west side of the existing academic building, is underway for the new academic wing.
Work continues at the north athletic fields.
Asbestos surveys for the existing pool and auditorium/gymnasium buildings are almost complete.