GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects November 2021 – West Lake

November, 2021 by Granite Schools

West Lake STEM J unior High School – Demolition / Site Preperation

  • The demolition of the building is done
  • Soils are being imported, compacted and site is being staged for construction.
  • Soil compaction testing is being conducted and all tests so far have passed inspection.

West Lake Demolition

West Lake Demolition
West Lake Demolition
West Lake Demolition
West Lake Demolition

West Lake STEM Junior High School – Replacement

  • Project is in design.
  • 90% plan review was held on 12//03/2021.
  • Request for Proposal has been issued fo contractors for pre-qualification.
  • Bid release 11/29/2021.
West Lake Site Plan map
West Lake Site Plan
First Floor map
First Floor
Second Floor map
Second Floor
School diagram
west lake jhs replacement diagram

Filed Under: Project Updates, West Lake

 