Updates:
- Permanent power to the site is connected. Exterior glazing is 95% complete. The two rooftop air handling units serving the Gymnasium have arrived
- In the Athletic Wing and the Kitchen, the electrical rough-in is 75% complete. The floor and wall tile are also 75% complete.
- The stage rigging in Performing Arts is being installed.
- In the CTE Wing, the mechanical, electrical, plumbing installation and the interior paint work is moving forward.
- The Academic and Administration Wings are progressing with cabinetry installation. The diffusers and grills are 85% complete.