Updates:
Academics
●Activity Stairs in the cafeteria are fully erected.
●Drywall and framing are nearing completion in the cafeteria area.
●All in-wall utilities are near completion throughout the entire building.
●Ceiling grid is being worked on in all general classrooms and is complete in the Administration Suite. ●Casework/cabinets are being installed in the lab classrooms on level 4.
●Fixed glass walls have started in the general classroom groups on level 3.
●Curtain wall glass is nearing completion on the Cafeteria.
●Testing Center is now drywalled and taped.
●Trophy shelving is being installed in the new Athletics Vestibule.
●Tile is nearing completion in the Administration bathrooms.
●Fire sprinkler systems are nearing completion on 3 floors.
●Framing in the south stair tower has started.