Updates:
- Roofing is 90% complete.
- Glass is being installed around the perimeter of the building.
- Installation of interior finishes such as tile and paint continue.
- Landscaping has begun in the area east of the school.
- Rough grading of the athletic field has been completed and the running track is paved and striped.
- Parking, bus, and fire lane paving is complete.
- Millwork, overhead doors, and ceiling grids are being installed in the classrooms.