West Lake STEM Junior High School
Building Construction
Masonry walls for band, choral, and the auditorium are 95% complete.
Masons are placing veneer brick at exterior walls in the mechanical/cafeteria wing.
Structural steel placement in the administrative area is nearly complete.Roof decking is 65% in place. Once the roof is in place, drywall installation will begin in the two south wings.
Metal stud framing, plumbing, electrical, and mechanical systems are nearly complete on the first floor in the south wings of the academic building.