GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects May 2022 – Cyprus

May, 2022 by Granite Schools

Cyprus High School Building Construction

Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.

Auto shop footings, hillside drainage finished
Auto shop footings, hillside drainage finished
Orchestra pit underground electrical
Orchestra pit underground electrical
Foundation walls and columns being formed up in pool area
Foundation walls and columns being formed up in pool area
View of site crane paths
View of site crane paths
Crane onsite being built
Crane onsite being built
Casting slabs, framing tilt walls, and crane paths
Casting slabs, framing tilt walls, and crane paths

Filed Under: Cyprus, Project Updates

 