Cyprus High School: Builing Construction
Continuing underground plumbing for gymnasium and locker rooms.
Gymnasium and locker rooms rebar is being installed and concrete footings are being poured.
The New Cyprus High School
- Project Timeline
- 11/04 – Submittal List Returned to Architect with Requested Revisions Incorporated
- 11/19 – First Pour of Concrete Footings
- 11/22 – U/G Sewer Utility Work Started
- 11/29 – Building Site Preparation Continues
- 11/29 – U/G MEP Installation Continues
- 11/29 – Geothermal Drilling Work Planned to Begin, pending materials procurement
- Manpower Onsite
- Snapshot from Total = Westland (4), Suntec (5), KSC (6), US Mech (8), CR Lighting (4)
![Cyprus Building Gymnasium Construction](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-16-300x169.png)
![Cyprus Building Gymnasium Construction](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-17-300x168.png)
![Cyprus Building Gymnasium Construction](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-18-300x225.png)
![The New Cyprus High School - Progress Photos](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-19-300x171.png)
![The New Cyprus High School - Progress Photos](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-20-300x170.png)
![The New Cyprus High School - Lookahead Schedule](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-21-300x170.png)
![The New Cyprus High School - Lookahead Schedule](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-22-300x171.png)
![Cyprus Building Gymnasium Construction](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/12/image-15-300x169.png)