GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects October 2023 – Skyline High School

October, 2023

Updates:

Site Work:

  • West parking lot has been paved and striped
  • Retaining walls are complete

Academics:

  • Cafeteria and study hall steel is complete minus the main staircase
  • Administration suite is nearing completion with drywall
  • Roof is being completed above the cafeteria area
  • Glass is going in on the remaining openings on the east side of the building
  • Framing is nearing completion on all floors in the main building
  • Rough in-wall electrical and plumbing has started on the second and third floors, and is almost complete on the second floor
  • Canopies for the manufacturing yard and the art yard have been erected
  • The athletics vestibule is starting drywall and will be weather tight by the end of this week
View of the entire project from the northwest. The central building in the photo is the Academics phase
View of the entire project from the southeast.
Completed west parking lot with striping
Canopy over the new manufacturing yard with some of the equipment set
Glass going into the large openings on the south-east side of the Academics Building
New air handlers on level 4 getting final duct connections
Concrete stem wall that goes below the grand staircase in the cafeteria
Concessions in the Athletics Lobby.
New slab and tilt panel where Academics transitions to the Performing Arts Building
Framing progress in the Ceramics Lab on Level 2
Typical drywall progress on levels 3 and 4 in the General Classrooms
Main Entrance and New Athletic Entrance