Updates:
Site Work:
● Curbing and asphalt prep at the North end of the site
● Football stadium footings have been poured
● Light poles have been installed throughout the North end of the site
Athletics:
● Tile and waterproofing on-going in the PE Locker rooms
● Glass installation in the vestibule
● Glass installation in the Weight room
● Paint in the Dance room
Pool:
● Gallery seating has been poured on the observation deck
● Concrete floors in the locker room area
Administration:
● Steel erection
Academics:
● Framing, electrical rough in throughout classroom spaces
● Cement floors on levels 2,3 and 4.
● Steel stud erection and metal decking
Performing Arts:
● Projector booth concrete has been poured
● Orchestra steps have been formed and poured